Day 38 of 46Stage 4 · Monitoring and controllingMondayMonitoring risks and reserves

The risk review

The monthly risk review. Some risks are gone, a new one has appeared, and how much contingency is left?

Stage goal: Keep the project on track and control every change.
Team
Antonia (Quality and Compliance Lead) Aya (Project Coordinator)
Stakeholders
Abigail (Finance Business Partner) Arash (Contractor Project Manager)
How the day goes
  1. 09:00Risk review with the leads, risk owners and Arash (Contractor)
  2. 11:00Contingency check with Abigail (Finance)
  3. 14:00Book the licence inspection
  4. 16:00Update the risk register with Aya (Project Coordinator)

Situation 1 of 4

09:00 · Risk review with the leads, risk owners and Arash (Contractor)
Antonia (Quality and Compliance Lead)
The ventilation risk is gone: the inspector approved the design. But the health authority now has a 6-week backlog for licence inspections.

What do you do with the register?

Review risks regularly: close those that have passed, add new ones, and act early when the response is still cheap.

Situation 2 of 4

11:00 · Contingency check with Abigail (Finance)
Abigail (Finance Business Partner)
How much contingency is left, and is it enough?

How do you check?

Track contingency like a bank balance: what's used, what's left, and whether it's enough for the risks still open.

Situation 3 of 4

16:00 · Update the risk register with Aya (Project Coordinator)
Aya (Project Coordinator)
The weekly risk review is getting boring. The same list every week. Can we drop it?

What do you do?

Keep risk reviews short and focused on change: new risks, moving triggers and the top few.

Situation 4 of 4

09:00 · Risk review with the leads, risk owners and Arash (Contractor)
Arash (Contractor Project Manager)
The recovery plan is working: we're running weekend shifts to win back the two weeks. But at weekends there's only one supervisor on site, and the crews are tired.

What does the register need?

Responses leave residual risk and can create secondary risks: record both, with owners and responses.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Monitoring risks

  • Review risks regularly: close those that have passed, add new ones, check triggers and whether responses are working.
  • Near the end of a project, new risks often appear around handover and approvals.

Where you will meet this: Monitor risks · risk review · risk audit

Common practice

Reserve analysis

  • Track contingency like a bank balance: how much is used, how much is left, and whether it covers the risks still open.
  • Unused contingency can be released when risks pass.

Where you will meet this: Reserve analysis · contingency drawdown

Common practice

Triggers

  • A trigger is an early sign that a risk is about to happen, like a supplier's backlog growing.
  • Watching triggers lets you act before the risk becomes an issue.

Where you will meet this: Risk triggers · warning signs

Concept

What's left, and what's new

  • Residual risk is what remains after a response. A secondary risk is a new risk that the response itself creates. Both go in the register with owners.
  • A workaround is an unplanned response to a problem that has already happened. Frequent workarounds mean risks were missed during planning.

Where you will meet this: Residual risk · secondary risk · workaround

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 38 complete

4 situations today.

Your responsibility todayMonitoring risks and reserves
Technique you usedRisk review, reserve analysis, triggers
Key points to remember
  • Review risks regularly: close those that have passed, add new ones, and act early when the response is still cheap.
  • Track contingency like a bank balance: what's used, what's left, and whether it's enough for the risks still open.
  • Keep risk reviews short and focused on change: new risks, moving triggers and the top few.
  • Responses leave residual risk and can create secondary risks: record both, with owners and responses.