Day 12 of 46Stage 2 · PlanningTuesdaySchedule and critical path

How long will it really take?

The purchase now completes in month 2. Can the clinic still open in month 7? Build the schedule and find out.

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Team
Aine (IT Lead) Aya (Project Coordinator)
Stakeholders
Atticus (Director of Community Health)
Documents today Project schedule
How the day goes
  1. 09:00Activities and dependencies with the leads
  2. 11:00Estimates for the building works with the leads
  3. 14:00Find the critical path with Aya (Project Coordinator)
  4. 16:00Gantt chart, then a call from Atticus (Sponsor)

Situation 1 of 3

11:00 · Estimates for the building works with the leads
Aine (IT Lead)
The building contractor's estimate for the works is 13 weeks. Shall we put 13 in the plan?

How do you estimate something this uncertain?

For uncertain work, estimate a range (best, most likely, worst). The weighted average is more realistic, and the spread shows the risk.
Worked example 1

A three-point estimate

The contractor gives three durations for the building works, in weeks.

EstimateWeeks
Best case (optimistic)10
Most likely13
Worst case (pessimistic)22
Download the data (spreadsheet file)
  1. Weighted average (PERT)(best + 4 × most likely + worst) ÷ 6 = (10 + 52 + 22) ÷ 6= 14 weeks
  2. Spread(worst − best) ÷ 6 = 12 ÷ 6= 2 weeks
  3. Rough rangeabout 14 ± 2 × 2 weeks= 10 to 18 weeks
What it means14 weeks is a more honest plan than 13, and the wide range marks the building works as the activity to watch.
What Annelise decidesThe plan uses 14 weeks; the risk register gets an entry for building overruns.
Try it yourself in a spreadsheet
PERT estimate=(B2+4*B3+B4)/6
Spread=(B4-B2)/6

Equipment delivery: best 10, most likely 14, worst 20 weeks. PERT estimate?

Show the answer

(10 + 56 + 20) ÷ 6 = 14.3 weeks.

Situation 2 of 3

14:00 · Find the critical path with Aya (Project Coordinator)
Aya (Project Coordinator)
I've listed 60 activities. Which ones actually decide the opening date?

How do you find them?

The critical path is the longest chain of dependent activities. It sets the end date; activities off the path have slack (float).
Worked example 2

Finding the critical path

Twelve activities with durations (weeks) and what must finish first. A forward pass finds the earliest dates, a backward pass the latest; the difference is the float.

Float for each activity, in weeks (0 = critical)02468A1: 00A1A2: 00A2A3: 00A3A4: 00A4A5: 44A5A6: 77A6A7: 55A7A8: 55A8A9: 00A9A10: 00A10A11: 00A11A12: 00A12
IDActivityWeeksStarts weekFinishes weekFloat (weeks)
A1Survey and design7170
A2Purchase completes1880
A3Asbestos removal39110
A4Building works1412250
A5Equipment order and delivery148214
A6Booking system setup109187
A7Hiring129205
A8Training521255
A9Equipment installation226270
A10Inspection128280
A11Licence229300
A12Opening030300
Download the data (spreadsheet file)
  1. Forward passeach activity starts when all its predecessors finish; earliest finish = start + duration= opening at the end of week 30
  2. Backward passfrom week 30 back, the latest each activity can finish without delaying the end
  3. Floatlatest start − earliest start= hiring 5, equipment order 4, booking setup 7
  4. Critical pathactivities with zero float= A1 → A2 → A3 → A4 → A9 → A10 → A11 → A12
What it meansEight activities have no float: any delay to them delays opening. Hiring can slip 5 weeks and booking setup 7 without harm.
What Annelise decidesAnnelise (Project Manager) watches the building works and licence most closely, and uses the float in hiring when people are double-booked.
Try it yourself in a spreadsheet
Earliest finish=start + duration (start = MAX of predecessors' finishes)
Float=latest start - earliest start
Gantt chartstacked bar chart: invisible bar for the start, visible bar for the duration

If building works take 16 weeks instead of 14, when does the clinic open?

Show the answer

Building works are critical, so opening moves 2 weeks, to the end of week 32.

Situation 3 of 3

16:00 · Gantt chart, then a call from Atticus (Sponsor)
Atticus (Director of Community Health)sponsor
So, can we still open in month 7?

The critical path ends in week 30, month 7, with no slack. What do you tell him?

Report a date with how confident you are and what threatens it. A date without context invites surprises.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Estimating with ranges

  • For uncertain work, ask for best, most likely and worst cases.
  • A weighted average, (best + 4 × likely + worst) ÷ 6, is more realistic than one number, and the spread shows the risk.

Where you will meet this: Three-point estimating · PERT

Concept

Dependencies and the critical path

  • Link activities by what must finish before what. The longest chain of linked activities sets the end date: that's the critical path.
  • Activities off the path have slack (float): they can slip a little without moving the end date.

Where you will meet this: Critical path method · network diagram · float

Common practice

Gantt chart

  • A bar chart of activities against time, showing when each starts and ends, how they link, and which are critical.
  • Good for communicating the plan; the logic behind it lives in the dependencies.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 12 complete

3 situations today.

Your responsibility todayBuilding a realistic schedule
Technique you usedThree-point estimating, critical path, Gantt chart
Key points to remember
  • For uncertain work, estimate a range (best, most likely, worst). The weighted average is more realistic, and the spread shows the risk.
  • The critical path is the longest chain of dependent activities. It sets the end date; activities off the path have slack (float).
  • Report a date with how confident you are and what threatens it. A date without context invites surprises.