How long will it really take?
The purchase now completes in month 2. Can the clinic still open in month 7? Build the schedule and find out.
- 09:00Activities and dependencies with the leads
- 11:00Estimates for the building works with the leads
- 14:00Find the critical path with Aya (Project Coordinator)
- 16:00Gantt chart, then a call from Atticus (Sponsor)
Situation 1 of 3
11:00 · Estimates for the building works with the leadsHow do you estimate something this uncertain?
A three-point estimate
The contractor gives three durations for the building works, in weeks.
| Estimate | Weeks |
|---|---|
| Best case (optimistic) | 10 |
| Most likely | 13 |
| Worst case (pessimistic) | 22 |
- Weighted average (PERT)
(best + 4 × most likely + worst) ÷ 6 = (10 + 52 + 22) ÷ 6= 14 weeks - Spread
(worst − best) ÷ 6 = 12 ÷ 6= 2 weeks - Rough range
about 14 ± 2 × 2 weeks= 10 to 18 weeks
Try it yourself in a spreadsheet
| PERT estimate | =(B2+4*B3+B4)/6 |
| Spread | =(B4-B2)/6 |
Equipment delivery: best 10, most likely 14, worst 20 weeks. PERT estimate?
Show the answer
(10 + 56 + 20) ÷ 6 = 14.3 weeks.
Situation 2 of 3
14:00 · Find the critical path with Aya (Project Coordinator)How do you find them?
Finding the critical path
Twelve activities with durations (weeks) and what must finish first. A forward pass finds the earliest dates, a backward pass the latest; the difference is the float.
| ID | Activity | Weeks | Starts week | Finishes week | Float (weeks) |
|---|---|---|---|---|---|
| A1 | Survey and design | 7 | 1 | 7 | 0 |
| A2 | Purchase completes | 1 | 8 | 8 | 0 |
| A3 | Asbestos removal | 3 | 9 | 11 | 0 |
| A4 | Building works | 14 | 12 | 25 | 0 |
| A5 | Equipment order and delivery | 14 | 8 | 21 | 4 |
| A6 | Booking system setup | 10 | 9 | 18 | 7 |
| A7 | Hiring | 12 | 9 | 20 | 5 |
| A8 | Training | 5 | 21 | 25 | 5 |
| A9 | Equipment installation | 2 | 26 | 27 | 0 |
| A10 | Inspection | 1 | 28 | 28 | 0 |
| A11 | Licence | 2 | 29 | 30 | 0 |
| A12 | Opening | 0 | 30 | 30 | 0 |
- Forward pass
each activity starts when all its predecessors finish; earliest finish = start + duration= opening at the end of week 30 - Backward pass
from week 30 back, the latest each activity can finish without delaying the end - Float
latest start − earliest start= hiring 5, equipment order 4, booking setup 7 - Critical path
activities with zero float= A1 → A2 → A3 → A4 → A9 → A10 → A11 → A12
Try it yourself in a spreadsheet
| Earliest finish | =start + duration (start = MAX of predecessors' finishes) |
| Float | =latest start - earliest start |
| Gantt chart | stacked bar chart: invisible bar for the start, visible bar for the duration |
If building works take 16 weeks instead of 14, when does the clinic open?
Show the answer
Building works are critical, so opening moves 2 weeks, to the end of week 32.
Situation 3 of 3
16:00 · Gantt chart, then a call from Atticus (Sponsor)The critical path ends in week 30, month 7, with no slack. What do you tell him?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Estimating with ranges
- For uncertain work, ask for best, most likely and worst cases.
- A weighted average, (best + 4 × likely + worst) ÷ 6, is more realistic than one number, and the spread shows the risk.
Where you will meet this: Three-point estimating · PERT
Dependencies and the critical path
- Link activities by what must finish before what. The longest chain of linked activities sets the end date: that's the critical path.
- Activities off the path have slack (float): they can slip a little without moving the end date.
Where you will meet this: Critical path method · network diagram · float
Gantt chart
- A bar chart of activities against time, showing when each starts and ends, how they link, and which are critical.
- Good for communicating the plan; the logic behind it lives in the dependencies.
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 12 complete
3 situations today.
- For uncertain work, estimate a range (best, most likely, worst). The weighted average is more realistic, and the spread shows the risk.
- The critical path is the longest chain of dependent activities. It sets the end date; activities off the path have slack (float).
- Report a date with how confident you are and what threatens it. A date without context invites surprises.