A request lands on your desk
The director wants a new clinic, the mayor has promised one, and nobody has checked whether it makes sense.
Stage goal: Decide whether the project is worth doing, and how.
Team
Aya (Project Coordinator)
Stakeholders
Atticus (Director of Community Health)
Techniques today Stakeholder map (power and interest)
Documents today Project mandate
How the day goes
- 09:00Meeting with Atticus (Sponsor)
- 11:00Read the project mandate with Atticus (Sponsor)
- 15:00List who to talk to first, with Aya (Project Coordinator)
Situation 1 of 3
09:00 · Meeting with Atticus (Sponsor)Atticus (Director of Community Health)sponsor
The mayor promised Riverside a clinic by next autumn. Here's my one-page request. Can you start building next week?
What do you do first?
A project starts as a request (a mandate). First understand the need and whether it's worth doing; only then plan.
Used here Project mandate
Situation 2 of 3
11:00 · Read the project mandate with Atticus (Sponsor)Atticus (Director of Community Health)sponsor
The objective is simple: build a clinic.
How do you help rewrite the objective?
Write objectives as the outcome people need, not the solution someone already has in mind.
Situation 3 of 3
15:00 · List who to talk to first, with Aya (Project Coordinator)Aya (Project Coordinator)
Who should we even talk to first? This touches health, finance, the council, residents…
What is a good first step?
Identify stakeholders early and decide how to involve each one. Late discovery is expensive.
Used here Stakeholder map (power and interest)
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Concept
A request is not a project yet
- Projects usually start with a short request from someone who wants something done.
- That request is a trigger to check whether a project is justified, and how it could be done. It is not a plan.
Where you will meet this: Project mandate (PRINCE2) · idea or project request form
Concept
Need versus solution
- Write the objective as the outcome people need (“care within 15 minutes”), not the solution someone has in mind (“build a clinic”).
- A need-based objective lets you compare options and later measure success.
Common practice
Stakeholders from day one
- Stakeholders are everyone who is affected by the project or can affect it.
- Mapping them by influence and interest helps you decide how closely to involve each group.
Where you will meet this: Stakeholder identification · stakeholder register
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 1 complete
3 situations today.
Your responsibility todayTurning a request into a decision
Technique you usedNeed-based objectives, stakeholder mapping
Key points to remember
- A project starts as a request (a mandate). First understand the need and whether it's worth doing; only then plan.
- Write objectives as the outcome people need, not the solution someone already has in mind.
- Identify stakeholders early and decide how to involve each one. Late discovery is expensive.
Techniques today Stakeholder map (power and interest)
Documents today Project mandate