Earned value
A way to measure progress objectively by comparing the work planned, the work actually done (valued at its budget) and what it actually cost.
What it is
Earned value compares three numbers at a point in time: planned value (the budgeted cost of the work planned by now), earned value (the budgeted cost of the work actually done) and actual cost (what that work really cost).
From them come two simple indices: schedule performance (EV ÷ PV) and cost performance (EV ÷ AC). Below 1 means behind schedule or over cost.
When to use it
Throughout executing, at each reporting period, on any project with a time-phased budget.
Variations
- Earned schedule expresses schedule performance in time units instead of money.
- Burn-up chart a visual cousin used in agile work.
Why it works
Comparing money spent with money planned says nothing about progress: you might have spent less because nothing happened. Earned value ties money to the work actually done.
It gives an early, objective warning, and a way to forecast the final cost while there's still time to act.
Do
- Agree the progress rules before work starts; arguments about “percent complete” ruin earned value.
- Show the trend, not just one point: three periods of falling CPI say more than one low number.
Don't
- Measuring progress by money spent.
- Guessing percent complete instead of using clear rules (for example 0/100 or 50/50 per task).
Step by step
- Make a time-phased budget Each piece of work has a budget and a planned time. Adding them up by period gives the planned value curve.
- Agree how to measure progress Use simple rules per task: 0/100 (counts only when done), 50/50 (half when started), or measured milestones. Avoid guessing percentages.
- At each reporting date, collect three numbers PV from the plan, EV from the progress rules, AC from finance.
- Calculate the indices SPI = EV ÷ PV, CPI = EV ÷ AC. Also the variances: SV = EV − PV, CV = EV − AC.
- Forecast the finish Estimate at completion: if past overruns were one-offs, AC + (budget − EV). If they'll continue, budget ÷ CPI.
- Act on it Look for causes behind low indices, report honestly, and decide on actions before the gap grows.