Monitoring and control · cheat sheet

Earned value

A way to measure progress objectively by comparing the work planned, the work actually done (valued at its budget) and what it actually cost.

Common practice
6 steps
Used by Project Manager

What it is

Earned value compares three numbers at a point in time: planned value (the budgeted cost of the work planned by now), earned value (the budgeted cost of the work actually done) and actual cost (what that work really cost).

From them come two simple indices: schedule performance (EV ÷ PV) and cost performance (EV ÷ AC). Below 1 means behind schedule or over cost.

When to use it

Throughout executing, at each reporting period, on any project with a time-phased budget.

Variations

  • Earned schedule expresses schedule performance in time units instead of money.
  • Burn-up chart a visual cousin used in agile work.

Why it works

Comparing money spent with money planned says nothing about progress: you might have spent less because nothing happened. Earned value ties money to the work actually done.

It gives an early, objective warning, and a way to forecast the final cost while there's still time to act.

Do

  • Agree the progress rules before work starts; arguments about “percent complete” ruin earned value.
  • Show the trend, not just one point: three periods of falling CPI say more than one low number.

Don't

  • Measuring progress by money spent.
  • Guessing percent complete instead of using clear rules (for example 0/100 or 50/50 per task).

Step by step

  1. Make a time-phased budget Each piece of work has a budget and a planned time. Adding them up by period gives the planned value curve.
  2. Agree how to measure progress Use simple rules per task: 0/100 (counts only when done), 50/50 (half when started), or measured milestones. Avoid guessing percentages.
  3. At each reporting date, collect three numbers PV from the plan, EV from the progress rules, AC from finance.
  4. Calculate the indices SPI = EV ÷ PV, CPI = EV ÷ AC. Also the variances: SV = EV − PV, CV = EV − AC.
  5. Forecast the finish Estimate at completion: if past overruns were one-offs, AC + (budget − EV). If they'll continue, budget ÷ CPI.
  6. Act on it Look for causes behind low indices, report honestly, and decide on actions before the gap grows.
Also called: EVM, planned value, earned value, actual cost, SPI, CPI, EACPrint the blank template ↗

Worked example

The situation. A website rebuild with a budget of €200,000 over 10 weeks. At week 5:

  1. Planned value: €100,000 of work should be done.
  2. Earned value: the finished pages were budgeted at €80,000.
  3. Actual cost: €90,000 has been spent.
  4. SPI = 0.8 (behind), CPI ≈ 0.89 (over cost). If this continues, the final cost is about €225,000.

The result. The sponsor saw the problem at week 5, not week 10, and agreed to drop two low-value pages to stay within budget.

Earned value tracker Print blank
DatePlanned valueEarned valueActual costSPI (EV÷PV)CPI (EV÷AC)
Week 5100,00080,00090,0000.800.89

Filled in for: A website rebuild with a budget of €200,000 over 10 weeks. At week 5:

DatePlanned valueEarned valueActual costSPI (EV÷PV)CPI (EV÷AC)

Copy this structure, or print the blank version and fill it in by hand.

Before you use it: check these

CheckIf it fails
Earned value measured by agreed rules (for example 0/50/100% per task)Agree the rules first; guessed percentages make SPI and CPI meaningless
Planned value from an approved baselineRe-baseline only through change control, and say so in the report
Actual costs for the same work and periodAccrue costs for work done but not yet invoiced

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

The spending profile and S-curve

From Day 14: What will it cost? of the Project Manager story

The baseline spread month by month from the schedule (€ thousands).

Cumulative planned spend: the S-curve, € thousands01,2502,5003,7505,000M1: 150150M1M2: 500500M2M3: 1,4001,400M3M4: 2,4002,400M4M5: 3,3003,300M5M6: 3,9003,900M6M7: 4,2004,200M7

Step by step

  1. Monthly spendfrom the schedule: when each item's work happens
  2. Cumulativeadd each month to the total so far= S-shaped
  3. Peakmonths 3 to 5, during building works= €2.8M in three months
  4. Planned value latercumulative at month 4= €2,400k
MonthSpendCumulative
M1150150
M2350500
M39001400
M410002400
M59003300
M66003900
M73004200

How to read the result

Spending is slow at first, steep in months 3 to 5, then flat. The cumulative figure is the planned value used later for earned value.

What it led to

Abigail (Finance) times the council's quarterly payments to the peak.

Do it in a spreadsheet

Cumulative=C1+B2
Chartline or column chart of column C
Try it yourself: What is the planned value at the end of month 5?

€3,300k.

Worked example with real data

Earned value at month 4

From Day 32: Are we on track? of the Project Manager story

Planned value from the S-curve, earned value from work actually done, actual cost from finance (€ thousands). Budget at completion €4,050k.

Planned value, earned value and actual cost, € thousands06251,2501,8752,500PV: 2,4002,400PVEV: 2,2002,200EVAC: 2,2502,250AC

Step by step

  1. Schedule varianceEV − PV = 2,200 − 2,400= −200: behind
  2. Cost varianceEV − AC = 2,200 − 2,250= −50: slightly over
  3. Schedule performance indexEV ÷ PV= 0.92
  4. Cost performance indexEV ÷ AC= 0.98
  5. Forecast if efficiency continuesbudget ÷ CPI = 4,050 ÷ 0.978= about €4,142k
MeasureValue (€k)
Planned value (PV)2400
Earned value (EV)2200
Actual cost (AC)2250

How to read the result

The project has done less than planned (92%) and each euro buys 98 cents of planned work. Spending less than planned did not mean being under budget.

What it led to

Status amber for time with a recovery plan; cost green, forecast inside the €4.2M baseline.

Do it in a spreadsheet

SPI=B3/B2
CPI=B3/B4
Forecast=4050/(B3/B4)
Try it yourself: What CPI would the rest of the work need to finish on the €4,050k budget?

(4,050 − 2,200) ÷ (4,050 − 2,250) = 1.03: harder than today's 0.98.

Worked example with real data

Estimate at completion

From Day 34: Out of tolerance of the Project Manager story

Two ways to forecast the final cost, from the month 4 figures (€ thousands): budget 4,050, EV 2,200, AC 2,250, CPI 0.978, SPI 0.917.

Estimate at completion by method, € thousands01,2502,5003,7505,000One-off: 4,1004,100One-offCPI: 4,1424,142CPICPI × SPI: 4,3144,314CPI × SPI

Step by step

  1. One-off2,250 + (4,050 − 2,200)= 4,100
  2. Continuing4,050 ÷ 0.978= 4,142
  3. Pessimistic2,250 + 1,850 ÷ (0.978 × 0.917)= 4,314
  4. Against the baselinebaseline 4,200 (work 4,050 + contingency 150)= first two inside, third outside
MethodCalculationEstimate at completion (€k)
Overrun was a one-offAC + (BAC − EV)4100
Efficiency continuesBAC ÷ CPI4142
Cost and schedule pressure continueAC + (BAC − EV) ÷ (CPI × SPI)4314

How to read the result

Cost stays inside tolerance unless both cost and schedule pressure continue. Time is what has broken tolerance.

What it led to

The exception report covers time; the cost forecast is watched monthly.

Do it in a spreadsheet

One-off=AC+(BAC-EV)
CPI method=BAC/CPI
Variance at completion=BAC-EAC
Try it yourself: Variance at completion with the CPI method?

4,050 − 4,142 = −92: about €92k over the work estimate, within the €150k contingency.

In the roles

How a Project Manager uses it

End of month 4: PV €2.4M, EV €2.2M, AC €2.25M. SPI 0.92 (behind), CPI 0.98 (slightly over). The forecast at completion stays inside the €4.2M baseline.

Questions people ask

Is earned value only for big projects?

No. A simple spreadsheet with the three numbers works for any project with a budget and a plan.