Risk identification
Ways to find what could go wrong (or better than expected) before it happens: brainstorming, checklists, past projects and checking assumptions.
What it is
Finding the uncertain events that could affect your objectives, positively or negatively, before they happen.
When to use it
From the very start, at every stage and whenever something changes. Not a one-off workshop.
Why it works
You can only manage risks you know about. Early identification gives you time and cheap options.
Do
- “Budget risk” isn't a risk; name the cause and the effect.
Don't
- Writing vague worries (“budget risk”) instead of specific causes and effects.
- Only looking for threats and missing opportunities.
- Identifying risks once and never again.
Step by step
- Gather different perspectives Team, users, suppliers, experts.
- Use prompts Checklists of common risk areas, past lessons, the assumptions list, the WBS.
- Write each risk properly Because of [cause], [event] may happen, which would [effect].
- Look for opportunities too Things that could go better than planned.
- Give each risk an owner And a first estimate.
- Repeat At every stage and when things change.