Who's needed when?
The plan looks fine on paper, until you see that Antonia is booked for 160% of her time in month 5 and nobody has planned the training.
- 09:00Resource plan with Aya
- 11:00Antonia's workload
- 14:00Training plan with Adaugo
Situation 1 of 3
09:00 · Resource plan with AyaWhat do you look for?
Situation 2 of 3
11:00 · Antonia's workloadHow do you fix it?
Levelling one person's load
Antonia (Compliance Lead)'s planned load in month 5 is 160%. Only tasks with float can move without changing the end date.
| Task in month 5 | Load | Float | What happens |
|---|---|---|---|
| Licence application | 50% | 0 (critical) | Stays |
| Fire safety audit | 30% | 6 weeks | Moved to month 4 |
| Inspection 1 | 25% | 3 weeks | Done by the council's compliance team |
| Inspection 2 | 25% | 2 weeks | Stays |
| Inspection 3 | 30% | 5 weeks | Moved to month 6 |
- Before
50 + 30 + 25 + 25 + 30= 160% - Move tasks with float
fire audit to month 4, inspection 3 to month 6= −60% - Get help
inspection 1 to the council's team= −25% - After
50 + 25 + extra checks 20= 95%
Try it yourself in a spreadsheet
| Load per month | =SUMIFS(load, person, "Antonia", month, 5) |
Why not move the licence application?
Show the answer
It has no float: it's on the critical path, so moving it would delay opening.
Situation 3 of 3
14:00 · Training plan with AdaugoWhat does the training plan need?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Resources over time
- Plan people by week or month, not just in total, including holidays and other duties.
- A resource chart per person shows peaks where someone is over-allocated.
Where you will meet this: Resource management plan · resource histogram · resource calendar
Levelling
- Fix over-allocation by moving work that has float, sharing it, or adding help.
- Only change the critical path, and the end date, as a last resort.
Where you will meet this: Resource levelling · resource smoothing
Training as project work
- Training has dependencies, lead times and owners like any other work.
- Check readiness by what people can do, not just by attendance.
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 15 complete
3 situations today.
- Plan people over time, not just in total. Include holidays and other work, and look for peaks.
- Resolve over-allocation by moving work that has float, sharing it, or adding help. Touch the critical path only as a last resort.
- Plan training like any other work: who, what, when, and how readiness is checked.