Day 15 of 46Stage 2 · PlanningThursdayResource planning and levelling

Who's needed when?

The plan looks fine on paper, until you see that Antonia is booked for 160% of her time in month 5 and nobody has planned the training.

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Team
Aya (Project Coordinator) Antonia (Quality and Compliance Lead) Adaugo (HR and Training Lead)
How the day goes
  1. 09:00Resource plan with Aya
  2. 11:00Antonia's workload
  3. 14:00Training plan with Adaugo

Situation 1 of 3

09:00 · Resource plan with Aya
Aya (Project Coordinator)
I've put all the schedule tasks against people. Can you check if it works?

What do you look for?

Plan people over time, not just in total. Include holidays and other work, and look for peaks.

Situation 2 of 3

11:00 · Antonia's workload
Antonia (Quality and Compliance Lead)
In month 5 I have the licence application, three inspections and the fire safety audit. I can't do all of that.

How do you fix it?

Resolve over-allocation by moving work that has float, sharing it, or adding help. Touch the critical path only as a last resort.
Worked example 1

Levelling one person's load

Antonia (Compliance Lead)'s planned load in month 5 is 160%. Only tasks with float can move without changing the end date.

Task in month 5LoadFloatWhat happens
Licence application50%0 (critical)Stays
Fire safety audit30%6 weeksMoved to month 4
Inspection 125%3 weeksDone by the council's compliance team
Inspection 225%2 weeksStays
Inspection 330%5 weeksMoved to month 6
Download the data (spreadsheet file)
  1. Before50 + 30 + 25 + 25 + 30= 160%
  2. Move tasks with floatfire audit to month 4, inspection 3 to month 6= −60%
  3. Get helpinspection 1 to the council's team= −25%
  4. After50 + 25 + extra checks 20= 95%
What it meansThe overload is removed without moving the opening date, because only tasks with float moved.
What Annelise decidesThe resource plan is updated, and month 4 and 6 loads are checked so the peak doesn't just move.
Try it yourself in a spreadsheet
Load per month=SUMIFS(load, person, "Antonia", month, 5)

Why not move the licence application?

Show the answer

It has no float: it's on the critical path, so moving it would delay opening.

Situation 3 of 3

14:00 · Training plan with Adaugo
Adaugo (HR and Training Lead)
Thirty new staff need training on the booking system, infection control and fire safety. When?

What does the training plan need?

Plan training like any other work: who, what, when, and how readiness is checked.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Resources over time

  • Plan people by week or month, not just in total, including holidays and other duties.
  • A resource chart per person shows peaks where someone is over-allocated.

Where you will meet this: Resource management plan · resource histogram · resource calendar

Concept

Levelling

  • Fix over-allocation by moving work that has float, sharing it, or adding help.
  • Only change the critical path, and the end date, as a last resort.

Where you will meet this: Resource levelling · resource smoothing

Common practice

Training as project work

  • Training has dependencies, lead times and owners like any other work.
  • Check readiness by what people can do, not just by attendance.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 15 complete

3 situations today.

Your responsibility todayPlanning people and skills
Technique you usedResource plan, levelling, training plan
Key points to remember
  • Plan people over time, not just in total. Include holidays and other work, and look for peaks.
  • Resolve over-allocation by moving work that has float, sharing it, or adding help. Touch the critical path only as a last resort.
  • Plan training like any other work: who, what, when, and how readiness is checked.