Out of tolerance
The booking system will be three weeks late, beyond your time limit. Check the cost forecast too, then write an exception report.
- 09:00Alfonso (Software Vendor): integration delay
- 11:00Forecast with Abigail (Finance)
- 13:00Write the exception report
- 16:00Emergency board meeting
Situation 1 of 3
09:00 · Alfonso (Software Vendor): integration delayYour time tolerance is ± 2 weeks. What do you do?
Situation 2 of 3
11:00 · Forecast with Abigail (Finance)How do you forecast the final cost?
Estimate at completion
Two ways to forecast the final cost, from the month 4 figures (€ thousands): budget 4,050, EV 2,200, AC 2,250, CPI 0.978, SPI 0.917.
| Method | Calculation | Estimate at completion (€k) |
|---|---|---|
| Overrun was a one-off | AC + (BAC − EV) | 4100 |
| Efficiency continues | BAC ÷ CPI | 4142 |
| Cost and schedule pressure continue | AC + (BAC − EV) ÷ (CPI × SPI) | 4314 |
- One-off
2,250 + (4,050 − 2,200)= 4,100 - Continuing
4,050 ÷ 0.978= 4,142 - Pessimistic
2,250 + 1,850 ÷ (0.978 × 0.917)= 4,314 - Against the baseline
baseline 4,200 (work 4,050 + contingency 150)= first two inside, third outside
Try it yourself in a spreadsheet
| One-off | =AC+(BAC-EV) |
| CPI method | =BAC/CPI |
| Variance at completion | =BAC-EAC |
Variance at completion with the CPI method?
Show the answer
4,050 − 4,142 = −92: about €92k over the work estimate, within the €150k contingency.
Situation 3 of 3
16:00 · Emergency board meetingHow do you run the board discussion?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Forecasting the finish
- Estimate at completion = actual cost so far + the cost of the remaining work.
- If past overruns were one-offs, use the remaining budget; if they'll continue, adjust for cost performance. Show both.
Where you will meet this: EAC · ETC · VAC
Exceptions
- When a forecast goes beyond an agreed tolerance, it's an exception. The project manager escalates at once to the level that can decide.
- Waiting turns options into problems.
Where you will meet this: Management by exception · exception report (PRINCE2)
Options, not blame
- An exception report gives the cause, the impact, the options with their cost, time and risk, and a recommendation.
- Causes are learned from, not used to blame.
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 34 complete
3 situations today.
- When a forecast goes beyond tolerance, escalate straight away. Exceptions go to the people with the authority to decide.
- Forecast the final cost from performance so far. Show the likely case and the range.
- An exception report gives the cause, the impact, options and a recommendation. The board decides; lessons are captured without blame.