Day 34 of 46Stage 4 · Monitoring and controllingThursdayExceptions and forecasting

Out of tolerance

The booking system will be three weeks late, beyond your time limit. Check the cost forecast too, then write an exception report.

Stage goal: Keep the project on track and control every change.
Stakeholders
Alfonso (Software Vendor Project Manager) Abigail (Finance Business Partner) Atticus (Director of Community Health)
How the day goes
  1. 09:00Alfonso (Software Vendor): integration delay
  2. 11:00Forecast with Abigail (Finance)
  3. 13:00Write the exception report
  4. 16:00Emergency board meeting

Situation 1 of 3

09:00 · Alfonso (Software Vendor): integration delay
Alfonso (Software Vendor Project Manager)
The council's patient records system needs a security upgrade first. Integration will be three weeks late.

Your time tolerance is ± 2 weeks. What do you do?

When a forecast goes beyond tolerance, escalate straight away. Exceptions go to the people with the authority to decide.

Situation 2 of 3

11:00 · Forecast with Abigail (Finance)
Abigail (Finance Business Partner)
With the claim and the change, what will the whole project cost now?

How do you forecast the final cost?

Forecast the final cost from performance so far. Show the likely case and the range.
Worked example 1

Estimate at completion

Two ways to forecast the final cost, from the month 4 figures (€ thousands): budget 4,050, EV 2,200, AC 2,250, CPI 0.978, SPI 0.917.

Estimate at completion by method, € thousands01,2502,5003,7505,000One-off: 4,1004,100One-offCPI: 4,1424,142CPICPI × SPI: 4,3144,314CPI × SPI
MethodCalculationEstimate at completion (€k)
Overrun was a one-offAC + (BAC − EV)4100
Efficiency continuesBAC ÷ CPI4142
Cost and schedule pressure continueAC + (BAC − EV) ÷ (CPI × SPI)4314
Download the data (spreadsheet file)
  1. One-off2,250 + (4,050 − 2,200)= 4,100
  2. Continuing4,050 ÷ 0.978= 4,142
  3. Pessimistic2,250 + 1,850 ÷ (0.978 × 0.917)= 4,314
  4. Against the baselinebaseline 4,200 (work 4,050 + contingency 150)= first two inside, third outside
What it meansCost stays inside tolerance unless both cost and schedule pressure continue. Time is what has broken tolerance.
What Annelise decidesThe exception report covers time; the cost forecast is watched monthly.
Try it yourself in a spreadsheet
One-off=AC+(BAC-EV)
CPI method=BAC/CPI
Variance at completion=BAC-EAC

Variance at completion with the CPI method?

Show the answer

4,050 − 4,142 = −92: about €92k over the work estimate, within the €150k contingency.

Situation 3 of 3

16:00 · Emergency board meeting
Atticus (Director of Community Health)sponsor
This vendor has let us down. I want to know whose fault this is.

How do you run the board discussion?

An exception report gives the cause, the impact, options and a recommendation. The board decides; lessons are captured without blame.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Forecasting the finish

  • Estimate at completion = actual cost so far + the cost of the remaining work.
  • If past overruns were one-offs, use the remaining budget; if they'll continue, adjust for cost performance. Show both.

Where you will meet this: EAC · ETC · VAC

Concept

Exceptions

  • When a forecast goes beyond an agreed tolerance, it's an exception. The project manager escalates at once to the level that can decide.
  • Waiting turns options into problems.

Where you will meet this: Management by exception · exception report (PRINCE2)

Common practice

Options, not blame

  • An exception report gives the cause, the impact, the options with their cost, time and risk, and a recommendation.
  • Causes are learned from, not used to blame.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 34 complete

3 situations today.

Your responsibility todayHandling exceptions
Technique you usedTolerances, estimate at completion, exception report
Key points to remember
  • When a forecast goes beyond tolerance, escalate straight away. Exceptions go to the people with the authority to decide.
  • Forecast the final cost from performance so far. Show the likely case and the range.
  • An exception report gives the cause, the impact, options and a recommendation. The board decides; lessons are captured without blame.