The longest chain of dependent activities through the plan. It sets the end date; activities off it have slack.
Common practice 7 steps Used by Project Manager
What it is
The critical path is the longest chain of dependent activities from start to finish. It sets the shortest possible duration of the project.
Activities on it have no slack: if one slips, the end date slips. Activities off it have float, so they can move a little without affecting the end.
When to use it
When building or changing a schedule, and whenever someone asks “can we finish earlier?”.
Variations
Critical chain adds shared buffers at the end of chains instead of padding each task.
Near-critical paths chains with very little float that deserve attention too.
Why it works
It tells you where to focus. Speeding up a non-critical task doesn't help the end date; protecting critical tasks does.
It also tells you what to say when someone asks “can we finish earlier?”: only by shortening the critical path.
Do
Outside dependencies (permits, deliveries, approvals) are often on the critical path and outside your control: book them early.
Show the critical path in a different colour on every Gantt chart you share.
Don't
Missing dependencies, so the path looks shorter than it is.
Ignoring near-critical paths with very little slack.
Step by step
List the activitiesUse the work breakdown to list activities with a duration estimate each.
Find the dependenciesFor each activity, ask: what must finish before this can start? Note outside dependencies too, like approvals or deliveries.
Draw the networkBoxes for activities, arrows for dependencies. Sticky notes on a wall work well.
Walk forwardsFrom the start, work out the earliest start and finish of each activity. The latest earliest-finish is the project end.
Walk backwardsFrom the end, work out the latest each activity can finish without delaying the end. The difference between latest and earliest is the float.
Mark the zero-float chainActivities with zero float form the critical path. Highlight them in the schedule and watch them most closely.
Recheck when things changeA delay on a non-critical task can use up its float and make a new critical path.
Filled in for: Opening a new café: lease signed, fit-out, equipment, hiring, permit, opening.
Activity
Duration
Depends on
Float
Copy this structure, or print the blank version and fill it in by hand. Write activities with durations and dependencies; mark the chain with zero float as critical.
Before you use it: check these
Check
If it fails
Every activity has its predecessors recorded
An activity with no links hides float; link it before trusting the path
Durations are realistic, not wishes
Use three-point estimates for uncertain work
People are not double-booked
Level resources; the critical path can move
How to do it with real data
The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Twelve activities with durations (weeks) and what must finish first. A forward pass finds the earliest dates, a backward pass the latest; the difference is the float.
Step by step
Forward passeach activity starts when all its predecessors finish; earliest finish = start + duration= opening at the end of week 30
Backward passfrom week 30 back, the latest each activity can finish without delaying the end
Eight activities have no float: any delay to them delays opening. Hiring can slip 5 weeks and booking setup 7 without harm.
What it led to
Annelise (Project Manager) watches the building works and licence most closely, and uses the float in hiring when people are double-booked.
Do it in a spreadsheet
Earliest finish
=start + duration (start = MAX of predecessors' finishes)
Float
=latest start - earliest start
Gantt chart
stacked bar chart: invisible bar for the start, visible bar for the duration
Try it yourself: If building works take 16 weeks instead of 14, when does the clinic open?
Building works are critical, so opening moves 2 weeks, to the end of week 32.
In the roles
How a Project Manager uses it
Purchase → asbestos removal → building works → equipment → inspection → licence → opening has no slack and ends in week 30. Hiring has 5 weeks of slack.