Procurement · cheat sheet

Supplier scorecard

A regular, evidence-based score of a supplier against agreed measures, discussed with the supplier to agree improvements.

Common practice
5 steps
Used by Project Manager

What it is

A regular, evidence-based score of a supplier on agreed measures, discussed with them to agree improvements.

When to use it

Monthly or at milestones for every major supplier.

Why it works

It keeps supplier conversations factual, catches problems early, and turns complaints into actions.

Do

  • Recognise good performance too; suppliers respond to it.

Don't

  • Scores without evidence.
  • Using the scorecard only to punish.

Step by step

  1. Agree measures at the start Time, quality, safety, communication, cost.
  2. Score 1 to 5 with evidence Dates, inspection results, incidents.
  3. Share before meeting No surprises.
  4. Discuss strengths and gaps Both.
  5. Agree actions With owners and dates; check next time.
Also called: Supplier performance review, vendor ratingPrint the blank template ↗

Worked example

The situation. A building contractor in month 4.

  1. Safety 5, time 2, quality 3, communication 3.
  2. Action: a recovery plan with weekly checkpoints.

The result. Time improved to 4 within two months.

Supplier scorecard Print blank
MeasureScoreEvidence
Safety5No incidents
Time2Two weeks behind
Quality3One defect, fixed
Communication3Missed a handover

Filled in for: A building contractor in month 4.

MeasureScore 1–5EvidenceAction

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

The building contractor scores 5 on safety but 2 on time in month 4. Arash (Contractor Project Manager) agrees a recovery plan with weekly checkpoints.

Questions people ask

How often?

Monthly or at milestones for important suppliers.