Monitoring and control · cheat sheet

Change board

The agreed group or person that decides on changes beyond the project manager's authority, based on impact and options.

Common practice
5 steps
Used by Project Manager

What it is

The agreed person or group that decides on changes beyond the project manager's authority, based on impact and options.

When to use it

Set up in planning; meets when a change needs a decision, or at regular intervals.

Why it works

It makes sure significant changes are decided by the right people, consistently, and recorded.

Do

  • Batch small changes for regular meetings; urgent ones can be decided by email with a record.

Don't

  • Every small change going to the board.
  • Decisions taken outside the board, then reported.

Step by step

  1. Define authority levels Project manager within tolerance; board above it.
  2. Choose members Sponsor, user side, supplier side where relevant.
  3. Decide on evidence Impact analysis and options.
  4. Record decisions and reasons In the change log.
  5. Make sure updates happen Plans, baselines, contracts, communication.
Also called: Change control board, CCB, change authorityPrint the blank template ↗

Worked example

The situation. A scope change worth €60,000.

  1. Beyond the €25,000 limit, so it went to the board.
  2. Board approved a smaller version for €30,000.

The result. The change was made without breaking the budget.

Change board decisions Print blank
ChangeImpact summaryOptionsDecisionCon­ditionsDate

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

Atticus (Sponsor), Amani (Clinical Lead) and a contractor representative approve the wall change, paid from contingency, with two finishing tasks overlapped so opening doesn't move.

Questions people ask

Does every change go to the board?

No. Only those beyond the agreed tolerance.