Governance and roles · cheat sheet Stage gate A decision point at the end of each stage where the board decides to continue, continue with conditions, or stop.
Common practice 5 steps Used by Project Manager, Process Improvement Specialist
What it is A decision point at the end of a stage where leaders decide to continue, continue with conditions, or stop, based on evidence.
When to use it At the end of every management stage.
Why it works It makes continuing a conscious decision, checks the business case regularly, and lets projects stop before more money is wasted.
Do A gate where “stop” is never an option isn't a gate. Don't A gate nobody would ever close. Gates without an updated business case. Step by step Prepare an end-stage report Performance against baselines, risks, lessons.
Update the business case Costs, benefits, dates.
Present the next stage's plan What, when, how much.
Decide Go, go with conditions, or stop.
Record the decision And any conditions.
Worked example The situation. An app project after its pilot stage.
Costs on plan, but user uptake half of expected. Board decides: go, on condition of a redesign of sign-up first. The result. Uptake doubled after the redesign.
Area Plan Actual or forecast Comment
Copy this structure, or print the blank version and fill it in by hand.
In the roles How a Project Manager uses itAt the end of building works, the board reviews the end-stage report and says go, on condition that the licence result is in before the opening event is announced.
How a Process Improvement Specialist uses itAt the end of Define, Atticus (Sponsor) checks the charter, scope, customer needs, team and plan, and signs the charter.
Questions people ask Is stopping a failure? No. Stopping a project that no longer makes sense is good management.