Risk · cheat sheet

Risk responses

The ways to deal with a risk before it happens: for threats avoid, transfer, reduce or accept; for opportunities exploit, enhance, share or accept.

Common practice
6 steps
Used by Project Manager

What it is

The ways to deal with a risk before it happens. For threats: avoid, transfer, reduce or accept. For opportunities: exploit, enhance, share or accept.

When to use it

For every significant risk, as soon as it's analysed.

Why it works

Different risks need different responses. Choosing deliberately is cheaper than reacting when the risk happens.

Do

  • Adding contingency money is acceptance, not reduction; prefer responses that change the risk.

Don't

  • Always choosing “add contingency”.
  • Responses that are never put into the plan.

Step by step

  1. Start with the highest risks From your ranking.
  2. Consider each strategy Avoid (change the plan), transfer (contract, insurance), reduce (lower likelihood or impact), accept (maybe with money aside).
  3. For opportunities Exploit (make sure), enhance (make likelier), share (with a partner), accept.
  4. Choose and cost the response Is it worth it?
  5. Give it an owner and a date And add it to the plan.
  6. Check if it worked Re-score the risk.
Also called: Avoid, transfer, reduce, accept, exploit, enhance, sharePrint the blank template ↗

Worked example

The situation. Risks for an outdoor event.

  1. Rain: reduce (marquees).
  2. Supplier failure: transfer (penalty clause, back-up).
  3. Venue double-booking: avoid (signed contract now).
  4. Small catering shortfall: accept.

The result. It rained; the event went ahead under marquees.

Risk response plan Print blank
RiskStrategyActionOwner
Heavy rainReduceMarquees and drainageSite lead
Supplier failureTransferPenalty clause, back-up supplierProcurement
Double bookingAvoidSign venue contract nowProject manager

Filled in for: Risks for an outdoor event.

RiskStrategyActionsOwnerCostDue

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

Equipment price rise: transfer, with a fixed-price contract. Ventilation licence risk: reduce, with an early design review by the inspector. Digital health grant: enhance, Aine (IT Lead) owns the application.

Questions people ask

Can I combine strategies?

Yes, often: reduce the likelihood and transfer the rest.