Who's in charge here?
The money is approved and everyone wants to start. Before anything is bought, the project needs an official start, an owner and clear limits.
Stage goal: Start the project properly: authority, people and direction.
Team
Aya (Project Coordinator)
Stakeholders
Atticus (Director of Community Health) Abigail (Finance Business Partner)
How the day goes
- 09:00Draft the project charter
- 11:30Charter review with Atticus (Sponsor)
- 14:00Finance check-in with Abigail (Finance)
- 16:00Equipment lead times with Aya (Project Coordinator)
Situation 1 of 3
11:30 · Charter review with Atticus (Sponsor)Atticus (Director of Community Health)sponsor
The council approved the money. Just get going, we don't need more paperwork.
What do you do before committing any money?
A project officially starts with a charter signed by the sponsor. It names the project manager and says how far their authority goes.
Used here Project charter
Situation 2 of 3
14:00 · Finance check-in with Abigail (Finance)Abigail (Finance Business Partner)
The structural survey of the warehouse costs €40,000. Can you just approve it yourself?
Your charter says you may spend up to €25,000 alone. What do you do?
Agreed limits (tolerances) let the project manager act quickly inside them and escalate, with a recommendation, outside them.
Situation 3 of 3
16:00 · Equipment lead times with Aya (Project Coordinator)Aya (Project Coordinator)
The X-ray and lab equipment takes 14 weeks to arrive. If we order after the design is approved, we can't open in month 7.
What do you do with this?
Write risks down as soon as you see them, give each an owner and agree a response while there is still time to act.
Used here Risk identification RAID log
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Concept
The project charter
- A short document, signed by the sponsor, that officially starts the project.
- It names the project manager, states the objective, the rough scope, the big milestones and the budget, and says how much the project manager may decide alone.
Where you will meet this: Project charter (PMI) · project brief (PRINCE2)
Concept
Tolerances and escalation
- Tolerances are agreed limits, for example ± €25,000 or ± 2 weeks. Inside them the project manager acts; outside them they escalate.
- Escalate with a recommendation, not just a problem, so the decision is quick.
Where you will meet this: Tolerances · management by exception
Concept
Risks are written down early
- A risk is something uncertain that would affect the objectives if it happened.
- Record its cause and effect, give it an owner and agree a response while there is still time to act.
Where you will meet this: Risk register · risk owner · risk response
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 5 complete
3 situations today.
Your responsibility todayStarting the project with clear authority
Technique you usedProject charter, tolerances, early risk response
Key points to remember
- A project officially starts with a charter signed by the sponsor. It names the project manager and says how far their authority goes.
- Agreed limits (tolerances) let the project manager act quickly inside them and escalate, with a recommendation, outside them.
- Write risks down as soon as you see them, give each an owner and agree a response while there is still time to act.