Management by exception
Leaders agree limits (tolerances) for cost, time and scope; the project manager acts freely inside them and escalates only when a limit will be exceeded.
What it is
Leaders agree limits (tolerances) for time, cost, scope, quality and risk. Within them, the project manager decides; beyond them, the issue is escalated at once.
When to use it
When the project starts and the governance is set up; used every day after that.
Why it works
It lets leaders steer without attending every meeting, and lets the project manager act quickly within clear limits.
Do
- Tolerances too tight mean everything escalates; too wide, and leaders lose control.
Don't
- Tolerances so tight that everything is escalated.
- Escalating a problem without options.
- Hiding a breach until it can't be hidden.
Step by step
- Agree tolerances For example ± €25,000 or ± 2 weeks per stage.
- Write them down In the charter or plan.
- Decide inside them And report afterwards.
- Forecast regularly So you see an exception coming.
- Escalate at once when a forecast exceeds them With options and a recommendation.
- Let leaders review at set points Stage ends, monthly boards.