Scope and scheduling · cheat sheet Resource levelling Adjusting the schedule so nobody is booked for more than they can do, by moving work that has float, sharing it, or adding help.
Common practice 6 steps Used by Project Manager
What it is Adjusting a schedule so nobody is booked for more than they can do, by moving work that has float, sharing it, or adding help.
When to use it After the first schedule exists and whenever people's availability changes.
Why it works Plans that overload people fail quietly: work slips, quality drops, people burn out. Levelling makes the plan doable.
Do Nobody can work at 100% on project tasks for long; leave room for the unexpected. Don't Looking only at totals per person. Forgetting people's other jobs. Step by step Load tasks per person over time Include holidays and other duties.
Chart it A bar per week or month; mark 100%.
Find the peaks Who is over 100%, and when?
Move tasks with float Into quieter periods.
Share or add help Where moving isn't enough.
Touch the critical path last Only then does the end date move.
Worked example The situation. A small team planning a product launch.
The designer is at 150% in week 6. Two non-critical tasks move to week 8; a freelancer takes one. The result. The launch date held and the designer stayed healthy.
Person Week 5 Week 6 Week 7 Week 8 Designer (before) 80% 150% 90% 40% Designer (after) 80% 95% 90% 85%
Filled in for: A small team planning a product launch.
Person Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Notes
Copy this structure, or print the blank version and fill it in by hand.
Before you use it: check these Check If it fails Float known for every task Calculate the critical path first The new peak is checked after moving tasks Check the months the tasks moved into
How to do it with real data The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataLevelling one person's load
From Day 15: Who's needed when? of the Project Manager story
Antonia (Compliance Lead)'s planned load in month 5 is 160%. Only tasks with float can move without changing the end date.
Step by step Before 50 + 30 + 25 + 25 + 30 = 160% Move tasks with float fire audit to month 4, inspection 3 to month 6 = −60% Get help inspection 1 to the council's team = −25% After 50 + 25 + extra checks 20 = 95%
Task in month 5 Load Float What happens Licence application 50% 0 (critical) Stays Fire safety audit 30% 6 weeks Moved to month 4 Inspection 1 25% 3 weeks Done by the council's compliance team Inspection 2 25% 2 weeks Stays Inspection 3 30% 5 weeks Moved to month 6
How to read the result The overload is removed without moving the opening date, because only tasks with float moved.
What it led to The resource plan is updated, and month 4 and 6 loads are checked so the peak doesn't just move.
Do it in a spreadsheet Load per month =SUMIFS(load, person, "Antonia", month, 5)
Try it yourself: Why not move the licence application? It has no float: it's on the critical path, so moving it would delay opening.
In the roles How a Project Manager uses itAntonia (Quality and Compliance Lead) is at 160% in month 5. Moving tasks with float and getting help with one inspection brings her to 95% without moving the opening date.
Questions people ask Levelling or smoothing? Levelling can move the end date; smoothing only uses float and keeps it.
← All techniques and tools