Scope and scheduling · cheat sheet

Resource levelling

Adjusting the schedule so nobody is booked for more than they can do, by moving work that has float, sharing it, or adding help.

Common practice
6 steps
Used by Project Manager

What it is

Adjusting a schedule so nobody is booked for more than they can do, by moving work that has float, sharing it, or adding help.

When to use it

After the first schedule exists and whenever people's availability changes.

Why it works

Plans that overload people fail quietly: work slips, quality drops, people burn out. Levelling makes the plan doable.

Do

  • Nobody can work at 100% on project tasks for long; leave room for the unexpected.

Don't

  • Looking only at totals per person.
  • Forgetting people's other jobs.

Step by step

  1. Load tasks per person over time Include holidays and other duties.
  2. Chart it A bar per week or month; mark 100%.
  3. Find the peaks Who is over 100%, and when?
  4. Move tasks with float Into quieter periods.
  5. Share or add help Where moving isn't enough.
  6. Touch the critical path last Only then does the end date move.
Also called: Resource smoothing, resource histogramPrint the blank template ↗

Worked example

The situation. A small team planning a product launch.

  1. The designer is at 150% in week 6.
  2. Two non-critical tasks move to week 8; a freelancer takes one.

The result. The launch date held and the designer stayed healthy.

Resource load sheet Print blank
PersonWeek 5Week 6Week 7Week 8
Designer (before)80%150%90%40%
Designer (after)80%95%90%85%

Filled in for: A small team planning a product launch.

PersonWeek 1Week 2Week 3Week 4Week 5Week 6Notes

Copy this structure, or print the blank version and fill it in by hand.

Before you use it: check these

CheckIf it fails
Float known for every taskCalculate the critical path first
The new peak is checked after moving tasksCheck the months the tasks moved into

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

Levelling one person's load

From Day 15: Who's needed when? of the Project Manager story

Antonia (Compliance Lead)'s planned load in month 5 is 160%. Only tasks with float can move without changing the end date.

Step by step

  1. Before50 + 30 + 25 + 25 + 30= 160%
  2. Move tasks with floatfire audit to month 4, inspection 3 to month 6= −60%
  3. Get helpinspection 1 to the council's team= −25%
  4. After50 + 25 + extra checks 20= 95%
Task in month 5LoadFloatWhat happens
Licence application50%0 (critical)Stays
Fire safety audit30%6 weeksMoved to month 4
Inspection 125%3 weeksDone by the council's compliance team
Inspection 225%2 weeksStays
Inspection 330%5 weeksMoved to month 6

How to read the result

The overload is removed without moving the opening date, because only tasks with float moved.

What it led to

The resource plan is updated, and month 4 and 6 loads are checked so the peak doesn't just move.

Do it in a spreadsheet

Load per month=SUMIFS(load, person, "Antonia", month, 5)
Try it yourself: Why not move the licence application?

It has no float: it's on the critical path, so moving it would delay opening.

In the roles

How a Project Manager uses it

Antonia (Quality and Compliance Lead) is at 160% in month 5. Moving tasks with float and getting help with one inspection brings her to 95% without moving the opening date.

Questions people ask

Levelling or smoothing?

Levelling can move the end date; smoothing only uses float and keeps it.