Day 17 of 46Stage 2 · PlanningFridayQuantitative risk analysis

Putting numbers on risk

The board asks: how sure are you about month 7? And should we pay €40,000 for a survey? Time to put numbers on risk.

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Stakeholders
Abigail (Finance Business Partner) Atticus (Director of Community Health)
Documents today Risk management plan
How the day goes
  1. 09:00Survey decision with Abigail
  2. 11:00Atticus (Sponsor): how certain is the opening date?
  3. 15:00Risk appetite with Atticus

Situation 1 of 3

09:00 · Survey decision with Abigail
Abigail (Finance Business Partner)
The structural survey costs €40,000. Without it, there's a 30% chance of finding problems mid-works, costing about €300,000. Is the survey worth it?

How do you decide?

Expected value (probability × impact) helps compare choices under uncertainty. A decision tree shows the options and their outcomes.
Worked example 1

Is the survey worth €40,000?

Without a structural survey there's a 30% chance of finding problems mid-works, costing about €300,000. With the survey, most of that is found early; a 5% chance remains.

Expected cost of each option025,00050,00075,000100,000No / survey: €90,000€90,000NosurveySurvey: €55,000€55,000Survey
OptionCertain costChance of problemsCost if they happenExpected cost
No survey030%30000090000
Survey400005%30000055000
Download the data (spreadsheet file)
  1. Expected value without the survey0.30 × €300,000= €90,000
  2. With the survey€40,000 + 0.05 × €300,000= €55,000
  3. Difference90,000 − 55,000= €35,000 in favour of the survey
What it meansOn average the survey saves €35,000, and it removes most of the chance of a €300,000 shock in the middle of the works.
What Annelise decidesOrder the survey. The decision tree goes into the business case file.
Try it yourself in a spreadsheet
Expected cost=B2+C2*D2

At what chance of problems would the survey stop being worth it (with 5% remaining after it)?

Show the answer

When p × 300,000 = 40,000 + 15,000: p = 18%.

Situation 2 of 3

11:00 · Atticus (Sponsor): how certain is the opening date?
Atticus (Director of Community Health)sponsor
Can you promise month 7? Yes or no?

How do you answer?

Simulating the schedule with ranges shows how likely each date is. Confidence levels are more honest than one date.
Worked example 2

How likely is month 7?

Each critical activity gets a range (best, most likely, worst), and the schedule is run thousands of times. Here are 200 of the runs: weeks to opening.

Simulated weeks to opening, 200 runs02040608026 to 27: 6627 to 28: 202028 to 29: 424229 to 30: 484830 to 31: 444431 to 32: 252532 to 33: 9933 to 34: 5534 to 35: 035 to 36: 112627282930313233343536Week 30: month 7Week 32
RunWeeks to opening
Run 130.3
Run 228.7
Run 329.8
Run 430.9
Run 532.1
Run 630.4
Run 728.6
Run 828.6
Run 930.2
Run 1029.6
Run 1128
Run 1230.6
Run 1327.8
Run 1430.1
Run 1530.4
Run 1626.9
Run 1729.5
Run 1829.4
Run 1931
Run 2027.6
Run 2130.3
Run 2228.9
Run 2327.4
Run 2430
Run 2530.1
Run 2628.8
Run 2729.6
Run 2828.9
Run 2930.8
Run 3031.3
Run 3130.1
Run 3227.6
Run 3328.9
Run 3428.7
Run 3530.2
Run 3630.2
Run 3730.5
Run 3830.2
Run 3926.9
Run 4028.3
Run 4131
Run 4228.5
Run 4331.3
Run 4427.4
Run 4529.2
Run 4628.2
Run 4729.9
Run 4827.8
Run 4930.3
Run 5030.3
Run 5130
Run 5230.1
Run 5329.6
Run 5432
Run 5530.7
Run 5628.6
Run 5729.6
Run 5829.5
Run 5926.5
Run 6027.6
Run 6128.3
Run 6231.3
Run 6328.6
Run 6426.4
Run 6531
Run 6628.6
Run 6729.3
Run 6830.5
Run 6931.8
Run 7029.5
Run 7132.3
Run 7232.4
Run 7331
Run 7432.6
Run 7527.6
Run 7629.6
Run 7733.2
Run 7828.1
Run 7935
Run 8030
Run 8130.3
Run 8231.1
Run 8328.7
Run 8433.2
Run 8529.4
Run 8630
Run 8728.1
Run 8828.7
Run 8928.7
Run 9029
Run 9128.9
Run 9232.8
Run 9328.5
Run 9430.9
Run 9531.9
Run 9629.5
Run 9728.1
Run 9829.1
Run 9931.7
Run 10027.6
Run 10130.5
Run 10228.7
Run 10328.2
Run 10430.2
Run 10528.7
Run 10628.5
Run 10730.6
Run 10829.5
Run 10929.1
Run 11029.2
Run 11127.4
Run 11230.5
Run 11327.1
Run 11426.3
Run 11532
Run 11629.7
Run 11731.1
Run 11829.6
Run 11931.7
Run 12030
Run 12128.8
Run 12229.6
Run 12329.8
Run 12431.2
Run 12532.1
Run 12627
Run 12731.4
Run 12831.2
Run 12928.9
Run 13029.2
Run 13130
Run 13229.9
Run 13329.4
Run 13430
Run 13528
Run 13630.2
Run 13727.2
Run 13828.7
Run 13929.4
Run 14027.8
Run 14128.2
Run 14228.6
Run 14330.9
Run 14430.5
Run 14531.7
Run 14629.5
Run 14729.5
Run 14829.2
Run 14928.1
Run 15027
Run 15129.8
Run 15230.8
Run 15333
Run 15427.2
Run 15529.8
Run 15629.9
Run 15729.7
Run 15829
Run 15929.4
Run 16030.1
Run 16128
Run 16231.8
Run 16329.6
Run 16431.6
Run 16528.5
Run 16630.8
Run 16727.4
Run 16829.9
Run 16930.2
Run 17029
Run 17133
Run 17226.7
Run 17331.2
Run 17430.7
Run 17531
Run 17630.1
Run 17729.5
Run 17829.6
Run 17927.8
Run 18028.1
Run 18129.1
Run 18228.4
Run 18331.7
Run 18428.8
Run 18530.5
Run 18631.6
Run 18731.5
Run 18829.9
Run 18929.6
Run 19027.6
Run 19131.4
Run 19229.6
Run 19328.7
Run 19429
Run 19527.6
Run 19632.6
Run 19733.3
Run 19830.5
Run 19929.5
Run 20028
Download the data (spreadsheet file)
  1. Rangesfor example building works 10, 13, 16 weeks; asbestos 2, 3, 4
  2. Run many timeseach run draws a duration for every activity and adds the critical path
  3. By week 30 (month 7)runs finishing by week 30 ÷ all runs= about 60%
  4. By week 32 (mid-month 8)= about 94%
  5. Middle resultmedian of the runs= about 30 weeks
What it meansMonth 7 is a little better than a coin toss; mid-month 8 is very likely. A single date hides that.
What Annelise decidesAtticus (Sponsor) keeps month 7 as the target and announces “autumn” publicly.
Try it yourself in a spreadsheet
One random number (cell C2)=RAND()
One triangular draw from it=IF(C2<(m-a)/(b-a), a+SQRT(C2*(b-a)*(m-a)), b-SQRT((1-C2)*(b-a)*(b-m))) (a best, m most likely, b worst)
Share by week 30=COUNTIF(B2:B201,"<=30")/200

What share of the 200 runs finish by week 32?

Show the answer

=COUNTIF(B2:B201,"<=32")/200: about 94%.

Situation 3 of 3

15:00 · Risk appetite with Atticus
Atticus (Director of Community Health)sponsor
How much risk are we willing to take? Some people want everything safe, others want speed.

What do you agree?

Agree how much risk is acceptable in each area, and write it down. It guides every risk decision afterwards.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Expected value

  • Probability × impact gives the expected value of a risk.
  • Comparing expected values of options, often drawn as a decision tree, helps choose under uncertainty.

Where you will meet this: Expected monetary value (EMV) · decision tree analysis

Concept

How sure is the date?

  • Running the schedule many times with each activity's range of durations shows how likely each finish date is.
  • Report confidence levels, such as 60% by month 7, over 90% by mid-month 8.

Where you will meet this: Monte Carlo simulation · quantitative risk analysis

Concept

Risk appetite

  • How much risk the organisation is willing to accept, often different per area: low for safety and law, higher for extras.
  • It guides every risk decision.

Where you will meet this: Risk appetite · risk thresholds · risk management plan

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 17 complete

3 situations today.

Your responsibility todayQuantifying risk
Technique you usedExpected value, decision tree, schedule simulation, risk appetite
Key points to remember
  • Expected value (probability × impact) helps compare choices under uncertainty. A decision tree shows the options and their outcomes.
  • Simulating the schedule with ranges shows how likely each date is. Confidence levels are more honest than one date.
  • Agree how much risk is acceptable in each area, and write it down. It guides every risk decision afterwards.
Documents today Risk management plan