Putting numbers on risk
The board asks: how sure are you about month 7? And should we pay €40,000 for a survey? Time to put numbers on risk.
- 09:00Survey decision with Abigail
- 11:00Atticus (Sponsor): how certain is the opening date?
- 15:00Risk appetite with Atticus
Situation 1 of 3
09:00 · Survey decision with AbigailHow do you decide?
Is the survey worth €40,000?
Without a structural survey there's a 30% chance of finding problems mid-works, costing about €300,000. With the survey, most of that is found early; a 5% chance remains.
| Option | Certain cost | Chance of problems | Cost if they happen | Expected cost |
|---|---|---|---|---|
| No survey | 0 | 30% | 300000 | 90000 |
| Survey | 40000 | 5% | 300000 | 55000 |
- Expected value without the survey
0.30 × €300,000= €90,000 - With the survey
€40,000 + 0.05 × €300,000= €55,000 - Difference
90,000 − 55,000= €35,000 in favour of the survey
Try it yourself in a spreadsheet
| Expected cost | =B2+C2*D2 |
At what chance of problems would the survey stop being worth it (with 5% remaining after it)?
Show the answer
When p × 300,000 = 40,000 + 15,000: p = 18%.
Situation 2 of 3
11:00 · Atticus (Sponsor): how certain is the opening date?How do you answer?
How likely is month 7?
Each critical activity gets a range (best, most likely, worst), and the schedule is run thousands of times. Here are 200 of the runs: weeks to opening.
| Run | Weeks to opening |
|---|---|
| Run 1 | 30.3 |
| Run 2 | 28.7 |
| Run 3 | 29.8 |
| Run 4 | 30.9 |
| Run 5 | 32.1 |
| Run 6 | 30.4 |
| Run 7 | 28.6 |
| Run 8 | 28.6 |
| Run 9 | 30.2 |
| Run 10 | 29.6 |
| Run 11 | 28 |
| Run 12 | 30.6 |
| Run 13 | 27.8 |
| Run 14 | 30.1 |
| Run 15 | 30.4 |
| Run 16 | 26.9 |
| Run 17 | 29.5 |
| Run 18 | 29.4 |
| Run 19 | 31 |
| Run 20 | 27.6 |
| Run 21 | 30.3 |
| Run 22 | 28.9 |
| Run 23 | 27.4 |
| Run 24 | 30 |
| Run 25 | 30.1 |
| Run 26 | 28.8 |
| Run 27 | 29.6 |
| Run 28 | 28.9 |
| Run 29 | 30.8 |
| Run 30 | 31.3 |
| Run 31 | 30.1 |
| Run 32 | 27.6 |
| Run 33 | 28.9 |
| Run 34 | 28.7 |
| Run 35 | 30.2 |
| Run 36 | 30.2 |
| Run 37 | 30.5 |
| Run 38 | 30.2 |
| Run 39 | 26.9 |
| Run 40 | 28.3 |
| Run 41 | 31 |
| Run 42 | 28.5 |
| Run 43 | 31.3 |
| Run 44 | 27.4 |
| Run 45 | 29.2 |
| Run 46 | 28.2 |
| Run 47 | 29.9 |
| Run 48 | 27.8 |
| Run 49 | 30.3 |
| Run 50 | 30.3 |
| Run 51 | 30 |
| Run 52 | 30.1 |
| Run 53 | 29.6 |
| Run 54 | 32 |
| Run 55 | 30.7 |
| Run 56 | 28.6 |
| Run 57 | 29.6 |
| Run 58 | 29.5 |
| Run 59 | 26.5 |
| Run 60 | 27.6 |
| Run 61 | 28.3 |
| Run 62 | 31.3 |
| Run 63 | 28.6 |
| Run 64 | 26.4 |
| Run 65 | 31 |
| Run 66 | 28.6 |
| Run 67 | 29.3 |
| Run 68 | 30.5 |
| Run 69 | 31.8 |
| Run 70 | 29.5 |
| Run 71 | 32.3 |
| Run 72 | 32.4 |
| Run 73 | 31 |
| Run 74 | 32.6 |
| Run 75 | 27.6 |
| Run 76 | 29.6 |
| Run 77 | 33.2 |
| Run 78 | 28.1 |
| Run 79 | 35 |
| Run 80 | 30 |
| Run 81 | 30.3 |
| Run 82 | 31.1 |
| Run 83 | 28.7 |
| Run 84 | 33.2 |
| Run 85 | 29.4 |
| Run 86 | 30 |
| Run 87 | 28.1 |
| Run 88 | 28.7 |
| Run 89 | 28.7 |
| Run 90 | 29 |
| Run 91 | 28.9 |
| Run 92 | 32.8 |
| Run 93 | 28.5 |
| Run 94 | 30.9 |
| Run 95 | 31.9 |
| Run 96 | 29.5 |
| Run 97 | 28.1 |
| Run 98 | 29.1 |
| Run 99 | 31.7 |
| Run 100 | 27.6 |
| Run 101 | 30.5 |
| Run 102 | 28.7 |
| Run 103 | 28.2 |
| Run 104 | 30.2 |
| Run 105 | 28.7 |
| Run 106 | 28.5 |
| Run 107 | 30.6 |
| Run 108 | 29.5 |
| Run 109 | 29.1 |
| Run 110 | 29.2 |
| Run 111 | 27.4 |
| Run 112 | 30.5 |
| Run 113 | 27.1 |
| Run 114 | 26.3 |
| Run 115 | 32 |
| Run 116 | 29.7 |
| Run 117 | 31.1 |
| Run 118 | 29.6 |
| Run 119 | 31.7 |
| Run 120 | 30 |
| Run 121 | 28.8 |
| Run 122 | 29.6 |
| Run 123 | 29.8 |
| Run 124 | 31.2 |
| Run 125 | 32.1 |
| Run 126 | 27 |
| Run 127 | 31.4 |
| Run 128 | 31.2 |
| Run 129 | 28.9 |
| Run 130 | 29.2 |
| Run 131 | 30 |
| Run 132 | 29.9 |
| Run 133 | 29.4 |
| Run 134 | 30 |
| Run 135 | 28 |
| Run 136 | 30.2 |
| Run 137 | 27.2 |
| Run 138 | 28.7 |
| Run 139 | 29.4 |
| Run 140 | 27.8 |
| Run 141 | 28.2 |
| Run 142 | 28.6 |
| Run 143 | 30.9 |
| Run 144 | 30.5 |
| Run 145 | 31.7 |
| Run 146 | 29.5 |
| Run 147 | 29.5 |
| Run 148 | 29.2 |
| Run 149 | 28.1 |
| Run 150 | 27 |
| Run 151 | 29.8 |
| Run 152 | 30.8 |
| Run 153 | 33 |
| Run 154 | 27.2 |
| Run 155 | 29.8 |
| Run 156 | 29.9 |
| Run 157 | 29.7 |
| Run 158 | 29 |
| Run 159 | 29.4 |
| Run 160 | 30.1 |
| Run 161 | 28 |
| Run 162 | 31.8 |
| Run 163 | 29.6 |
| Run 164 | 31.6 |
| Run 165 | 28.5 |
| Run 166 | 30.8 |
| Run 167 | 27.4 |
| Run 168 | 29.9 |
| Run 169 | 30.2 |
| Run 170 | 29 |
| Run 171 | 33 |
| Run 172 | 26.7 |
| Run 173 | 31.2 |
| Run 174 | 30.7 |
| Run 175 | 31 |
| Run 176 | 30.1 |
| Run 177 | 29.5 |
| Run 178 | 29.6 |
| Run 179 | 27.8 |
| Run 180 | 28.1 |
| Run 181 | 29.1 |
| Run 182 | 28.4 |
| Run 183 | 31.7 |
| Run 184 | 28.8 |
| Run 185 | 30.5 |
| Run 186 | 31.6 |
| Run 187 | 31.5 |
| Run 188 | 29.9 |
| Run 189 | 29.6 |
| Run 190 | 27.6 |
| Run 191 | 31.4 |
| Run 192 | 29.6 |
| Run 193 | 28.7 |
| Run 194 | 29 |
| Run 195 | 27.6 |
| Run 196 | 32.6 |
| Run 197 | 33.3 |
| Run 198 | 30.5 |
| Run 199 | 29.5 |
| Run 200 | 28 |
- Ranges
for example building works 10, 13, 16 weeks; asbestos 2, 3, 4 - Run many times
each run draws a duration for every activity and adds the critical path - By week 30 (month 7)
runs finishing by week 30 ÷ all runs= about 60% - By week 32 (mid-month 8)
= about 94% - Middle result
median of the runs= about 30 weeks
Try it yourself in a spreadsheet
| One random number (cell C2) | =RAND() |
| One triangular draw from it | =IF(C2<(m-a)/(b-a), a+SQRT(C2*(b-a)*(m-a)), b-SQRT((1-C2)*(b-a)*(b-m))) (a best, m most likely, b worst) |
| Share by week 30 | =COUNTIF(B2:B201,"<=30")/200 |
What share of the 200 runs finish by week 32?
Show the answer
=COUNTIF(B2:B201,"<=32")/200: about 94%.
Situation 3 of 3
15:00 · Risk appetite with AtticusWhat do you agree?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Expected value
- Probability × impact gives the expected value of a risk.
- Comparing expected values of options, often drawn as a decision tree, helps choose under uncertainty.
Where you will meet this: Expected monetary value (EMV) · decision tree analysis
How sure is the date?
- Running the schedule many times with each activity's range of durations shows how likely each finish date is.
- Report confidence levels, such as 60% by month 7, over 90% by mid-month 8.
Where you will meet this: Monte Carlo simulation · quantitative risk analysis
Risk appetite
- How much risk the organisation is willing to accept, often different per area: low for safety and law, higher for extras.
- It guides every risk decision.
Where you will meet this: Risk appetite · risk thresholds · risk management plan
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 17 complete
3 situations today.
- Expected value (probability × impact) helps compare choices under uncertainty. A decision tree shows the options and their outcomes.
- Simulating the schedule with ranges shows how likely each date is. Confidence levels are more honest than one date.
- Agree how much risk is acceptable in each area, and write it down. It guides every risk decision afterwards.