Day 19 of 46Stage 2 · PlanningMondayQuality and communication plans

Good enough, and who hears what

What does “quality” mean for a clinic, and how will 12 people and a whole district stay informed?

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Team
Antonia (Quality and Compliance Lead) Aya (Project Coordinator)
Stakeholders
Amani (Clinical Lead)
Documents today Communication plan
How the day goes
  1. 09:00Quality workshop with Amani (Clinical Lead) and Antonia (Compliance Lead)
  2. 11:00Acceptance tests with Antonia (Compliance Lead)
  3. 14:00Communication plan with Aya (Project Coordinator)
  4. 16:00Review the meeting rhythm

Situation 1 of 3

09:00 · Quality workshop with Amani (Clinical Lead) and Antonia (Compliance Lead)
Amani (Clinical Lead)senior user
Quality means the best of everything: top equipment, marble floors, the latest scanners.

How do you define quality for the project?

Quality is meeting the requirements and being fit for use, not being the most expensive. Define how each deliverable will be accepted.

Situation 2 of 3

11:00 · Acceptance tests with Antonia (Compliance Lead)
Antonia (Quality and Compliance Lead)
When do we check quality? At the end, when the clinic is finished?

How do you plan quality checks?

Plan quality checks throughout the project, not only at the end. Preventing and catching defects early is far cheaper.

Situation 3 of 3

14:00 · Communication plan with Aya (Project Coordinator)
Aya (Project Coordinator)
With 12 people on the team, that's 66 different conversations that could go wrong. How do we keep everyone informed?

What goes into the communication plan?

Plan communication per audience: what, how, how often and who. Communication channels grow fast as people are added.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Quality is fitness for purpose

  • Quality means meeting the requirements and being fit for use. Grade is the level of features or luxury.
  • Low grade can be fine; low quality never is. Extra features nobody asked for are gold-plating.

Where you will meet this: Quality vs grade · gold-plating

Common practice

Quality checks throughout

  • Plan reviews, inspections and tests at each step, not only at the end.
  • The later a defect is found, the more it costs to fix.

Where you will meet this: Quality planning · quality control · cost of quality

Concept

The communication plan

  • For each audience: what they need, in what format, how often, and who sends it.
  • With n people there are n × (n − 1) ÷ 2 possible channels, so communication needs a plan.

Where you will meet this: Communication management plan · communication channels

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 19 complete

3 situations today.

Your responsibility todayPlanning quality and communication
Technique you usedAcceptance criteria, quality checks, communication plan
Key points to remember
  • Quality is meeting the requirements and being fit for use, not being the most expensive. Define how each deliverable will be accepted.
  • Plan quality checks throughout the project, not only at the end. Preventing and catching defects early is far cheaper.
  • Plan communication per audience: what, how, how often and who. Communication channels grow fast as people are added.
Documents today Communication plan