Closing and transition · cheat sheet

Hypercare

A short, planned period after going live where project and operations staff work side by side to fix teething problems quickly.

Common practice
5 steps
Used by Project Manager

What it is

A short, planned period after go-live where project and operations staff work side by side to fix teething problems fast.

When to use it

The first weeks after going live.

Why it works

The first days after go-live expose problems nobody predicted. Fast fixes protect users and the new team's confidence.

Do

  • End it on the agreed date, or operations never fully own the result.

Don't

  • Disappearing on go-live day.
  • Never ending it, so operations never take full ownership.

Step by step

  1. Agree the length Often two to six weeks.
  2. Place people where problems appear Front desk, systems, phones.
  3. Log every issue Fix urgent ones the same day.
  4. Hand lasting fixes to operations With documentation.
  5. End on the agreed date Open items owned by operations.
Also called: Early life support, post-go-live supportPrint the blank template ↗

Worked example

The situation. Day one at a new clinic.

  1. 40 calls waiting; second line opened and call-backs added by 11:00.
  2. Joint support for four weeks, then the project stepped back.

The result. Operations took full ownership in week 5 with no open urgent issues.

Hypercare log Print blank
DateIssueUrgencyFixed byLasting fix ownerClosed

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

On opening day 40 calls wait on the phone line. Project and clinic staff open a second line and a call-back option; the queue is under 10 by 11:00. Joint support lasts four weeks.

Questions people ask

Is hypercare part of the project?

Usually yes, as the last part of the project's work.

Related techniques