The change request
Amani (Clinical Lead)'s wall change comes back, properly this time. Assess its impact, get the right people to decide, and make sure everything is updated.
Stage goal: Keep the project on track and control every change.
Team
Aya (Project Coordinator)
Stakeholders
Amani (Clinical Lead) Arash (Contractor Project Manager)
How the day goes
- 09:00Log Amani (Clinical Lead)'s change request
- 11:00Impact analysis with Arash (Contractor) and Aya (Project Coordinator)
- 14:00Change board
- 16:00Update plans and tell everyone
Situation 1 of 3
09:00 · Log Amani (Clinical Lead)'s change requestAmani (Clinical Lead)senior user
We need those two walls moved: the treatment area is too cramped for a wheelchair and a trolley. It's important.
What do you do with the request?
Every change is logged and its impact assessed before a decision, however good the reason.
Situation 2 of 3
11:00 · Impact analysis with Arash (Contractor) and Aya (Project Coordinator)Arash (Contractor Project Manager)
Moving the walls means €18,000 and about a week, because the ventilation in that area moves too.
Who decides, and how?
The right people decide changes, based on the impact and options. Who decides depends on the size of the impact, as agreed in the plan.
Situation 3 of 3
16:00 · Update plans and tell everyoneAya (Project Coordinator)
It's approved. Arash (Contractor) can start Monday. Are we done?
What else must happen?
An approved change isn't finished until the plans, baselines, contracts and people are all updated.
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Concept
Change requests
- Every proposed change to scope, time, cost or quality is written down with its reason.
- It isn't done until it's assessed and decided, however small or obviously right it seems.
Where you will meet this: Change request · request for change
Common practice
Impact analysis
- Before deciding, look at what the change does to scope, time, cost, quality, risk and other work.
- Include options, such as doing it later or in a different way.
Where you will meet this: Impact assessment
Concept
Integrated change control
- One process for all changes: log, assess, decide (by the right person or board), then update every plan, baseline and contract affected.
- Who decides depends on the size of the impact, as agreed in the plan.
Where you will meet this: Perform integrated change control (PMI) · change control approach (PRINCE2) · change control board
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 33 complete
3 situations today.
Your responsibility todayControlling change
Technique you usedChange requests, impact analysis, change board
Key points to remember
- Every change is logged and its impact assessed before a decision, however good the reason.
- The right people decide changes, based on the impact and options. Who decides depends on the size of the impact, as agreed in the plan.
- An approved change isn't finished until the plans, baselines, contracts and people are all updated.