Day 20 of 46Stage 2 · PlanningTuesdayBaselines and plan approval

Signing off the plan

The plan is ready. Then the mayor asks for the clinic one month earlier. Show the options, agree the baselines, start building.

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Team
Aya (Project Coordinator) Adaugo (HR and Training Lead)
Stakeholders
Atticus (Director of Community Health) Adeline (Portfolio Manager)
How the day goes
  1. 09:00Final plan review with Aya (Project Coordinator)
  2. 11:00Project board: plan approval
  3. 14:00Atticus (Sponsor) asks for an earlier opening
  4. 16:00Baselines set; brief the team

Situation 1 of 4

14:00 · Atticus (Sponsor) asks for an earlier opening
Atticus (Director of Community Health)sponsor
The mayor wants the opening in month 6, before the summer. Make it happen.

How do you respond?

To shorten a schedule you can add resources to critical work (crashing) or overlap activities (fast-tracking). Both cost money or add risk; the sponsor decides.
Worked example 1

What would an earlier opening cost?

Options to gain weeks on the critical path for an opening in month 6.

OptionWeeks gainedExtra cost (€)Cost per week (€)Risk
Second building crew (crashing)412000030000Low
Overlap fit-out with building works (fast-tracking)300Rework: 25% chance of €60,000
Both512000024000Rework risk remains
Download the data (spreadsheet file)
  1. Crashing€120,000 ÷ 4 weeks= €30,000 a week
  2. Fast-trackingno direct cost; expected rework 0.25 × €60,000= €15,000 expected
  3. Only critical activitiescompressing anything with float gains nothing
What it meansWeeks can be bought, at a price or with risk. Only work on the critical path is worth compressing.
What Annelise decidesAtticus (Sponsor) keeps month 7 and holds a public “first look” event in month 6 instead.
Try it yourself in a spreadsheet
Cost per week=C2/B2

Why not compress hiring to open earlier?

Show the answer

Hiring has 5 weeks of float; it isn't on the critical path, so shortening it gains no time.

Situation 2 of 4

16:00 · Baselines set; brief the team
Aya (Project Coordinator)
Once the plan is approved, we'll just update it whenever something changes, right?

What happens to the plan after approval?

Approved baselines are the yardstick for progress. Forecasts change freely; baselines change only through change control.

Situation 3 of 4

16:00 · Baselines set; brief the team
Adaugo (HR and Training Lead)
Do you need my detailed plan for hiring in month 5 right now? Half of it depends on who we hire first.

How much detail does the plan need for later months?

Plan near-term work in detail and later work in outline, adding detail as you learn (progressive elaboration, or rolling-wave planning).

Situation 4 of 4

11:00 · Project board: plan approval
Adeline (Portfolio Manager)
Two things. The council's project office needs your plan in our standard format for the portfolio report. And the digital health programme says the patient-record link your booking system needs will be a month late.

How do you handle these?

Projects sit inside programmes and portfolios: follow the project office's standards and manage dependencies on other work with owners on both sides.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Shortening a schedule

  • Crashing adds resources to critical activities; it costs money.
  • Fast-tracking overlaps activities that would normally run one after another; it adds risk of rework. The sponsor weighs the trade-off.

Where you will meet this: Schedule compression · crashing · fast-tracking

Concept

Baselines

  • The approved scope, schedule and budget become baselines: the yardstick for measuring progress.
  • Forecasts change as you learn; baselines only change through approved change requests.

Where you will meet this: Scope, schedule and cost baselines · performance measurement baseline

Concept

Plan in waves

  • Plan the near term in detail and later work in outline.
  • Add detail as information arrives, usually at the end of each stage.

Where you will meet this: Progressive elaboration · rolling-wave planning · stage plans (PRINCE2)

Concept

Projects, programmes, portfolios and the project office

  • A programme groups related projects that together deliver a bigger change, such as digital health across the council. A portfolio is everything an organisation chooses to fund, ranked against its strategy.
  • A project management office (PMO) sets common methods and templates, collects reports and supports project managers.
  • Dependencies between projects are managed like risks: written down, with an owner on each side and a date to check.

Where you will meet this: Programme management · portfolio management · PMO

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 20 complete

4 situations today.

Your responsibility todayGetting the plan approved
Technique you usedSchedule compression, baselines, rolling-wave planning
Key points to remember
  • To shorten a schedule you can add resources to critical work (crashing) or overlap activities (fast-tracking). Both cost money or add risk; the sponsor decides.
  • Approved baselines are the yardstick for progress. Forecasts change freely; baselines change only through change control.
  • Plan near-term work in detail and later work in outline, adding detail as you learn (progressive elaboration, or rolling-wave planning).
  • Projects sit inside programmes and portfolios: follow the project office's standards and manage dependencies on other work with owners on both sides.