Signing off the plan
The plan is ready. Then the mayor asks for the clinic one month earlier. Show the options, agree the baselines, start building.
- 09:00Final plan review with Aya (Project Coordinator)
- 11:00Project board: plan approval
- 14:00Atticus (Sponsor) asks for an earlier opening
- 16:00Baselines set; brief the team
Situation 1 of 4
14:00 · Atticus (Sponsor) asks for an earlier openingHow do you respond?
What would an earlier opening cost?
Options to gain weeks on the critical path for an opening in month 6.
| Option | Weeks gained | Extra cost (€) | Cost per week (€) | Risk |
|---|---|---|---|---|
| Second building crew (crashing) | 4 | 120000 | 30000 | Low |
| Overlap fit-out with building works (fast-tracking) | 3 | 0 | 0 | Rework: 25% chance of €60,000 |
| Both | 5 | 120000 | 24000 | Rework risk remains |
- Crashing
€120,000 ÷ 4 weeks= €30,000 a week - Fast-tracking
no direct cost; expected rework 0.25 × €60,000= €15,000 expected - Only critical activities
compressing anything with float gains nothing
Try it yourself in a spreadsheet
| Cost per week | =C2/B2 |
Why not compress hiring to open earlier?
Show the answer
Hiring has 5 weeks of float; it isn't on the critical path, so shortening it gains no time.
Situation 2 of 4
16:00 · Baselines set; brief the teamWhat happens to the plan after approval?
Situation 3 of 4
16:00 · Baselines set; brief the teamHow much detail does the plan need for later months?
Situation 4 of 4
11:00 · Project board: plan approvalHow do you handle these?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Shortening a schedule
- Crashing adds resources to critical activities; it costs money.
- Fast-tracking overlaps activities that would normally run one after another; it adds risk of rework. The sponsor weighs the trade-off.
Where you will meet this: Schedule compression · crashing · fast-tracking
Baselines
- The approved scope, schedule and budget become baselines: the yardstick for measuring progress.
- Forecasts change as you learn; baselines only change through approved change requests.
Where you will meet this: Scope, schedule and cost baselines · performance measurement baseline
Plan in waves
- Plan the near term in detail and later work in outline.
- Add detail as information arrives, usually at the end of each stage.
Where you will meet this: Progressive elaboration · rolling-wave planning · stage plans (PRINCE2)
Projects, programmes, portfolios and the project office
- A programme groups related projects that together deliver a bigger change, such as digital health across the council. A portfolio is everything an organisation chooses to fund, ranked against its strategy.
- A project management office (PMO) sets common methods and templates, collects reports and supports project managers.
- Dependencies between projects are managed like risks: written down, with an owner on each side and a date to check.
Where you will meet this: Programme management · portfolio management · PMO
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 20 complete
4 situations today.
- To shorten a schedule you can add resources to critical work (crashing) or overlap activities (fast-tracking). Both cost money or add risk; the sponsor decides.
- Approved baselines are the yardstick for progress. Forecasts change freely; baselines change only through change control.
- Plan near-term work in detail and later work in outline, adding detail as you learn (progressive elaboration, or rolling-wave planning).
- Projects sit inside programmes and portfolios: follow the project office's standards and manage dependencies on other work with owners on both sides.