Scope and scheduling · cheat sheet

Work breakdown (decomposition)

Splitting the whole scope into deliverables, then into smaller pieces, until each piece can be estimated, scheduled and owned.

Common practice
6 steps
Used by Project Manager

What it is

Breaking the whole scope of a project into deliverables, then into smaller pieces, until each piece can be estimated, scheduled and owned. The result is a tree called a work breakdown structure (WBS).

When to use it

In planning, after the scope is agreed. Also useful any time a piece of work feels too big to estimate.

Why it works

It makes sure all the work is included exactly once. Schedules, budgets, responsibilities and risks are all built on it, so gaps in the WBS become gaps everywhere.

Do

  • Nouns, not verbs: “Training materials”, not “write training materials”.
  • Stop splitting when more detail wouldn't change how you manage it.

Don't

  • Mixing activities and deliverables.
  • Forgetting project management work itself.
  • Going so deep that tracking costs more than doing.

Step by step

  1. Start with the whole Put the project or main deliverable at the top.
  2. Split into major deliverables Usually 4 to 8 nouns (things, not activities). Include project management as its own branch.
  3. Keep splitting Break each deliverable into smaller pieces until each can be estimated, given to one owner and done in a reasonable time.
  4. Apply the 100% rule The children of each box add up to exactly the parent: nothing missing, nothing extra.
  5. Number every box 1, 1.1, 1.1.1 so everyone refers to the same thing.
  6. Write a short dictionary For important pieces: what's included, acceptance criteria, owner, estimate.
Also called: WBS, product breakdownPrint the blank template ↗

Worked example

The situation. Organising a two-day company conference.

  1. 1 Venue · 2 Programme · 3 Speakers · 4 Attendees · 5 Catering · 6 Communication · 7 Project management.
  2. 2 Programme splits into 2.1 Agenda, 2.2 Workshops, 2.3 Evening event.
  3. Each lowest box gets an owner and an estimate.

The result. Catering for the evening event, nearly forgotten, appeared as its own box and got an owner.

Work breakdown worksheet Print blank
CodeDelive­rableIncludes
1VenueBooking, layout, AV
2ProgrammeAgenda, workshops, evening event
3SpeakersInvites, travel, briefing
7Project managementPlan, budget, reporting

Filled in for: Organising a two-day company conference.

CodeDelive­rable or work packageOwnerEstimate

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

Annelise (Project Manager) and the leads break the clinic into 1 Building, 2 Equipment, 3 Booking system, 4 People, 5 Licence and opening, 6 Project management, then each into work packages such as 1.2 Asbestos removal.

Questions people ask

Is a WBS a schedule?

No. It shows what; the schedule shows when and in what order.