Work breakdown (decomposition)
Splitting the whole scope into deliverables, then into smaller pieces, until each piece can be estimated, scheduled and owned.
What it is
Breaking the whole scope of a project into deliverables, then into smaller pieces, until each piece can be estimated, scheduled and owned. The result is a tree called a work breakdown structure (WBS).
When to use it
In planning, after the scope is agreed. Also useful any time a piece of work feels too big to estimate.
Why it works
It makes sure all the work is included exactly once. Schedules, budgets, responsibilities and risks are all built on it, so gaps in the WBS become gaps everywhere.
Do
- Nouns, not verbs: “Training materials”, not “write training materials”.
- Stop splitting when more detail wouldn't change how you manage it.
Don't
- Mixing activities and deliverables.
- Forgetting project management work itself.
- Going so deep that tracking costs more than doing.
Step by step
- Start with the whole Put the project or main deliverable at the top.
- Split into major deliverables Usually 4 to 8 nouns (things, not activities). Include project management as its own branch.
- Keep splitting Break each deliverable into smaller pieces until each can be estimated, given to one owner and done in a reasonable time.
- Apply the 100% rule The children of each box add up to exactly the parent: nothing missing, nothing extra.
- Number every box 1, 1.1, 1.1.1 so everyone refers to the same thing.
- Write a short dictionary For important pieces: what's included, acceptance criteria, owner, estimate.