Stakeholders · cheat sheet

Stakeholder map (power and interest)

Place each stakeholder by how much influence they have and how much they care, then engage each group differently.

Common practice
6 steps
Used by Project Manager, Product Owner, Scrum Master, Process Improvement Specialist

What it is

A stakeholder map places everyone affected by, or able to affect, your work on a simple grid: how much influence they have, and how interested they are.

The four boxes suggest how to involve each group: manage closely (high, high), keep satisfied (high influence, low interest), keep informed (low influence, high interest) and monitor (low, low).

When to use it

At the start, and whenever new people appear or someone's interest changes.

Variations

  • Engagement assessment compares how engaged each person is now with how engaged you need them to be.
  • Salience model adds urgency and legitimacy to power.

Why it works

You can't give everyone the same attention. The map helps you spend your time where it matters, and makes sure nobody important is forgotten.

It also shows risks: a powerful person who isn't interested yet can suddenly block you.

Do

  • Don't ignore end users just because they look low-influence; their reaction decides whether the result is used.
  • Keep the map private if it contains frank views.

Don't

  • Making the map once and forgetting it.
  • Ignoring end users because they look low-influence.

Step by step

  1. Brainstorm everyone With the team, list people and groups who are affected or can affect the work: users, managers, finance, legal, suppliers, regulators, neighbours. Use checklists and past projects.
  2. Rate influence and interest For each, ask: can they change or stop the work? How much do they care about it? Use high, medium, low.
  3. Place them on the grid Draw the four boxes and write names in them. Discuss disagreements; they often reveal something important.
  4. Decide how to engage each box Manage closely: regular personal contact. Keep satisfied: short updates on what matters to them. Keep informed: regular news. Monitor: light touch.
  5. Turn it into actions Add owners and channels, often in a stakeholder register or communication plan.
  6. Revisit it People move boxes. Update the map at each stage or when something changes.
Also called: Power/interest grid, stakeholder matrixPrint the blank template ↗

Worked example

The situation. A council plans to close a road for six months to build a new tram line.

  1. Mapped: residents, shop owners, bus company, emergency services, the mayor, the transport regulator.
  2. Emergency services: high influence, low interest at first. Kept satisfied with early route planning.
  3. Shop owners: medium influence, very high interest. Kept informed weekly, with a named contact.

The result. Emergency routes were agreed before the closure, and shop complaints dropped after the weekly updates started.

Stakeholder map Print blank
Stakehol­derInflue­nce (H/M/L)Interest (H/M/L)BoxHow we engageOwner

Copy this structure, or print the blank version and fill it in by hand. Boxes: manage closely · keep satisfied · keep informed · monitor.

In the roles

How a Project Manager uses it

On day one, Annelise (Project Manager) lists everyone the Riverside clinic touches: the council, finance, doctors, residents, the contractor. In initiating, a team workshop adds the health authority inspector (high influence, low interest: keep satisfied), the warehouse neighbours and the nurses' union.

How a Product Owner uses it

Adam (CEO): high influence, high interest, manage closely. Ali (Sales) and Amelia (Marketing): high interest, involve regularly. Aisha (Customer): high interest, keep close through tests and interviews. Finance: high influence, low interest, short updates.

How a Scrum Master uses it

Aaron (Scrum Master) maps Adam (high influence, needs coaching), Abel (IT Operations Manager) in IT (high influence on impediments, build a relationship), Astrid (other team, regular contact).

How a Process Improvement Specialist uses it

GPs, reception, nurses, the council and residents mapped by influence and interest; reception and GPs need the closest involvement.

Questions people ask

How often should I update it?

At least at each stage, and whenever someone new appears or an attitude changes.

Related techniques

← All techniques and tools