Are we on track?
End of month 4. Everyone says things are “fine”. Measure progress properly, find the colour that's really true, and write the status report.
- 09:00Progress figures with Aya (Project Coordinator) and Abigail (Finance)
- 11:00Booking system check with Aya (Project Coordinator) and the new IT lead
- 14:00Write the status report
- 16:00Send it to Atticus (Sponsor)
Situation 1 of 3
09:00 · Progress figures with Aya (Project Coordinator) and Abigail (Finance)Is the project under budget?
Earned value at month 4
Planned value from the S-curve, earned value from work actually done, actual cost from finance (€ thousands). Budget at completion €4,050k.
| Measure | Value (€k) |
|---|---|
| Planned value (PV) | 2400 |
| Earned value (EV) | 2200 |
| Actual cost (AC) | 2250 |
- Schedule variance
EV − PV = 2,200 − 2,400= −200: behind - Cost variance
EV − AC = 2,200 − 2,250= −50: slightly over - Schedule performance index
EV ÷ PV= 0.92 - Cost performance index
EV ÷ AC= 0.98 - Forecast if efficiency continues
budget ÷ CPI = 4,050 ÷ 0.978= about €4,142k
Try it yourself in a spreadsheet
| SPI | =B3/B2 |
| CPI | =B3/B4 |
| Forecast | =4050/(B3/B4) |
What CPI would the rest of the work need to finish on the €4,050k budget?
Show the answer
(4,050 − 2,200) ÷ (4,050 − 2,250) = 1.03: harder than today's 0.98.
Situation 2 of 3
11:00 · Booking system check with Aya (Project Coordinator) and the new IT leadWhat colour is it really?
Situation 3 of 3
16:00 · Send it to Atticus (Sponsor)What goes in the status report?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Earned value
- Three numbers: planned value (work planned by now), earned value (work actually done, valued at its budget) and actual cost.
- Earned value ÷ planned value shows schedule performance; earned value ÷ actual cost shows cost performance. Below 1 means behind or over.
Where you will meet this: Earned value management · SPI · CPI · SV · CV
Status colours with rules
- Red, amber and green only help if everyone uses the same rules, for example amber = recoverable within tolerance with a plan.
- A report that's green outside and red inside (a “watermelon”) hides problems until it's too late.
Where you will meet this: RAG status
The status report
- Short and honest: overall status and why, progress against the baselines, what's done and next, top risks and issues, and decisions needed.
- The detail lives in the logs; the report points to what matters.
Where you will meet this: Status report · highlight report (PRINCE2) · work performance reports
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 32 complete
3 situations today.
- Measure progress by the value of work done, not money spent. Planned value, earned value and actual cost together show schedule and cost performance.
- Status colours need agreed rules and honest use. Reporting green while things fail removes leaders' chance to help.
- A good status report is short, honest and compares progress with the baselines. It ends with what's needed from the reader.