Day 32 of 46Stage 4 · Monitoring and controllingTuesdayStatus, earned value and honest reporting

Are we on track?

End of month 4. Everyone says things are “fine”. Measure progress properly, find the colour that's really true, and write the status report.

Stage goal: Keep the project on track and control every change.
Team
Aya (Project Coordinator)
Stakeholders
Abigail (Finance Business Partner) Atticus (Director of Community Health)
How the day goes
  1. 09:00Progress figures with Aya (Project Coordinator) and Abigail (Finance)
  2. 11:00Booking system check with Aya (Project Coordinator) and the new IT lead
  3. 14:00Write the status report
  4. 16:00Send it to Atticus (Sponsor)

Situation 1 of 3

09:00 · Progress figures with Aya (Project Coordinator) and Abigail (Finance)
Abigail (Finance Business Partner)
We've spent €2.25M and the plan said €2.4M by now. So we're under budget, right?

Is the project under budget?

Measure progress by the value of work done, not money spent. Planned value, earned value and actual cost together show schedule and cost performance.
Worked example 1

Earned value at month 4

Planned value from the S-curve, earned value from work actually done, actual cost from finance (€ thousands). Budget at completion €4,050k.

Planned value, earned value and actual cost, € thousands06251,2501,8752,500PV: 2,4002,400PVEV: 2,2002,200EVAC: 2,2502,250AC
MeasureValue (€k)
Planned value (PV)2400
Earned value (EV)2200
Actual cost (AC)2250
Download the data (spreadsheet file)
  1. Schedule varianceEV − PV = 2,200 − 2,400= −200: behind
  2. Cost varianceEV − AC = 2,200 − 2,250= −50: slightly over
  3. Schedule performance indexEV ÷ PV= 0.92
  4. Cost performance indexEV ÷ AC= 0.98
  5. Forecast if efficiency continuesbudget ÷ CPI = 4,050 ÷ 0.978= about €4,142k
What it meansThe project has done less than planned (92%) and each euro buys 98 cents of planned work. Spending less than planned did not mean being under budget.
What Annelise decidesStatus amber for time with a recovery plan; cost green, forecast inside the €4.2M baseline.
Try it yourself in a spreadsheet
SPI=B3/B2
CPI=B3/B4
Forecast=4050/(B3/B4)

What CPI would the rest of the work need to finish on the €4,050k budget?

Show the answer

(4,050 − 2,200) ÷ (4,050 − 2,250) = 1.03: harder than today's 0.98.

Situation 2 of 3

11:00 · Booking system check with Aya (Project Coordinator) and the new IT lead
Aya (Project Coordinator)
The booking system is green on the dashboard. But the new IT lead says half the test bookings fail.

What colour is it really?

Status colours need agreed rules and honest use. Reporting green while things fail removes leaders' chance to help.

Situation 3 of 3

16:00 · Send it to Atticus (Sponsor)
Atticus (Director of Community Health)sponsor
Just send me a short status. Keep it positive.

What goes in the status report?

A good status report is short, honest and compares progress with the baselines. It ends with what's needed from the reader.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Earned value

  • Three numbers: planned value (work planned by now), earned value (work actually done, valued at its budget) and actual cost.
  • Earned value ÷ planned value shows schedule performance; earned value ÷ actual cost shows cost performance. Below 1 means behind or over.

Where you will meet this: Earned value management · SPI · CPI · SV · CV

Common practice

Status colours with rules

  • Red, amber and green only help if everyone uses the same rules, for example amber = recoverable within tolerance with a plan.
  • A report that's green outside and red inside (a “watermelon”) hides problems until it's too late.

Where you will meet this: RAG status

Common practice

The status report

  • Short and honest: overall status and why, progress against the baselines, what's done and next, top risks and issues, and decisions needed.
  • The detail lives in the logs; the report points to what matters.

Where you will meet this: Status report · highlight report (PRINCE2) · work performance reports

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 32 complete

3 situations today.

Your responsibility todayMeasuring and reporting progress
Technique you usedEarned value, RAG status rules, the status report
Key points to remember
  • Measure progress by the value of work done, not money spent. Planned value, earned value and actual cost together show schedule and cost performance.
  • Status colours need agreed rules and honest use. Reporting green while things fail removes leaders' chance to help.
  • A good status report is short, honest and compares progress with the baselines. It ends with what's needed from the reader.