Monitoring and control · cheat sheet RAG status Showing status as red, amber or green per area, using rules everyone has agreed, so the colour means the same to everyone.
Common practice 5 steps Used by Project Manager
What it is Showing status as red, amber or green per area, using rules everyone has agreed, with a one-line reason.
When to use it In status reports and dashboards, every reporting period.
Why it works It gives leaders a quick, comparable view, but only if the colours mean the same thing to everyone.
Do A watermelon (green outside, red inside) report destroys trust when it's discovered. Don't “Watermelon” reports: green outside, red inside. Colours without reasons. Step by step Agree the rules Green: on plan. Amber: off plan, recoverable within tolerance, with a plan. Red: beyond tolerance or needs a decision.
Rate each area Scope, time, cost, quality, risk.
Add a reason Always one line why.
Report the rule's colour Not the comfortable one.
Watch trends Amber for many weeks is a warning too.
Worked example The situation. A booking system shows green while half the tests fail.
Rule check: off plan but recoverable with a plan → amber. Recovery plan by Friday. The result. The sponsor offered help a week earlier than he would otherwise have known.
Area Status Why Scope Green No unapproved changes Time Amber 2 weeks behind, recovery plan Quality Amber Tests at 50% pass
Filled in for: A booking system shows green while half the tests fail.
Area Red Amber Green Why Action
Copy this structure, or print the blank version and fill it in by hand. Green: on plan · Amber: off plan, recoverable within tolerance, with a plan · Red: beyond tolerance or needs a decision.
In the roles How a Project Manager uses itThe booking system is green on the dashboard while half the test bookings fail. With the agreed rules it becomes amber, with a recovery plan by Friday.
Questions people ask Should we add blue for complete? Some teams do; keep the rules written down.