Governance and roles · cheat sheet

RACI

A simple way to say who is Responsible, Accountable, Consulted and Informed for each piece of work or decision.

Common practice
6 steps
Used by Project Manager, Process Improvement Specialist

What it is

A RACI chart is a grid. Down the side are the pieces of work or decisions; across the top are people or roles. In each cell you write one letter: R, A, C or I.

R (Responsible) does the work. A (Accountable) owns the result and signs it off; there is exactly one per row. C (Consulted) is asked for input before. I (Informed) is told after.

When to use it

When several people or organisations work on the same deliverables, or when ownership is unclear or disputed.

Variations

  • RASCI adds S for Support: people who help the responsible person.
  • DACI Driver, Approver, Contributors, Informed: used for decisions rather than deliverables.
  • Delegation levels a finer scale for how much a team decides on its own.

Why it works

Most project friction comes from unclear ownership: two people both think they decide, or nobody does. A RACI makes the assumptions visible so they can be agreed before they cause trouble.

Because each row has exactly one A, the chart also tells you who to go to when something about that deliverable needs a decision.

Do

  • Build it with the people named, not alone at your desk.
  • When someone is accountable for everything, nobody else feels accountable for anything.
  • Keep it to one page; link to it from the project plan.

Don't

  • Two people accountable for one thing, or nobody.
  • Consulting everyone on everything.
  • Making the chart alone and announcing it.

Step by step

  1. List what needs owning Write the main deliverables and the recurring decisions, one per row. Ten to twenty rows is usually enough; more detail rarely helps.
  2. List the people or roles Use roles where people may change, names where it helps. Include suppliers and approvers, not just the core team.
  3. Fill in A first For each row, agree who is accountable. If two people claim it, settle it now with the sponsor. If nobody wants it, that's a risk to raise.
  4. Add R, then C and I Responsible can be several people. Keep C small: every C is someone who can slow a decision down. I is cheap; use it generously.
  5. Check the columns A column full of R's is an overloaded person. A column of only I's may not need to be in the meetings. A column with no letters may be a missing stakeholder.
  6. Agree it, then use it Walk through it with everyone named. Share it, refer to it in disputes, and update it when people or deliverables change.
Also called: Responsibility assignment matrix, RAM, RASCIPrint the blank template ↗

Worked example

The situation. A company is launching a new customer portal with an outside design agency and its own IT team.

  1. Rows: portal design, content, security review, launch date, budget changes.
  2. Two managers both claimed the launch date: the chart made the sponsor accountable and the project manager responsible.
  3. The security review had no A at first. The IT security lead accepted it, so the gap was closed before launch week.

The result. Fewer “I thought you were doing that” moments, and disputes settled by pointing at the chart instead of arguing.

Responsibility chart Print blank
Delive­rable or decisionSponsorProject managerDesign agencyIT security lead
Portal designCIAC
ContentARCI
Security reviewICCA
Launch dateARCC

Filled in for: A company is launching a new customer portal with an outside design agency and its own IT team.

Delive­rable or decisionPerson 1Person 2Person 3Person 4One A?

Copy this structure, or print the blank version and fill it in by hand. Write a name at the top of each column. R = responsible, A = accountable (exactly one per row), C = consulted, I = informed.

In the roles

How a Project Manager uses it

Aine (IT Lead) and Alfonso (Software Vendor Project Manager) both thought they decided the booking system setup. The RACI makes Alfonso responsible, Aine accountable and Amani (Clinical Lead) consulted on clinical workflows.

How a Process Improvement Specialist uses it

Atticus (Sponsor) approves each phase, Aurelie (Practice Nurse Manager) owns the process, Amara (Process Improvement Specialist) leads, the team analyses and tests.

Questions people ask

Can the same person be R and A?

Yes, often for smaller items. The point is that there is one clear A.

Is a RACI an org chart?

No. An org chart shows reporting lines; a RACI shows who does what for specific work, across departments and suppliers.