Running the schedule hundreds of times with each activity's duration picked from its range, to see how likely each finish date is.
Common practice 6 steps Used by Project Manager
What it is
Running a schedule or budget model hundreds or thousands of times, each time picking every uncertain value from its range, to see how likely each result is.
When to use it
When the board needs a confidence level for a date or budget, on projects with uncertain activities.
Why it works
A single date or cost hides uncertainty. Simulation gives honest confidence levels and shows which activities drive the risk.
Do
The answer is only as good as the ranges; ask the people who do the work.
Don't
Presenting the result as more precise than the inputs.
Ignoring dependencies between risks.
Step by step
Give uncertain items rangesBest, likely, worst.
Build the modelThe schedule logic or cost lines.
Run it many timesWith a tool or a spreadsheet.
Read confidence levelsFor example: 50% by date X, 80% by date Y.
Find the driversWhich items affect the result most?
Each critical activity gets a range (best, most likely, worst), and the schedule is run thousands of times. Here are 200 of the runs: weeks to opening.
Step by step
Rangesfor example building works 10, 13, 16 weeks; asbestos 2, 3, 4
Run many timeseach run draws a duration for every activity and adds the critical path
By week 30 (month 7)runs finishing by week 30 ÷ all runs= about 60%