Risk · cheat sheet

Schedule simulation

Running the schedule hundreds of times with each activity's duration picked from its range, to see how likely each finish date is.

Common practice
6 steps
Used by Project Manager

What it is

Running a schedule or budget model hundreds or thousands of times, each time picking every uncertain value from its range, to see how likely each result is.

When to use it

When the board needs a confidence level for a date or budget, on projects with uncertain activities.

Why it works

A single date or cost hides uncertainty. Simulation gives honest confidence levels and shows which activities drive the risk.

Do

  • The answer is only as good as the ranges; ask the people who do the work.

Don't

  • Presenting the result as more precise than the inputs.
  • Ignoring dependencies between risks.

Step by step

  1. Give uncertain items ranges Best, likely, worst.
  2. Build the model The schedule logic or cost lines.
  3. Run it many times With a tool or a spreadsheet.
  4. Read confidence levels For example: 50% by date X, 80% by date Y.
  5. Find the drivers Which items affect the result most?
  6. Act and re-run Reduce the biggest uncertainties.
Also called: Monte Carlo simulation, quantitative schedule riskPrint the blank template ↗

Worked example

The situation. A software release with six uncertain tasks.

  1. 1,000 runs.
  2. 50% confidence: 14 March; 80%: 28 March; 90%: 7 April.
  3. Biggest driver: data migration.

The result. The company announced “early April” and put extra effort into data migration.

Simulation inputs Print blank
Activity or costBestLikelyWorstDepends on

Copy this structure, or print the blank version and fill it in by hand.

Before you use it: check these

CheckIf it fails
Ranges for every uncertain activity, from people who know the workNarrow guesses give false confidence: widen them
Linked risks move togetherModel the link, or the spread will look too small
Enough runs: about 1,000 or moreRun more until the percentages stop changing

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

How likely is month 7?

From Day 17: Putting numbers on risk of the Project Manager story

Each critical activity gets a range (best, most likely, worst), and the schedule is run thousands of times. Here are 200 of the runs: weeks to opening.

Simulated weeks to opening, 200 runs02040608026 to 27: 6627 to 28: 202028 to 29: 424229 to 30: 484830 to 31: 444431 to 32: 252532 to 33: 9933 to 34: 5534 to 35: 035 to 36: 112627282930313233343536Week 30: month 7Week 32

Step by step

  1. Rangesfor example building works 10, 13, 16 weeks; asbestos 2, 3, 4
  2. Run many timeseach run draws a duration for every activity and adds the critical path
  3. By week 30 (month 7)runs finishing by week 30 ÷ all runs= about 60%
  4. By week 32 (mid-month 8)= about 94%
  5. Middle resultmedian of the runs= about 30 weeks
RunWeeks to opening
Run 130.3
Run 228.7
Run 329.8
Run 430.9
Run 532.1
Run 630.4
Run 728.6
Run 828.6
Run 930.2
Run 1029.6
Run 1128
Run 1230.6
Run 1327.8
Run 1430.1
Run 1530.4
Run 1626.9
Run 1729.5
Run 1829.4
Run 1931
Run 2027.6
Run 2130.3
Run 2228.9
Run 2327.4
Run 2430
Run 2530.1
Run 2628.8
Run 2729.6
Run 2828.9
Run 2930.8
Run 3031.3
Run 3130.1
Run 3227.6
Run 3328.9
Run 3428.7
Run 3530.2
Run 3630.2
Run 3730.5
Run 3830.2
Run 3926.9
Run 4028.3
Run 4131
Run 4228.5
Run 4331.3
Run 4427.4
Run 4529.2
Run 4628.2
Run 4729.9
Run 4827.8
Run 4930.3
Run 5030.3
Run 5130
Run 5230.1
Run 5329.6
Run 5432
Run 5530.7
Run 5628.6
Run 5729.6
Run 5829.5
Run 5926.5
Run 6027.6
Run 6128.3
Run 6231.3
Run 6328.6
Run 6426.4
Run 6531
Run 6628.6
Run 6729.3
Run 6830.5
Run 6931.8
Run 7029.5
Run 7132.3
Run 7232.4
Run 7331
Run 7432.6
Run 7527.6
Run 7629.6
Run 7733.2
Run 7828.1
Run 7935
Run 8030
Run 8130.3
Run 8231.1
Run 8328.7
Run 8433.2
Run 8529.4
Run 8630
Run 8728.1
Run 8828.7
Run 8928.7
Run 9029
Run 9128.9
Run 9232.8
Run 9328.5
Run 9430.9
Run 9531.9
Run 9629.5
Run 9728.1
Run 9829.1
Run 9931.7
Run 10027.6
Run 10130.5
Run 10228.7
Run 10328.2
Run 10430.2
Run 10528.7
Run 10628.5
Run 10730.6
Run 10829.5
Run 10929.1
Run 11029.2
Run 11127.4
Run 11230.5
Run 11327.1
Run 11426.3
Run 11532
Run 11629.7
Run 11731.1
Run 11829.6
Run 11931.7
Run 12030
Run 12128.8
Run 12229.6
Run 12329.8
Run 12431.2
Run 12532.1
Run 12627
Run 12731.4
Run 12831.2
Run 12928.9
Run 13029.2
Run 13130
Run 13229.9
Run 13329.4
Run 13430
Run 13528
Run 13630.2
Run 13727.2
Run 13828.7
Run 13929.4
Run 14027.8
Run 14128.2
Run 14228.6
Run 14330.9
Run 14430.5
Run 14531.7
Run 14629.5
Run 14729.5
Run 14829.2
Run 14928.1
Run 15027
Run 15129.8
Run 15230.8
Run 15333
Run 15427.2
Run 15529.8
Run 15629.9
Run 15729.7
Run 15829
Run 15929.4
Run 16030.1
Run 16128
Run 16231.8
Run 16329.6
Run 16431.6
Run 16528.5
Run 16630.8
Run 16727.4
Run 16829.9
Run 16930.2
Run 17029
Run 17133
Run 17226.7
Run 17331.2
Run 17430.7
Run 17531
Run 17630.1
Run 17729.5
Run 17829.6
Run 17927.8
Run 18028.1
Run 18129.1
Run 18228.4
Run 18331.7
Run 18428.8
Run 18530.5
Run 18631.6
Run 18731.5
Run 18829.9
Run 18929.6
Run 19027.6
Run 19131.4
Run 19229.6
Run 19328.7
Run 19429
Run 19527.6
Run 19632.6
Run 19733.3
Run 19830.5
Run 19929.5
Run 20028

How to read the result

Month 7 is a little better than a coin toss; mid-month 8 is very likely. A single date hides that.

What it led to

Atticus (Sponsor) keeps month 7 as the target and announces “autumn” publicly.

Do it in a spreadsheet

One random number (cell C2)=RAND()
One triangular draw from it=IF(C2<(m-a)/(b-a), a+SQRT(C2*(b-a)*(m-a)), b-SQRT((1-C2)*(b-a)*(b-m))) (a best, m most likely, b worst)
Share by week 30=COUNTIF(B2:B201,"<=30")/200
Try it yourself: What share of the 200 runs finish by week 32?

=COUNTIF(B2:B201,"<=32")/200: about 94%.

In the roles

How a Project Manager uses it

Riverside has about a 60% chance of opening in month 7 and over 90% by mid-month 8. The board targets month 7 but announces “autumn”.

Questions people ask

Do I need special software?

Spreadsheet add-ons and many planning tools can do it; for small models a spreadsheet alone works.