Day 18 of 46Stage 2 · PlanningFridayProcurement and contracts

Buying what we need

Most of the clinic is bought, not built. Decide what to buy, what kind of contract to use, and choose suppliers fairly.

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Team
Aine (IT Lead)
Stakeholders
Alder (Procurement Officer)
How the day goes
  1. 09:00Make or buy with Aine (IT Lead)
  2. 11:00Contract types with Alder (Procurement)
  3. 14:00Tender evaluation with Alder (Procurement)
  4. 16:00Draft the statement of work

Situation 1 of 4

09:00 · Make or buy with Aine (IT Lead)
Aine (IT Lead)
My team could build our own booking system. It would fit us perfectly.

Make or buy?

Decide make or buy on whole-life cost, time, risk, skills and support, not on who wants to build it.
Used here Make or buy

Situation 2 of 4

11:00 · Contract types with Alder (Procurement)
Alder (Procurement Officer)
For the building works, should we pay a fixed price, or pay for the time and materials they use?

Which contract type fits?

Fixed price suits clear scope; time and materials suits uncertain work. The contract type decides who carries the cost risk.

Situation 3 of 4

14:00 · Tender evaluation with Alder (Procurement)
Alder (Procurement Officer)
One of the building bids comes from a company owned by Aine (IT Lead)'s cousin.

What should happen?

Buying must be fair and documented: published criteria, declared conflicts of interest, and a recorded decision.
Worked example 1

Scoring the building bids

Three bids scored 1 to 5 against the published criteria and weights (out of 100).

Criterion (weight)Bid ABid BBid C
Price (40)435
Quality of approach (30)352
Experience (20)342
Programme (10)443
Weighted total350390330
Download the data (spreadsheet file)
  1. Bid A4 × 40 + 3 × 30 + 3 × 20 + 4 × 10= 350
  2. Bid B3 × 40 + 5 × 30 + 4 × 20 + 4 × 10= 390
  3. Bid C5 × 40 + 2 × 30 + 2 × 20 + 3 × 10= 330
What it meansBid B wins on quality and experience even though Bid C is cheapest. The published weights make the choice defensible.
What Annelise decidesBid B is recommended; the scores and the conflict-of-interest declaration are filed.
Try it yourself in a spreadsheet
Weighted total=SUMPRODUCT(B2:B5,{40;30;20;10})

If price were weighted 60 and quality 10, which bid would win?

Show the answer

A: 240 + 30 + 60 + 40 = 370; B: 180 + 50 + 80 + 40 = 350; C: 300 + 20 + 40 + 30 = 390. Bid C: weights decide outcomes, so publish them first.

Situation 4 of 4

14:00 · Tender evaluation with Alder (Procurement)
Alder (Procurement Officer)
One of the building bidders has invited you to a box at the cup final next week. “No strings attached,” he says.

What do you do?

Act so nobody could reasonably doubt your fairness: decline gifts during a tender, record offers, declare conflicts.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Make or buy

  • Compare doing the work yourself with buying it: whole-life cost, time, risk, skills and support.
  • Buying a proven product is often cheaper over its life than building a perfect fit.

Where you will meet this: Make-or-buy analysis

Concept

Contract types

  • Fixed price: the supplier carries the cost risk; suits clear scope.
  • Time and materials: the buyer carries it; suits uncertain work, ideally with a cap. Many contracts mix both, sometimes with incentives.

Where you will meet this: Fixed-price · cost-reimbursable · time and materials

Concept

Fair buying

  • Publish the criteria, score every bid against them, and record the decision.
  • Anyone with a conflict of interest declares it and stays out of the evaluation.

Where you will meet this: Procurement · tender evaluation · conflict of interest

Concept

Professional ethics

  • Project managers are trusted with money, information and decisions that affect people. Professional codes ask the same four things: take responsibility, respect people, be fair, be honest.
  • In practice: no gifts that could sway a decision, declare conflicts of interest, report bad news truthfully, and own your mistakes.

Where you will meet this: PMI Code of Ethics and Professional Conduct · IPMA personal integrity and reliability

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 18 complete

4 situations today.

Your responsibility todayBuying goods and services
Technique you usedMake or buy, contract types, tender evaluation
Key points to remember
  • Decide make or buy on whole-life cost, time, risk, skills and support, not on who wants to build it.
  • Fixed price suits clear scope; time and materials suits uncertain work. The contract type decides who carries the cost risk.
  • Buying must be fair and documented: published criteria, declared conflicts of interest, and a recorded decision.
  • Act so nobody could reasonably doubt your fairness: decline gifts during a tender, record offers, declare conflicts.