Risk · cheat sheet

Reserve analysis

Checking how much contingency and management reserve has been used, how much is left, and whether it still covers the risks that remain.

Common practice
5 steps
Used by Project Manager

What it is

Checking how much contingency and management reserve has been used, how much is left, and whether it covers the risks still open.

When to use it

At every risk review and stage end, and whenever contingency is used.

Why it works

Reserves run out quietly. Regular checks show early whether you'll need more, or can release some.

Do

  • Contingency is for risks, not for new scope.

Don't

  • Spending contingency on new scope.
  • Not noticing contingency running out until it's gone.

Step by step

  1. Start from the reserves Contingency (known risks) and management reserve (unknown).
  2. Record each use Which risk or change it paid for.
  3. Compare what's left with open risks Their likely cost.
  4. Release what's no longer needed When risks pass.
  5. Escalate early If it looks too small.
Also called: Contingency tracking, contingency drawdownPrint the blank template ↗

Worked example

The situation. A €150,000 contingency halfway through a project.

  1. Used: €40,000.
  2. Open risks worth about €70,000.
  3. Remaining €110,000: enough with a margin.

The result. The sponsor was confident the project wouldn't need the reserve.

Reserve tracker Print blank
DateUsed forAmountRemai­ning
Month 4Damp repairs20,000130,000
Month 5Wall change18,000112,000
Month 5Extra receptionist2,000110,000

Filled in for: A €150,000 contingency halfway through a project.

DateUsed for (risk or change)AmountRemai­ningApproved by

Copy this structure, or print the blank version and fill it in by hand.

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

From bottom-up estimate to total funding

From Day 14: What will it cost? of the Project Manager story

Each part of the work breakdown is estimated from quotes and the survey (€ thousands).

Bottom-up estimate by WBS item, € thousands01,0002,0003,0004,000Building: 3,0003,000BuildingEquipment: 650650EquipmentBooking: 200200BookingPeople: 120120PeopleLicence: 3030LicencePM: 5050PM

Step by step

  1. Add the estimates3,000 + 650 + 200 + 120 + 30 + 50= €4,050k
  2. Contingency for known risksheld by the project= + €150k
  3. Cost baseline4,050 + 150= €4,200k
  4. Management reserve for unknown risksheld by the sponsor= + €300k
  5. Total funding4,200 + 300= €4,500k
WBSItemEstimate (€k)
1Building3000
2Equipment650
3Booking system200
4People120
5Licence and opening30
6Project management50

How to read the result

The work fits the €4.2M approved in the business case, with €150k set aside for the risks on the register and €300k with the sponsor for the unexpected.

What it led to

The €4.2M becomes the cost baseline; contingency use is reported monthly.

Do it in a spreadsheet

Total=SUM(C2:C7)
Baseline=C8+150
Funding=C9+300
Try it yourself: If equipment quotes rose 15%, how much contingency would be left?

650 × 0.15 = €97.5k used; €150k − €97.5k = €52.5k left.

In the roles

How a Project Manager uses it

€40,000 of the €150,000 contingency is used (claim, wall change, Saturday receptionist). €110,000 remains against open risks worth about €70,000: enough, with a margin.

Questions people ask

What happens to unused contingency?

It's returned, or released as agreed with the sponsor.

Related techniques

← All techniques and tools