Risk · cheat sheet Reserve analysis Checking how much contingency and management reserve has been used, how much is left, and whether it still covers the risks that remain.
Common practice 5 steps Used by Project Manager
What it is Checking how much contingency and management reserve has been used, how much is left, and whether it covers the risks still open.
When to use it At every risk review and stage end, and whenever contingency is used.
Why it works Reserves run out quietly. Regular checks show early whether you'll need more, or can release some.
Do Contingency is for risks, not for new scope. Don't Spending contingency on new scope. Not noticing contingency running out until it's gone. Step by step Start from the reserves Contingency (known risks) and management reserve (unknown).
Record each use Which risk or change it paid for.
Compare what's left with open risks Their likely cost.
Release what's no longer needed When risks pass.
Escalate early If it looks too small.
Worked example The situation. A €150,000 contingency halfway through a project.
Used: €40,000. Open risks worth about €70,000. Remaining €110,000: enough with a margin. The result. The sponsor was confident the project wouldn't need the reserve.
Date Used for Amount Remaining Month 4 Damp repairs 20,000 130,000 Month 5 Wall change 18,000 112,000 Month 5 Extra receptionist 2,000 110,000
Filled in for: A €150,000 contingency halfway through a project.
Date Used for (risk or change) Amount Remaining Approved by
Copy this structure, or print the blank version and fill it in by hand.
How to do it with real data The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataFrom bottom-up estimate to total funding
From Day 14: What will it cost? of the Project Manager story
Each part of the work breakdown is estimated from quotes and the survey (€ thousands).
Bottom-up estimate by WBS item, € thousands 0 1,000 2,000 3,000 4,000 Building: 3,000 3,000 Building Equipment: 650 650 Equipment Booking: 200 200 Booking People: 120 120 People Licence: 30 30 Licence PM: 50 50 PM
Step by step Add the estimates 3,000 + 650 + 200 + 120 + 30 + 50 = €4,050k Contingency for known risks held by the project = + €150k Cost baseline 4,050 + 150 = €4,200k Management reserve for unknown risks held by the sponsor = + €300k Total funding 4,200 + 300 = €4,500k
WBS Item Estimate (€k) 1 Building 3000 2 Equipment 650 3 Booking system 200 4 People 120 5 Licence and opening 30 6 Project management 50
How to read the result The work fits the €4.2M approved in the business case, with €150k set aside for the risks on the register and €300k with the sponsor for the unexpected.
What it led to The €4.2M becomes the cost baseline; contingency use is reported monthly.
Do it in a spreadsheet Total =SUM(C2:C7)Baseline =C8+150Funding =C9+300
Try it yourself: If equipment quotes rose 15%, how much contingency would be left? 650 × 0.15 = €97.5k used; €150k − €97.5k = €52.5k left.
In the roles How a Project Manager uses it€40,000 of the €150,000 contingency is used (claim, wall change, Saturday receptionist). €110,000 remains against open risks worth about €70,000: enough, with a margin.
Questions people ask What happens to unused contingency? It's returned, or released as agreed with the sponsor.