Estimation · cheat sheet

Analogous estimating

Estimating from a similar past project, adjusted for the differences. Fast, but rough.

Common practice
5 steps
Used by Project Manager

What it is

Estimating a new piece of work from a similar past one, adjusted for differences. It's top-down and quick.

When to use it

Early on, when little detail is known: in the business case or the charter.

Why it works

When little is known, history is the best guide. It gives a reasonable first number for decisions like “is this worth doing?”.

Do

  • Use actuals from the past project, not its original estimate.

Don't

  • Treating a rough comparison as a commitment.
  • Comparing projects that aren't really alike.

Step by step

  1. Find a comparable past project Similar type, size and context, with known actual costs and durations.
  2. List the differences Size, location, prices, technology, team experience.
  3. Adjust Scale up or down for each difference, and adjust for price changes since then.
  4. Give a range Analogous estimates are rough; say so with a range, for example −25% to +50%.
  5. Replace it later Once the work is broken down, make a bottom-up estimate.
Also called: Top-down estimate, estimating by comparisonPrint the blank template ↗

Worked example

The situation. A council estimates a new playground.

  1. Last year's similar playground cost €180,000.
  2. The new one is 30% larger and prices rose 8%.
  3. Estimate: about €250,000, range €200,000 to €320,000.

The result. Good enough to decide to proceed and set aside funding; refined after design.

Analogous estimate worksheet Print blank
Past projectActual cost or timeDif­ferenceAdjus­tmentNew estimate

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

For the business case, Annelise (Project Manager) uses the cost of a clinic conversion in a neighbouring town, adjusted for size and today's prices, to arrive at about €4.2M.

Questions people ask

When is it unreliable?

When the past project wasn't really similar, or when nobody recorded actual costs.

Related techniques