Day 35 of 46Stage 4 · Monitoring and controllingMondayDescoping and re-baselining

The budget is cut

The council faces a funding gap. Every project must give back 5%. For the clinic, that's €210,000, with the opening date unchanged.

Stage goal: Keep the project on track and control every change.
Stakeholders
Atticus (Director of Community Health) Abigail (Finance Business Partner)
Techniques today MoSCoW Impact analysis
How the day goes
  1. 09:00News from Atticus
  2. 11:00Options workshop
  3. 15:00Board: new baseline

Situation 1 of 3

09:00 · News from Atticus
Atticus (Director of Community Health)sponsor
The council needs €210,000 back from us. The opening date can't move.

How do you approach it?

When money is cut, decide what to drop by priority and benefit, not equally. Show the effect of each option.

Situation 2 of 3

11:00 · Options workshop
Abigail (Finance Business Partner)
If the board agrees, what happens to the cost baseline?

What do you do?

Re-baseline only through an approved change, record why, and keep the history so performance stays honest.

Situation 3 of 3

15:00 · Board: new baseline
Atticus (Director of Community Health)sponsor
Does the business case still hold after the cut?

What do you check?

Big changes trigger a business case check. Record important decisions, with reasons, in a decision log.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Descoping by priority

  • When money or time is cut, drop or postpone work by priority and benefit, not equally everywhere.
  • Show the effect of each option on benefits and risk.
Concept

Re-baselining

  • Baselines change only through an approved decision. Record why and when, and keep the old version for comparison.
  • Performance is then measured against the new baseline.

Where you will meet this: Re-baselining · baseline change

Common practice

The decision log

  • A record of important decisions: what was decided, by whom, when and why.
  • It answers “why did we do that?” months later.

Where you will meet this: Decision log · decision register

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 35 complete

3 situations today.

Your responsibility todayHandling a budget cut
Technique you usedDescoping by priority, re-baselining, decision log
Key points to remember
  • When money is cut, decide what to drop by priority and benefit, not equally. Show the effect of each option.
  • Re-baseline only through an approved change, record why, and keep the history so performance stays honest.
  • Big changes trigger a business case check. Record important decisions, with reasons, in a decision log.
Techniques today MoSCoW Impact analysis