Day 45 of 46Stage 5 · ClosingMondayEarly termination

Closing a stopped project

The council stops a sister project, a mobile health van, after the funding partner withdraws. Adeline asks you to close it properly.

Stage goal: Hand over, close contracts, learn, and check the benefits.
Stakeholders
Adeline (Portfolio Manager)
How the day goes
  1. 09:00Briefing with Adeline
  2. 11:00Adeline (Portfolio Manager): what can be saved?
  3. 15:00Closing it down with Adeline (Portfolio Manager)

Situation 1 of 3

09:00 · Briefing with Adeline
Adeline (Portfolio Manager)
The van project is stopped. The team is upset; they think they failed.

How do you see it?

Stopping a project when the reason for it disappears is good governance. Explain it clearly and close it properly.
Used here Stage gate

Situation 2 of 3

11:00 · Adeline (Portfolio Manager): what can be saved?
Adeline (Portfolio Manager)
The van is half fitted out. What happens to everything already done?

What do you do?

When a project stops, save what can be reused, end contracts on their terms, and keep the knowledge.

Situation 3 of 3

15:00 · Closing it down with Adeline (Portfolio Manager)
Adeline (Portfolio Manager)
Do we still need a closure report for a project that never finished?

What do you produce?

Close stopped projects as carefully as finished ones: a closure report, formal closure, and lessons for the next.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Stopping is a decision

  • Projects should stop when their reason disappears. That's good governance, not failure.
  • Explain it clearly to the team.

Where you will meet this: Early termination · project cancellation

Common practice

Save what you can

  • Reuse equipment, designs and knowledge elsewhere, and end contracts on their terms to limit costs.
Concept

Close it properly

  • A stopped project still needs a closure report, formal closure and lessons.
  • Money, contracts and people mustn't be left in limbo.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 45 complete

3 situations today.

Your responsibility todayClosing a project early
Technique you usedEarly termination, salvage, closure report
Key points to remember
  • Stopping a project when the reason for it disappears is good governance. Explain it clearly and close it properly.
  • When a project stops, save what can be reused, end contracts on their terms, and keep the knowledge.
  • Close stopped projects as carefully as finished ones: a closure report, formal closure, and lessons for the next.