Procurement · cheat sheet

Make or buy

Deciding whether to do work in-house or buy it, by comparing whole-life cost, time, risk, skills and support.

Common practice
6 steps
Used by Project Manager

What it is

Deciding whether to do work in-house or buy it from outside, by comparing whole-life cost, time, risk, skills and support.

When to use it

In planning, for every major piece of work or product.

Why it works

The cheapest-looking option often isn't. A structured comparison avoids building what you should buy, or buying what you should keep in-house.

Do

  • Include the cost of your own people's time when you “make”.

Don't

  • Comparing only the purchase price.
  • Building because the team wants to, not because it's better.

Step by step

  1. Describe what's needed The need, not a solution.
  2. List options Make, buy, or a mix (buy and adapt).
  3. Compare whole-life cost Not just the purchase: running, maintenance, support over years.
  4. Compare time, risk and skills Can you do it? How fast? What could go wrong?
  5. Consider strategy Is it core knowledge to keep in-house?
  6. Decide and record why For later audits and lessons.
Also called: Make-or-buy analysis, build vs buyPrint the blank template ↗

Worked example

The situation. A clinic needs a booking system.

  1. Make: 9 months, two developers, maintenance for years.
  2. Buy: 3 months, licence fee, proven, supported.
  3. Decision: buy, and configure it.

The result. Live in three months; the in-house team focused on integration.

Make or buy comparison Print blank
Crite­rionMakeBuy
5-year cost€420,000€260,000
Time to go live9 months3 months
RiskHigh (new build)Low (proven)
SupportOwn teamVendor

Filled in for: A clinic needs a booking system.

Crite­rionWeightMakeBuyMix

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

Aine (IT Lead)'s team could build a booking system, but a proven product used by other clinics is cheaper over 5 years, ready sooner and supported. The council buys it.

Questions people ask

Is buying always faster?

Usually, but integration and customisation can eat the advantage.

Related techniques