Is it worth it?
Four ways to meet the need. Compare them fairly, including doing nothing, and write the case.
- 09:00Options with Aya (Project Coordinator) and Atticus (Sponsor)
- 11:00Costs and benefits with Abigail (Finance)
- 15:00First draft of the business case, with Amani (Clinical Lead)
Situation 1 of 4
09:00 · Options with Aya (Project Coordinator) and Atticus (Sponsor)What do you do?
Situation 2 of 4
11:00 · Costs and benefits with Abigail (Finance)What else belongs in the cost-benefit analysis?
Payback and sensitivity
Abigail (Finance) and Annelise (Project Manager) work out when the clinic pays back its cost, and what happens if things go worse than planned (€ thousands).
| Year | Investment | Running costs | Benefits (funding + fewer emergency visits) | Net | Cumulative |
|---|---|---|---|---|---|
| Year 0 | 4200 | 0 | 0 | -4200 | -4200 |
| Year 1 | 0 | 1900 | 2500 | 600 | -3600 |
| Year 2 | 0 | 1900 | 2500 | 600 | -3000 |
| Year 3 | 0 | 1900 | 2500 | 600 | -2400 |
| Year 4 | 0 | 1900 | 2500 | 600 | -1800 |
| Year 5 | 0 | 1900 | 2500 | 600 | -1200 |
- Net benefit a year
benefits − running costs: 2,500 − 1,900= €600k - Payback
investment ÷ net a year: 4,200 ÷ 600= 7 years - If building costs rise 20%
building €3,100k + 20% = 3,720, so the investment is 4,820; 4,820 ÷ 600= about 8 years - If benefits start 6 months late
7 + 0.5= 7.5 years - If funding falls 10%
net = 1,440 + 900 − 1,900 = 440; 4,200 ÷ 440= about 9.5 years
Try it yourself in a spreadsheet
| Net a year | =D2-C2 |
| Cumulative | =F1+E2 |
| Payback | =4200/600 |
What if running costs were €2.1M a year instead of €1.9M?
Show the answer
Net = 2,500 − 2,100 = 400; payback = 4,200 ÷ 400 = 10.5 years.
Situation 3 of 4
15:00 · First draft of the business case, with Amani (Clinical Lead)How do you write that benefit?
Situation 4 of 4
11:00 · Costs and benefits with Abigail (Finance)How do you compare money that arrives in different years?
Net present value and discounted payback
The same clinic, with each year's net benefit converted to today's money at the council's discount rate of 3.5%, over 15 years (€ thousands).
| Year | Net cash flow | Discount factor | Today's value | Cumulative today's value |
|---|---|---|---|---|
| Year 0 | -4200 | 1 | -4200 | -4200 |
| Year 1 | 600 | 0.966 | 580 | -3620 |
| Year 2 | 600 | 0.934 | 560 | -3060 |
| Year 3 | 600 | 0.902 | 541 | -2519 |
| Year 4 | 600 | 0.871 | 523 | -1996 |
| Year 5 | 600 | 0.842 | 505 | -1491 |
| Year 6 | 600 | 0.814 | 488 | -1003 |
| Year 7 | 600 | 0.786 | 472 | -531 |
| Year 8 | 600 | 0.759 | 456 | -76 |
| Year 9 | 600 | 0.734 | 440 | 365 |
| Year 10 | 600 | 0.709 | 425 | 790 |
| Year 11 | 600 | 0.685 | 411 | 1201 |
| Year 12 | 600 | 0.662 | 397 | 1598 |
| Year 13 | 600 | 0.639 | 384 | 1982 |
| Year 14 | 600 | 0.618 | 371 | 2352 |
| Year 15 | 600 | 0.597 | 358 | 2710 |
- Discount factor
1 ÷ (1 + 0.035)^year; year 10: 1 ÷ 1.035^10= 0.709 - Today's value
net cash flow × discount factor; year 10: 600 × 0.709= €425k - Net present value
sum of today's values, years 0 to 15= about €2,710k - Discounted payback
the cumulative value turns positive during year 9= about 8.2 years (simple payback: 7) - Internal rate of return
the rate where the net present value is zero= about 11.5%
Try it yourself in a spreadsheet
| Discount factor | =1/(1+3.5%)^A2 (A2 = the year number) |
| Net present value | =NPV(3.5%,B3:B17)+B2 |
| Internal rate of return | =IRR(B2:B17) |
What is the NPV if the council used a discount rate of 6%?
Show the answer
=NPV(6%,B3:B17)+B2: about €1,627k. Still positive, so the clinic still creates value.
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Options analysis
- Compare several realistic ways to meet the need, including doing nothing, on the same criteria.
- The recommended option is stronger when the alternatives were treated fairly.
Where you will meet this: Options appraisal · alternatives analysis
Cost-benefit analysis
- Look at one-off costs, running costs and benefits over several years.
- Show how sensitive the result is to cost rises or late benefits; ranges are more honest than one exact number.
Measurable benefits
- A benefit needs a baseline (today), a target and a date, so it can be checked after the project.
- Benefits you can't price are still described, because they matter to the decision.
Where you will meet this: Benefits management · benefits realisation
Money later is worth less
- A euro received in ten years is worth less than a euro today: it could have been used or invested in the meantime. Discounting converts future amounts into today's value.
- Net present value (NPV) adds up every year's discounted costs and benefits. Above zero, the project creates value at that discount rate. The internal rate of return (IRR) is the rate at which the NPV is exactly zero.
- Discounted payback is when the discounted benefits have repaid the investment. It is always later than simple payback.
Where you will meet this: Net present value · internal rate of return · discounted payback
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 3 complete
4 situations today.
- An options analysis compares real alternatives, including doing nothing, on the same criteria. It makes the recommendation defensible.
- Compare costs and benefits over several years, including running costs, and show what happens if assumptions change.
- Benefits need a baseline, a target and a date, so they can be checked after the project has finished.
- Money later is worth less than money now: discount future amounts to compare options fairly, and look beyond payback.