Work authorisation
Formally handing a piece of work to a team or supplier, with what to deliver, how it's accepted, dates, limits and reporting, so it starts at the right time with clear ownership.
What it is
Formally handing a piece of work to a team or supplier with what to deliver, acceptance criteria, dates, limits and reporting.
When to use it
Each time a piece of work starts during executing.
Why it works
It makes ownership clear and gives everyone the same picture of “done”, which prevents disputes later.
Do
- Verbal go-aheads are easily forgotten; write it down, even briefly.
Don't
- Starting work with a verbal “go ahead”.
- No acceptance criteria, so “done” is argued about later.
Step by step
- Take the work package From the WBS and schedule.
- Write what and how accepted Deliverables and criteria.
- Add dates, effort and tolerances How far time and cost may move.
- Agree reporting How and how often.
- Both sides confirm Then work starts.
- Close it on acceptance And record actual effort.