Governance and roles · cheat sheet

Work authorisation

Formally handing a piece of work to a team or supplier, with what to deliver, how it's accepted, dates, limits and reporting, so it starts at the right time with clear ownership.

Common practice
6 steps
Used by Project Manager

What it is

Formally handing a piece of work to a team or supplier with what to deliver, acceptance criteria, dates, limits and reporting.

When to use it

Each time a piece of work starts during executing.

Why it works

It makes ownership clear and gives everyone the same picture of “done”, which prevents disputes later.

Do

  • Verbal go-aheads are easily forgotten; write it down, even briefly.

Don't

  • Starting work with a verbal “go ahead”.
  • No acceptance criteria, so “done” is argued about later.

Step by step

  1. Take the work package From the WBS and schedule.
  2. Write what and how accepted Deliverables and criteria.
  3. Add dates, effort and tolerances How far time and cost may move.
  4. Agree reporting How and how often.
  5. Both sides confirm Then work starts.
  6. Close it on acceptance And record actual effort.
Also called: Work packages, work ordersPrint the blank template ↗

Worked example

The situation. Handing hiring to the HR lead.

  1. 12 roles by week 22; offers within 48 hours; weekly update; escalate if two weeks behind.

The result. Progress reports came every Monday without chasing.

Work package Print blank
Code and nameOwnerDeliverab­lesAccepted whenDatesToleran­cesRepor­ting

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

Adaugo (HR and Training Lead) receives work package 4.1 Hiring: 12 clinical roles by week 22, offers within 48 hours, weekly updates, escalate if two weeks behind.

Questions people ask

Is this bureaucracy?

For small work, a short email with the same points is enough.