Day 43 of 46Stage 5 · ClosingWednesdayProcurement closure

Closing the contracts

Suppliers want their final payments. Check what was agreed, settle what's fair, and close every contract properly.

Stage goal: Hand over, close contracts, learn, and check the benefits.
Stakeholders
Arash (Contractor Project Manager) Alfonso (Software Vendor Project Manager) Alder (Procurement Officer)
How the day goes
  1. 09:00Retention request from Arash (Contractor)
  2. 11:00Final invoice from Alfonso (Software Vendor)
  3. 14:00Contract closure with Alder (Procurement)
  4. 16:00Final supplier reviews

Situation 1 of 3

09:00 · Retention request from Arash (Contractor)
Arash (Contractor Project Manager)
All the defects are fixed. Can you release our 10% retention now?

What do you do?

Close contracts on the terms that were agreed: check the conditions, pay what's due when it's due, and record it.

Situation 2 of 3

11:00 · Final invoice from Alfonso (Software Vendor)
Alfonso (Software Vendor Project Manager)
Our final invoice includes €15,000 for the extra integration effort after the security upgrade.

How do you respond?

Settle final claims with the records: the contract, the change log and the evidence. Pay undisputed amounts on time.

Situation 3 of 3

14:00 · Contract closure with Alder (Procurement)
Alder (Procurement Officer)
How do we formally close the contracts?

What does closure include?

Close each contract formally: acceptance, final payment, documents, a final review and a closure letter.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Closing procurements

  • Each contract is closed formally: deliverables accepted, claims settled, final payments made, documents and warranties received.
  • A closure letter confirms it in writing.

Where you will meet this: Close procurements · contract closure

Common practice

Final claims

  • Settle final claims with the records: the contract, approved changes and evidence.
  • Pay undisputed amounts on time; discuss the rest.

Where you will meet this: Claims administration · final account

Common practice

Learning from buying

  • A short review of how the buying went (what worked, what to change) helps the next project's contracts.
  • Archive the contract records for audits and warranties.

Where you will meet this: Procurement audit · supplier evaluation

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 43 complete

3 situations today.

Your responsibility todayClosing contracts
Technique you usedContract closure, final accounts, procurement review
Key points to remember
  • Close contracts on the terms that were agreed: check the conditions, pay what's due when it's due, and record it.
  • Settle final claims with the records: the contract, the change log and the evidence. Pay undisputed amounts on time.
  • Close each contract formally: acceptance, final payment, documents, a final review and a closure letter.