Governance and roles · cheat sheet

Tailoring the approach

Adapting how a project is run (life cycle, documents, controls, meetings) to its size, risk and type of work, and choosing predictive, agile or hybrid for each part.

Common practice
6 steps
Used by Project Manager

What it is

Adapting how a project is run (its life cycle, documents, controls and meetings) to its size, risk and kind of work. It includes choosing predictive, agile or hybrid delivery for each part.

When to use it

At the start of a project, and at stage ends if the situation changes.

Why it works

No method fits every project as written. Too much process wastes time; too little loses control. Tailoring keeps what's useful and explains what's left out.

Do

  • Write down what you dropped and why; auditors and sponsors will ask.

Don't

  • One approach forced on everything.
  • Dropping controls without saying why.

Step by step

  1. Look at each part of the work How clear are requirements? How costly is change? How much do users need to try things?
  2. Choose the approach per part Predictive for clear, costly-to-change work; agile where learning from users matters; hybrid to combine them.
  3. Choose the controls Which documents, reviews and meetings does this project actually need?
  4. Agree with the standards owner The portfolio office or PMO.
  5. Record the decisions and why In the plan.
  6. Review at stage ends Adjust if the situation changes.
Also called: Choosing the delivery approach, predictive vs agile vs hybridPrint the blank template ↗

Worked example

The situation. A retailer opens a new store with a new loyalty app.

  1. Store fit-out: predictive, fixed design and contractor plan.
  2. Loyalty app: agile, two-week cycles with customer testing.
  3. Shared milestones: store opening, app launch the same week.
  4. Documents: 14 of the company's 20 standard ones kept.

The result. Both parts launched together, each run in the way that suited it.

Tailoring decisions Print blank
PartApproachWhy
Store fit-outPredictiveClear design, costly to change
Loyalty appAgileNeeds customer feedback
GovernanceOne board, shared milestonesOne project, one view

Filled in for: A retailer opens a new store with a new loyalty app.

Part or areaApproach or controlKept, combined or droppedWhyAgreed by

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

Riverside runs the building predictively and the booking system in agile Sprints, joined by shared milestones and one board. 17 of the council's 24 standard documents are kept; the rest are combined or dropped, with the portfolio office's agreement.

Questions people ask

Is hybrid just a compromise?

No. It uses each approach where it fits best, joined by shared milestones and governance.