Strategy and planning · cheat sheet

Benefits tracking

Measuring each expected benefit against its baseline and target after the project, with an owner who acts when it lags.

Common practice
6 steps
Used by Project Manager

What it is

Measuring each expected benefit after a project against its baseline and target, at agreed points, with an owner in the organisation who acts if it lags.

When to use it

Planned in the business case, handed over at closure, reviewed at set points after go-live.

Why it works

Projects are funded for their benefits, which usually arrive after the project ends. Without tracking, nobody knows if the money achieved anything.

Do

  • Don't change targets to match results; explain the gap instead.

Don't

  • Owners who leave with the project.
  • Only one measurement, too early to show anything.

Step by step

  1. Define each benefit What improves, the measure, the baseline today, the target and the date.
  2. Name an owner who stays Someone in the organisation, not in the project team.
  3. Agree review points For example 6 and 12 months after go-live.
  4. Measure and compare Actual vs baseline and target; look at the trend.
  5. Find causes and act For benefits that lag, agree actions.
  6. Report honestly Separate project success from benefit success.
Also called: Benefits realisation, benefits reviewPrint the blank template ↗

Worked example

The situation. A new online booking system for a dentist chain.

  1. Benefit: phone calls for bookings from 400 to 150 a day within 6 months.
  2. Month 6: 220 a day. Cause: older patients don't know about online booking.
  3. Action: reception staff show patients how to book.

The result. At month 12, calls were down to 160 per day.

Benefits tracker Print blank
BenefitBaselineTargetActualStatus
Booking calls per day400150220On the way
No-shows12%6%7%On the way

Filled in for: A new online booking system for a dentist chain.

BenefitMeasureBaselineTarget and dateActualOwnerAction

Copy this structure, or print the blank version and fill it in by hand.

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

How far towards each benefit?

From Day 46: Was it worth it? of the Project Manager story

Six months after opening, each benefit against its baseline and target.

Progress towards each target, %0255075100125GP / wait: 7575GPwaitTravel / time: 112112TraveltimeEmergency / visits: 6060Emergencyvisits

Step by step

  1. Formula(baseline − now) ÷ (baseline − target) × 100
  2. GP wait(3 − 1.5) ÷ (3 − 1)= 75%
  3. Travel(40 − 12) ÷ (40 − 15)= 112%: target beaten
  4. Emergency visits(0 − (−12)) ÷ (0 − (−20))= 60%
BenefitBaselineTargetNowProgress (%)
GP waiting time (weeks)311.575
Travel time to care (minutes)401512112
Minor emergency visits (% change)0-20-1260

How to read the result

One benefit is achieved and two are on the way. Separating project success from benefit success keeps the review honest.

What it led to

Actions for the two lagging benefits (reminders, awareness campaign) and a review at month 12.

Do it in a spreadsheet

Progress=(B2-D2)/(B2-C2)*100
Try it yourself: What GP wait would show 100%?

1 week, the target.

In the roles

How a Project Manager uses it

Six months after opening, GP waiting time is 1.5 weeks (from 3, target under 1). Amani (Clinical Lead) finds 15% no-shows and starts text reminders; the next review is at month 12.

Questions people ask

Who owns benefits?

The business, through a named owner, usually confirmed in the business case and the handover.