Measuring each expected benefit against its baseline and target after the project, with an owner who acts when it lags.
Common practice 6 steps Used by Project Manager
What it is
Measuring each expected benefit after a project against its baseline and target, at agreed points, with an owner in the organisation who acts if it lags.
When to use it
Planned in the business case, handed over at closure, reviewed at set points after go-live.
Why it works
Projects are funded for their benefits, which usually arrive after the project ends. Without tracking, nobody knows if the money achieved anything.
Do
Don't change targets to match results; explain the gap instead.
Don't
Owners who leave with the project.
Only one measurement, too early to show anything.
Step by step
Define each benefitWhat improves, the measure, the baseline today, the target and the date.
Name an owner who staysSomeone in the organisation, not in the project team.
Agree review pointsFor example 6 and 12 months after go-live.
Measure and compareActual vs baseline and target; look at the trend.
Find causes and actFor benefits that lag, agree actions.
Report honestlySeparate project success from benefit success.
One benefit is achieved and two are on the way. Separating project success from benefit success keeps the review honest.
What it led to
Actions for the two lagging benefits (reminders, awareness campaign) and a review at month 12.
Do it in a spreadsheet
Progress
=(B2-D2)/(B2-C2)*100
Try it yourself: What GP wait would show 100%?
1 week, the target.
In the roles
How a Project Manager uses it
Six months after opening, GP waiting time is 1.5 weeks (from 3, target under 1). Amani (Clinical Lead) finds 15% no-shows and starts text reminders; the next review is at month 12.