Day 36 of 46Stage 4 · Monitoring and controllingFridayAccepting deliverables and stopping scope creep

Is it done?

The building is nearly finished. The contractor is adding extras nobody asked for, Amani (Clinical Lead) is asked to sign it off, and residents want longer opening hours.

Stage goal: Keep the project on track and control every change.
Stakeholders
Arash (Contractor Project Manager) Amani (Clinical Lead) Azadeh (Community Council Representative)
How the day goes
  1. 09:00Site walk with Arash (Contractor)
  2. 11:00Building acceptance with Amani (Clinical Lead) and Antonia (Compliance Lead)
  3. 14:00Residents' requests with Azadeh (Community Council)
  4. 16:00Update the change log

Situation 1 of 3

09:00 · Site walk with Arash (Contractor)
Arash (Contractor Project Manager)
Good news: we upgraded the reception to oak panelling. No extra charge, it's our gift.

How do you respond?

Adding unrequested extras (gold-plating) is a change too. Check it against the requirements and record it.

Situation 2 of 3

11:00 · Building acceptance with Amani (Clinical Lead) and Antonia (Compliance Lead)
Amani (Clinical Lead)senior user
The building looks finished. Shall I just sign the acceptance?

How should acceptance work?

Deliverables are accepted against the agreed criteria by the people who'll use them, with any remaining defects listed and dated.

Situation 3 of 3

14:00 · Residents' requests with Azadeh (Community Council)
Azadeh (Community Council Representative)
Residents are asking: can the clinic open until 9 pm and on Saturdays?

Is this a project change?

Not every request belongs to the project. Send operational decisions to the business owner, and only bring the parts that affect project scope through change control.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Accepting deliverables

  • Deliverables are accepted by the people who'll use them, against the agreed acceptance criteria.
  • Minor remaining defects are listed with dates; a failed criterion means not accepted yet.

Where you will meet this: Validate scope (PMI) · acceptance

Concept

Scope creep and gold-plating

  • Scope creep is change that slips in without control. Gold-plating is adding extras nobody asked for, often with good intentions.
  • Both are changes and go through change control.
Common practice

Project or operations?

  • Some requests are about how the result will be run after the project, not about the project itself.
  • Pass them to the business owner; only the parts that change project scope come through change control.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 36 complete

3 situations today.

Your responsibility todayAccepting deliverables and protecting scope
Technique you usedAcceptance criteria, gold-plating, change control
Key points to remember
  • Adding unrequested extras (gold-plating) is a change too. Check it against the requirements and record it.
  • Deliverables are accepted against the agreed criteria by the people who'll use them, with any remaining defects listed and dated.
  • Not every request belongs to the project. Send operational decisions to the business owner, and only bring the parts that affect project scope through change control.