What will it cost?
The survey is back. Turn estimates into a budget that still has room for the risks you already know about.
- 09:00Cost estimates per WBS item
- 11:00Budget session with Abigail (Finance)
- 14:00Spending profile by month with Abigail (Finance)
- 16:00Agree the reserves with Atticus (Sponsor) and Abigail (Finance)
Situation 1 of 4
11:00 · Budget session with Abigail (Finance)How do you build the real budget?
Situation 2 of 4
16:00 · Agree the reserves with Atticus (Sponsor) and Abigail (Finance)What is the €150,000 for?
From bottom-up estimate to total funding
Each part of the work breakdown is estimated from quotes and the survey (€ thousands).
| WBS | Item | Estimate (€k) |
|---|---|---|
| 1 | Building | 3000 |
| 2 | Equipment | 650 |
| 3 | Booking system | 200 |
| 4 | People | 120 |
| 5 | Licence and opening | 30 |
| 6 | Project management | 50 |
- Add the estimates
3,000 + 650 + 200 + 120 + 30 + 50= €4,050k - Contingency for known risks
held by the project= + €150k - Cost baseline
4,050 + 150= €4,200k - Management reserve for unknown risks
held by the sponsor= + €300k - Total funding
4,200 + 300= €4,500k
Try it yourself in a spreadsheet
| Total | =SUM(C2:C7) |
| Baseline | =C8+150 |
| Funding | =C9+300 |
If equipment quotes rose 15%, how much contingency would be left?
Show the answer
650 × 0.15 = €97.5k used; €150k − €97.5k = €52.5k left.
Situation 3 of 4
14:00 · Spending profile by month with Abigail (Finance)What do you give finance?
The spending profile and S-curve
The baseline spread month by month from the schedule (€ thousands).
| Month | Spend | Cumulative |
|---|---|---|
| M1 | 150 | 150 |
| M2 | 350 | 500 |
| M3 | 900 | 1400 |
| M4 | 1000 | 2400 |
| M5 | 900 | 3300 |
| M6 | 600 | 3900 |
| M7 | 300 | 4200 |
- Monthly spend
from the schedule: when each item's work happens - Cumulative
add each month to the total so far= S-shaped - Peak
months 3 to 5, during building works= €2.8M in three months - Planned value later
cumulative at month 4= €2,400k
Try it yourself in a spreadsheet
| Cumulative | =C1+B2 |
| Chart | line or column chart of column C |
What is the planned value at the end of month 5?
Show the answer
€3,300k.
Situation 4 of 4
11:00 · Budget session with Abigail (Finance)What does that tell you?
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Top-down and bottom-up estimates
- Early on, estimate from similar past projects (top-down). It's fast but rough.
- Once the work is broken down, estimate each piece and add them up (bottom-up). It's slower but more accurate.
Where you will meet this: Analogous estimating · bottom-up estimating
Cost baseline and reserves
- Contingency covers risks you've identified and is part of the cost baseline.
- Management reserve covers the unknown; it sits outside the baseline and needs the sponsor's approval to use.
Where you will meet this: Cost baseline · contingency reserve · management reserve
Spending over time
- Spread the budget across months using the schedule. The cumulative line usually forms an S-curve.
- Finance uses it to arrange funding; you use it to track progress.
Where you will meet this: S-curve · funding requirements
Three ways to estimate
- Analogous: from a similar past project as a whole, adjusted for size and prices. Fast and rough; used early.
- Parametric: a rate from past data multiplied by a quantity, such as cost per square metre or hours per test. As good as the data behind the rate.
- Bottom-up: estimate each piece of the work breakdown and add them up. Slowest and most accurate. Comparing two methods catches mistakes.
Where you will meet this: Analogous, parametric and bottom-up estimating
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 14 complete
4 situations today.
- Early estimates come from similar past projects. Once the work is broken down, estimate each piece and add them up for a more accurate budget.
- The cost baseline includes contingency for known risks. A separate management reserve, held by the sponsor, covers the unknown.
- Spread the budget over time using the schedule. The cumulative spending curve (S-curve) is both a funding plan and a tracking tool.
- Check an estimate with a second method: a rate from similar projects (parametric) catches big errors in a bottom-up estimate.