Day 14 of 46Stage 2 · PlanningWednesdayCost baseline and reserves

What will it cost?

The survey is back. Turn estimates into a budget that still has room for the risks you already know about.

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Stakeholders
Abigail (Finance Business Partner)
Documents today Cost baseline
How the day goes
  1. 09:00Cost estimates per WBS item
  2. 11:00Budget session with Abigail (Finance)
  3. 14:00Spending profile by month with Abigail (Finance)
  4. 16:00Agree the reserves with Atticus (Sponsor) and Abigail (Finance)

Situation 1 of 4

11:00 · Budget session with Abigail (Finance)
Abigail (Finance Business Partner)
The business case said €4.2M. Can't we just use that number?

How do you build the real budget?

Early estimates come from similar past projects. Once the work is broken down, estimate each piece and add them up for a more accurate budget.

Situation 2 of 4

16:00 · Agree the reserves with Atticus (Sponsor) and Abigail (Finance)
Abigail (Finance Business Partner)
€4.05M! So we have €150,000 spare. Can I return it to the council?

What is the €150,000 for?

The cost baseline includes contingency for known risks. A separate management reserve, held by the sponsor, covers the unknown.
Worked example 1

From bottom-up estimate to total funding

Each part of the work breakdown is estimated from quotes and the survey (€ thousands).

Bottom-up estimate by WBS item, € thousands01,0002,0003,0004,000Building: 3,0003,000BuildingEquipment: 650650EquipmentBooking: 200200BookingPeople: 120120PeopleLicence: 3030LicencePM: 5050PM
WBSItemEstimate (€k)
1Building3000
2Equipment650
3Booking system200
4People120
5Licence and opening30
6Project management50
Download the data (spreadsheet file)
  1. Add the estimates3,000 + 650 + 200 + 120 + 30 + 50= €4,050k
  2. Contingency for known risksheld by the project= + €150k
  3. Cost baseline4,050 + 150= €4,200k
  4. Management reserve for unknown risksheld by the sponsor= + €300k
  5. Total funding4,200 + 300= €4,500k
What it meansThe work fits the €4.2M approved in the business case, with €150k set aside for the risks on the register and €300k with the sponsor for the unexpected.
What Annelise decidesThe €4.2M becomes the cost baseline; contingency use is reported monthly.
Try it yourself in a spreadsheet
Total=SUM(C2:C7)
Baseline=C8+150
Funding=C9+300

If equipment quotes rose 15%, how much contingency would be left?

Show the answer

650 × 0.15 = €97.5k used; €150k − €97.5k = €52.5k left.

Situation 3 of 4

14:00 · Spending profile by month with Abigail (Finance)
Abigail (Finance Business Partner)
Finance also needs to know when the money is spent. The council pays in quarterly instalments.

What do you give finance?

Spread the budget over time using the schedule. The cumulative spending curve (S-curve) is both a funding plan and a tracking tool.
Worked example 2

The spending profile and S-curve

The baseline spread month by month from the schedule (€ thousands).

Cumulative planned spend: the S-curve, € thousands01,2502,5003,7505,000M1: 150150M1M2: 500500M2M3: 1,4001,400M3M4: 2,4002,400M4M5: 3,3003,300M5M6: 3,9003,900M6M7: 4,2004,200M7
MonthSpendCumulative
M1150150
M2350500
M39001400
M410002400
M59003300
M66003900
M73004200
Download the data (spreadsheet file)
  1. Monthly spendfrom the schedule: when each item's work happens
  2. Cumulativeadd each month to the total so far= S-shaped
  3. Peakmonths 3 to 5, during building works= €2.8M in three months
  4. Planned value latercumulative at month 4= €2,400k
What it meansSpending is slow at first, steep in months 3 to 5, then flat. The cumulative figure is the planned value used later for earned value.
What Annelise decidesAbigail (Finance) times the council's quarterly payments to the peak.
Try it yourself in a spreadsheet
Cumulative=C1+B2
Chartline or column chart of column C

What is the planned value at the end of month 5?

Show the answer

€3,300k.

Situation 4 of 4

11:00 · Budget session with Abigail (Finance)
Abigail (Finance Business Partner)
A quick sanity check: the region's recent clinic conversions cost about €2,000 per square metre. Our warehouse is 1,500 square metres.

What does that tell you?

Check an estimate with a second method: a rate from similar projects (parametric) catches big errors in a bottom-up estimate.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Top-down and bottom-up estimates

  • Early on, estimate from similar past projects (top-down). It's fast but rough.
  • Once the work is broken down, estimate each piece and add them up (bottom-up). It's slower but more accurate.

Where you will meet this: Analogous estimating · bottom-up estimating

Concept

Cost baseline and reserves

  • Contingency covers risks you've identified and is part of the cost baseline.
  • Management reserve covers the unknown; it sits outside the baseline and needs the sponsor's approval to use.

Where you will meet this: Cost baseline · contingency reserve · management reserve

Common practice

Spending over time

  • Spread the budget across months using the schedule. The cumulative line usually forms an S-curve.
  • Finance uses it to arrange funding; you use it to track progress.

Where you will meet this: S-curve · funding requirements

Concept

Three ways to estimate

  • Analogous: from a similar past project as a whole, adjusted for size and prices. Fast and rough; used early.
  • Parametric: a rate from past data multiplied by a quantity, such as cost per square metre or hours per test. As good as the data behind the rate.
  • Bottom-up: estimate each piece of the work breakdown and add them up. Slowest and most accurate. Comparing two methods catches mistakes.

Where you will meet this: Analogous, parametric and bottom-up estimating

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 14 complete

4 situations today.

Your responsibility todaySetting the budget
Technique you usedBottom-up estimating, contingency and management reserve, S-curve
Key points to remember
  • Early estimates come from similar past projects. Once the work is broken down, estimate each piece and add them up for a more accurate budget.
  • The cost baseline includes contingency for known risks. A separate management reserve, held by the sponsor, covers the unknown.
  • Spread the budget over time using the schedule. The cumulative spending curve (S-curve) is both a funding plan and a tracking tool.
  • Check an estimate with a second method: a rate from similar projects (parametric) catches big errors in a bottom-up estimate.
Documents today Cost baseline