Day 46 of 46Stage 5 · ClosingTuesdayBenefits review, six months later

Was it worth it?

Six months after opening. The project is closed, but the question it was started for remains: are residents better off?

Stage goal: Hand over, close contracts, learn, and check the benefits.
Stakeholders
Amani (Clinical Lead) Abigail (Finance Business Partner) Azadeh (Community Council Representative)
Techniques today Benefits tracking
How the day goes
  1. 09:00Waiting-time figures with Amani (Clinical Lead)
  2. 11:00Emergency visit data with Abigail (Finance)
  3. 14:00Benefits review meeting
  4. 16:00Coffee with Azadeh (Community Council)

Situation 1 of 3

09:00 · Waiting-time figures with Amani (Clinical Lead)
Amani (Clinical Lead)senior user
GP waiting time is down from 3 weeks to 1.5. The target is under 1 week by month 12.

How do you read this?

Measure benefits against the baseline and the target, look at the trend, and act on what's holding them back.
Worked example 1

How far towards each benefit?

Six months after opening, each benefit against its baseline and target.

Progress towards each target, %0255075100125GP / wait: 7575GPwaitTravel / time: 112112TraveltimeEmergency / visits: 6060Emergencyvisits
BenefitBaselineTargetNowProgress (%)
GP waiting time (weeks)311.575
Travel time to care (minutes)401512112
Minor emergency visits (% change)0-20-1260
Download the data (spreadsheet file)
  1. Formula(baseline − now) ÷ (baseline − target) × 100
  2. GP wait(3 − 1.5) ÷ (3 − 1)= 75%
  3. Travel(40 − 12) ÷ (40 − 15)= 112%: target beaten
  4. Emergency visits(0 − (−12)) ÷ (0 − (−20))= 60%
What it meansOne benefit is achieved and two are on the way. Separating project success from benefit success keeps the review honest.
What Annelise decidesActions for the two lagging benefits (reminders, awareness campaign) and a review at month 12.
Try it yourself in a spreadsheet
Progress=(B2-D2)/(B2-C2)*100

What GP wait would show 100%?

Show the answer

1 week, the target.

Situation 2 of 3

11:00 · Emergency visit data with Abigail (Finance)
Abigail (Finance Business Partner)
Minor emergency visits are down 12%, not 20%. Some councillors are asking whether the project failed.

How do you answer?

Separate project success (delivered as agreed) from benefit success (outcomes achieved). Report both honestly.

Situation 3 of 3

16:00 · Coffee with Azadeh (Community Council)
Azadeh (Community Council Representative)
Residents love the clinic. Now they're asking again about a pharmacy inside it.

What happens with the idea?

Projects end, but needs keep coming. A new idea starts the cycle again with a request and a business case.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Concept

Benefits reviews

  • At agreed points after the project, measure each benefit against its baseline and target.
  • Look at the trend and the causes, and agree actions with the benefit owner.

Where you will meet this: Benefits review · post-project review

Concept

Two kinds of success

  • Project success: delivered what was agreed, within its limits.
  • Benefit success: the outcomes the money was approved for actually happen. A project can succeed while benefits lag, and the other way round.

Where you will meet this: Project success vs product or benefit success

Concept

The cycle starts again

  • New needs appear once the result is in use.
  • Each one starts properly, with a request and a business case, and the lessons from this project help it.

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 46 complete

3 situations today.

Your responsibility todayChecking the benefits
Technique you usedBenefits review, project vs benefit success, the next mandate
Key points to remember
  • Measure benefits against the baseline and the target, look at the trend, and act on what's holding them back.
  • Separate project success (delivered as agreed) from benefit success (outcomes achieved). Report both honestly.
  • Projects end, but needs keep coming. A new idea starts the cycle again with a request and a business case.
Techniques today Benefits tracking