Day 10 of 46Stage 2 · PlanningMondayScope statement and WBS

What exactly are we building?

“A clinic” means something different to everyone. Pin down the scope, then break it into pieces small enough to plan.

Stage goal: A realistic plan for scope, time, cost, risk, quality and buying.
Team
Aya (Project Coordinator)
Stakeholders
Amani (Clinical Lead) Atticus (Director of Community Health)
How the day goes
  1. 09:00Requirements workshop with Amani (Clinical Lead) and the clinical team
  2. 11:30Draft the scope statement
  3. 14:00Work breakdown with the leads
  4. 16:30Scope review with Atticus (Sponsor)

Situation 1 of 3

09:00 · Requirements workshop with Amani (Clinical Lead) and the clinical team
Amani (Clinical Lead)senior user
The doctors want 40 things in the clinic. Minor surgery, a physio gym, a café, a dental chair… Can we have them all?

How do you handle the list?

Collect requirements, then test each one against the objective. Prioritise openly and record what is out of scope and why.
Used here MoSCoW

Situation 2 of 3

16:30 · Scope review with Atticus (Sponsor)
Atticus (Director of Community Health)sponsor
The scope is obvious, isn't it? A clinic. Why write a document about it?

Why does the scope statement matter?

A scope statement describes the deliverables, how they'll be accepted, and what is excluded. Exclusions prevent as many arguments as inclusions.

Situation 3 of 3

14:00 · Work breakdown with the leads
Aya (Project Coordinator)
How do we get from “clinic” to things people can actually plan and do?

How do you break the work down?

A work breakdown structure splits the whole scope into deliverables and smaller pieces. If it's not in the WBS, it's not in the project.

Key concepts

The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.

Common practice

Collecting and prioritising requirements

  • Gather what users and stakeholders need, then test each request against the objective.
  • Sort openly into must, should, could and won't (this time), and record why.

Where you will meet this: Requirements management · MoSCoW

Concept

The scope statement

  • Describes each deliverable, how it will be accepted, and what is explicitly excluded.
  • It is the reference point for every later change request.

Where you will meet this: Project scope statement · product description

Concept

Work breakdown structure

  • A tree that splits the whole scope into deliverables, then into smaller pieces that can be estimated, scheduled and owned.
  • Everything in scope appears once; anything not in it is not in the project.

Where you will meet this: WBS · WBS dictionary · product breakdown structure (PRINCE2)

Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources

Day 10 complete

3 situations today.

Your responsibility todayDefining what the project will deliver
Technique you usedRequirements prioritisation, scope statement, work breakdown structure
Key points to remember
  • Collect requirements, then test each one against the objective. Prioritise openly and record what is out of scope and why.
  • A scope statement describes the deliverables, how they'll be accepted, and what is excluded. Exclusions prevent as many arguments as inclusions.
  • A work breakdown structure splits the whole scope into deliverables and smaller pieces. If it's not in the WBS, it's not in the project.