Supermarket opening52 questions5 phases

Freshmart: a Project Manager case study

A regional supermarket chain is converting an old cinema into its 30th store. Opening day is booked, a local celebrity will cut the ribbon, and 80 new staff need hiring and training. The building is listed, so the front can't change. You run the project.

What this case study tests
Heritage constraintsLong lead timesHiring as a riskBenefits after opening

You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Stakeholders
Anya (Project Manager)You
Alonso (Expansion Director)Sponsor
Agneta (Store Manager)Senior user: will run the store
Abram (Building Contractor Manager)Converts the cinema
Amalia (Heritage Officer)Protects the listed building
Asif (Refrigeration Supplier Manager)Fridges and freezers
Avery (Regional HR Manager)Hiring and training 80 people
Aster (Neighbourhood Association)Residents near the store
Freshmart

Starting up

A cinema becomes a supermarket

Question 1 of 52

Choose 1
Alonso (Expansion Director)
We've done 29 stores. Just copy the standard plan.

What do you check first?

Learn it on Day 1: A request lands on your desk

Question 2 of 52

True or false
Alonso (Expansion Director)
Options: convert the cinema, build on the car park, or open a smaller store elsewhere.

True or false: the analysis should include doing nothing.

Learn it on Day 3: Is it worth it?

Question 3 of 52

Choose 1
Alonso (Expansion Director)
The benefit: weekly sales of €250,000.

What makes it a good benefit statement?

Learn it on Day 3: Is it worth it?

Question 4 of 52

Choose 1
Alonso (Expansion Director)
Budget €4M. I hold €300,000 back.

Who can use the €300,000?

Learn it on Day 4: The decision

Question 5 of 52

Choose 1
Amalia (Heritage Officer)
The cinema's façade and foyer ceiling are protected. Any change needs my approval.

What is this?

Learn it on Day 5: Who's in charge here?

Question 6 of 52

Choose 1
Aster (Neighbourhood Association)
Residents worry about delivery lorries at night.

How do you engage them?

Learn it on Day 6: Everyone who matters

Technique: Stakeholder engagement assessment

Question 7 of 52

Choose 1
Agneta (Store Manager)
The fridge supplier and the builder both think they decide where the cold room goes.

What settles it?

Learn it on Day 7: Who does what

Technique: RACI

Question 8 of 52

Choose 1
Abram (Building Contractor Manager)
At the kick-off we heard the cinema has no loading bay. Everyone assumed it did.

What happens?

Learn it on Day 9: The kick-off

Technique: Risk identification

Question 9 of 52

Choose 1
Alonso (Expansion Director)
Converting the cinema costs more than building a new store elsewhere, but opens six months sooner.

How do you compare the options?

Learn it on Day 3: Is it worth it?

Question 10 of 52

Choose 1
Alonso (Expansion Director)
We're opening three stores this year, all under the expansion programme. Who decides things for this one?

What governance fits?

Learn it on Day 7: Who does what

Question 11 of 52

Choose 1
Alonso (Expansion Director)
The lease is signed. Can the contractor start tomorrow?

What do you need first?

Learn it on Day 5: Who's in charge here?
Freshmart

Planning

Fridges, staff and a ribbon

Question 12 of 52

Choose 1
Agneta (Store Manager)
We want a bakery, a café, a pharmacy and a flower shop inside.

How do you decide?

Learn it on Day 10: What exactly are we building?

Technique: MoSCoW

Question 13 of 52

Choose 1
Asif (Refrigeration Supplier Manager)
Fridges take 16 weeks to deliver.

Where does this sit in the plan?

Learn it on Day 12: How long will it really take?

Technique: Critical path

Question 14 of 52

Choose 1
Abram (Building Contractor Manager)
Conversion works: best 14 weeks, likely 18, worst 30.

What is the weighted estimate?

Learn it on Day 12: How long will it really take?

Technique: Three-point estimating

Question 15 of 52

Choose 1
Alonso (Expansion Director)
Our first estimate came from store 28.

Why update it?

Learn it on Day 14: What will it cost?

Technique: Analogous estimating

Question 16 of 52

Choose 1
Amalia (Heritage Officer)
Risk: heritage approval for the new shopfront takes three months.

Which response fits?

Learn it on Day 16: What could go wrong?

Technique: Risk responses

Question 17 of 52

Choose 1
Avery (Regional HR Manager)
Should we hire through an agency or do it ourselves?

How do you decide?

Learn it on Day 18: Buying what we need

Technique: Make or buy

Question 18 of 52

Choose 1
Abram (Building Contractor Manager)
Should our contract be fixed price?

What makes that fair here?

Learn it on Day 18: Buying what we need

Technique: Contract types

Question 19 of 52

Choose 1
Agneta (Store Manager)
Quality means everything brand new and top of the range.

What is quality here?

Learn it on Day 19: Good enough, and who hears what

Question 20 of 52

Choose 1
Alonso (Expansion Director)
The ribbon-cutting is fixed. Can we open a week earlier?

What do you do?

Learn it on Day 20: Signing off the plan

Technique: Schedule compression

Question 21 of 52

Choose 1
Alonso (Expansion Director)
Our store opening playbook has 40 steps written for new-build stores.

What do you do for a converted cinema?

Learn it on Day 8: How should we run it?

Technique: Tailoring the approach

Question 22 of 52

Choose 1
Agneta (Store Manager)
Store staff can't judge the checkout layout from drawings.

How do you test it?

Learn it on Day 11: From needs to tests

Technique: Prototyping and mock-ups

Question 23 of 52

Choose 1
Avery (Regional HR Manager)
The same five trainers are booked to train staff in three stores the same week.

What do you do?

Learn it on Day 15: Who's needed when?

Technique: Resource levelling

Question 24 of 52

Choose 1
Agneta (Store Manager)
Ideas for the store layout keep changing as we test them with shoppers.

How do you plan the work?

Learn it on Day 8: How should we run it?
Freshmart

Delivering

Inside the old cinema

Question 25 of 52

Choose 1
Abram (Building Contractor Manager)
Can we remove the old balcony supports now and check structural safety later?

What do you decide?

Learn it on Day 21: Breaking ground

Question 26 of 52

Choose 1
Avery (Regional HR Manager)
How do I hand the hiring to the store team clearly?

What goes in the work package?

Learn it on Day 21: Breaking ground

Technique: Work authorisation

Question 27 of 52

Choose 1
Avery (Regional HR Manager)
Only 50 of 80 hires so far, and opening is in 8 weeks.

What do you do?

Learn it on Day 23: Building the team

Technique: Risk responses

Question 28 of 52

Choose 1
Asif (Refrigeration Supplier Manager)
The freezers need a stronger floor. That's €35,000 extra.

What do you do?

Learn it on Day 25: When a supplier slips

Technique: Negotiation

Question 29 of 52

Choose 1
Agneta (Store Manager)
A food safety walk-through found the staff handwash sinks in the wrong place.

What happens?

Learn it on Day 26: Quality on site

Technique: Inspection and testing

Question 30 of 52

Choose 1
Agneta (Store Manager)
We have 90 snags. Where to start?

Which technique helps?

Learn it on Day 26: Quality on site

Technique: Pareto chart

Question 31 of 52

Choose 1
Aster (Neighbourhood Association)
A rumour says the store will be open 24 hours.

What do you do?

Learn it on Day 28: The neighbours are angry

Technique: Stakeholder communication plan

Question 32 of 52

Choose 1
Alonso (Expansion Director)
Let's announce the opening date before heritage approval comes through.

How do you respond?

Learn it on Day 28: The neighbours are angry

Technique: Saying no with reasons

Question 33 of 52

True or false
Abram (Building Contractor Manager)
The store manager asked my team directly to move the tills.

True or false: the contractor can make the change if the store manager asks.

Learn it on Day 30: A key person leaves

Question 34 of 52

Choose 1
Asif (Refrigeration Supplier Manager)
The refrigeration supplier has gone into administration two weeks before installation.

What do you do?

Learn it on Day 29: The supplier goes bust

Technique: Escalating impediments

Question 35 of 52

Choose 1
Agneta (Store Manager)
One of my new section managers seems lost and keeps asking for instructions.

How do you lead her?

Learn it on Day 24: Leading, not just managing

Technique: Situational leadership

Question 36 of 52

Choose 1
Avery (Regional HR Manager)
The 80 new staff come from very different backgrounds and jobs. Some have never worked in retail.

How do you prepare them?

Learn it on Day 31: Getting people ready
Freshmart

Keeping control

Six weeks to opening

Question 37 of 52

Choose 1
Alonso (Expansion Director)
Planned value €2.4M, earned value €2.2M, actual cost €2.3M.

What does this show?

Learn it on Day 32: Are we on track?

Technique: Earned value

Question 38 of 52

Choose 1
Alonso (Expansion Director)
Just send me a short update.

What goes in the status report?

Learn it on Day 32: Are we on track?

Technique: RAG status

Question 39 of 52

Choose 1
Agneta (Store Manager)
Can we add a click-and-collect area?

What happens?

Learn it on Day 33: The change request

Technique: Impact analysis

Question 40 of 52

Choose 1
Amalia (Heritage Officer)
Heritage approval is delayed four weeks. Opening day is at risk.

It's beyond your tolerance. What do you do?

Learn it on Day 34: Out of tolerance

Technique: Management by exception

Question 41 of 52

Choose 1
Asif (Refrigeration Supplier Manager)
We upgraded all fridges to a premium model at no extra cost.

What do you do?

Learn it on Day 36: Is it done?

Question 42 of 52

Choose 1
Agneta (Store Manager)
Can I accept the store building?

How?

Learn it on Day 36: Is it done?

Technique: Acceptance criteria and Given/When/Then

Question 43 of 52

Choose 1
Alonso (Expansion Director)
Is contingency enough for the last weeks?

What do you do?

Learn it on Day 38: The risk review

Technique: Reserve analysis

Question 44 of 52

Choose 2
Alonso (Expansion Director)
Before opening, the board meets.

Which two inputs help them decide?

Learn it on Day 40: Ready for the last stage?

Technique: Stage gate

Question 45 of 52

Choose 1
Alonso (Expansion Director)
Head office audited the project and found risks without owners.

What do you do?

Learn it on Day 37: Is the process working?

Technique: Blameless review

Freshmart

Closing

Ribbon, tills and the first week

Question 46 of 52

Choose 1
Agneta (Store Manager)
Shall we run a trial day with staff as customers?

Why?

Learn it on Day 41: Are we ready to open?

Technique: Dress rehearsal

Question 47 of 52

Choose 1
Alonso (Expansion Director)
Do we open on Saturday?

How do you decide?

Learn it on Day 41: Are we ready to open?

Technique: Go or no-go review

Question 48 of 52

Choose 1
Agneta (Store Manager)
Opening day: card payments fail on two tills.

Who handles it?

Learn it on Day 42: Opening day

Technique: Hypercare

Question 49 of 52

Choose 1
Abram (Building Contractor Manager)
Final invoice: €18,000 for unplanned weekend work.

What do you do?

Learn it on Day 43: Closing the contracts

Question 50 of 52

Choose 1
Alonso (Expansion Director)
Store 31 starts next year. What do they need from us?

What does the lessons report give them?

Learn it on Day 44: Letting the team go

Question 51 of 52

Choose 1
Agneta (Store Manager)
Month 6: weekly sales are €210,000, not €250,000.

How do you report it?

Learn it on Day 46: Was it worth it?

Technique: Benefits tracking

Question 52 of 52

Choose 1
Agneta (Store Manager)
After the ribbon is cut, who looks after the refrigeration, the tills and the building?

What do you plan?

Learn it on Day 42: Opening day