Estimating uncertain work with three numbers (best, most likely, worst case) and combining them into a more realistic figure.
Common practice 5 steps Used by Project Manager
What it is
Instead of one number, you ask for three: the best case, the most likely case and the worst case. A weighted average gives a more realistic estimate, and the spread shows the uncertainty.
When to use it
When an activity is uncertain or has never been done quite like this before.
Why it works
Single numbers hide risk and are usually optimistic. Asking for the worst case makes people think about what could go wrong, and the spread tells you which estimates deserve attention.
Do
Make sure the worst case is really bad, not “likely plus a bit”.
Add estimates for whole chains with care: the chance of everything going to plan is small.
Don't
Asking for three numbers but only using the most likely one.
Worst cases that are really just “likely plus a bit”.
Step by step
Pick the uncertain activitiesUse three-point estimates where it matters: long, new or risky work.
Ask the people who'll do the workGet best, most likely and worst cases. Ask what would have to happen for each.
14 weeks is a more honest plan than 13, and the wide range marks the building works as the activity to watch.
What it led to
The plan uses 14 weeks; the risk register gets an entry for building overruns.
Do it in a spreadsheet
PERT estimate
=(B2+4*B3+B4)/6
Spread
=(B4-B2)/6
Try it yourself: Equipment delivery: best 10, most likely 14, worst 20 weeks. PERT estimate?
(10 + 56 + 20) ÷ 6 = 14.3 weeks.
In the roles
How a Project Manager uses it
The building works: best 10 weeks, most likely 13, worst 22. (10 + 52 + 22) ÷ 6 = 14 weeks, and the 12-week spread marks the works as the main schedule risk.