Estimation · cheat sheet

Three-point estimating

Estimating uncertain work with three numbers (best, most likely, worst case) and combining them into a more realistic figure.

Common practice
5 steps
Used by Project Manager

What it is

Instead of one number, you ask for three: the best case, the most likely case and the worst case. A weighted average gives a more realistic estimate, and the spread shows the uncertainty.

When to use it

When an activity is uncertain or has never been done quite like this before.

Why it works

Single numbers hide risk and are usually optimistic. Asking for the worst case makes people think about what could go wrong, and the spread tells you which estimates deserve attention.

Do

  • Make sure the worst case is really bad, not “likely plus a bit”.
  • Add estimates for whole chains with care: the chance of everything going to plan is small.

Don't

  • Asking for three numbers but only using the most likely one.
  • Worst cases that are really just “likely plus a bit”.

Step by step

  1. Pick the uncertain activities Use three-point estimates where it matters: long, new or risky work.
  2. Ask the people who'll do the work Get best, most likely and worst cases. Ask what would have to happen for each.
  3. Calculate Weighted (beta) average: (best + 4 × likely + worst) ÷ 6. Simple (triangular) average: (best + likely + worst) ÷ 3.
  4. Look at the spread Worst minus best. A wide spread means a risk to watch and maybe to respond to.
  5. Use it in the plan Schedule with the weighted estimate, record the range, and add contingency for the risky chains.
Also called: PERT estimate, range estimatePrint the blank template ↗

Worked example

The situation. Migrating a customer database.

  1. Best case 4 weeks (clean data), most likely 6, worst 14 (lots of duplicates).
  2. Weighted: (4 + 24 + 14) ÷ 6 = 7 weeks.
  3. Spread of 10 weeks: data quality is checked in week 1 as an early warning.

The result. The plan said 7 weeks, with a check after week 1. Duplicates were found early and the migration took 8 weeks, without surprising anyone.

Three-point estimate sheet Print blank
ActivityBestMost likelyWorstWeighted (B+4L+W)÷6Spread (W−B)
Database migration4614710

Filled in for: Migrating a customer database.

ActivityBestMost likelyWorstWeighted (B+4L+W)÷6Spread (W−B)

Copy this structure, or print the blank version and fill it in by hand.

Before you use it: check these

CheckIf it fails
The three estimates come from people who know the workAsk them separately, then discuss differences
The worst case is truly bad, not just a little lateAsk what would make it go badly wrong

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

A three-point estimate

From Day 12: How long will it really take? of the Project Manager story

The contractor gives three durations for the building works, in weeks.

Step by step

  1. Weighted average (PERT)(best + 4 × most likely + worst) ÷ 6 = (10 + 52 + 22) ÷ 6= 14 weeks
  2. Spread(worst − best) ÷ 6 = 12 ÷ 6= 2 weeks
  3. Rough rangeabout 14 ± 2 × 2 weeks= 10 to 18 weeks
EstimateWeeks
Best case (optimistic)10
Most likely13
Worst case (pessimistic)22

How to read the result

14 weeks is a more honest plan than 13, and the wide range marks the building works as the activity to watch.

What it led to

The plan uses 14 weeks; the risk register gets an entry for building overruns.

Do it in a spreadsheet

PERT estimate=(B2+4*B3+B4)/6
Spread=(B4-B2)/6
Try it yourself: Equipment delivery: best 10, most likely 14, worst 20 weeks. PERT estimate?

(10 + 56 + 20) ÷ 6 = 14.3 weeks.

In the roles

How a Project Manager uses it

The building works: best 10 weeks, most likely 13, worst 22. (10 + 52 + 22) ÷ 6 = 14 weeks, and the 12-week spread marks the works as the main schedule risk.

Questions people ask

Which formula should I use?

The weighted one leans towards the most likely case and is common. The simple average is more cautious. Pick one and use it consistently.