The supplier goes bust
The furniture supplier goes into administration with half the order undelivered and a 30% deposit paid. Opening is eleven weeks away.
Stage goal: Build, buy, hire and keep everyone working together.
Team
Aya (Project Coordinator)
Stakeholders
Alder (Procurement Officer)
Documents today Risk register Issue log
How the day goes
- 09:00News from Alder
- 11:00Furniture options with Alder (Procurement)
- 15:00Issue log with Aya (Project Coordinator), then the board
Situation 1 of 3
09:00 · News from AlderAlder (Procurement Officer)
The furniture supplier has gone into administration. We paid a 30% deposit and only half was delivered.
What do you do first?
When a supplier fails, act on two tracks: protect what you're owed under the contract, and secure a replacement at once.
Situation 2 of 3
11:00 · Furniture options with Alder (Procurement)Alder (Procurement Officer)
A new supplier can deliver in nine weeks, for €18,000 more. Or we use standard furniture in six weeks.
How do you decide?
When plans break, lay out the options against the requirements, time, cost and risk, and choose openly.
Situation 3 of 3
15:00 · Issue log with Aya (Project Coordinator), then the boardAya (Project Coordinator)
Should this go in the risk register or somewhere else?
Where do issues go?
Issues (happening now) go in an issue log with owners and actions; risks (might happen) stay in the risk register.
Used here Issue log Risk register
Key concepts
The ideas behind today. Concept how the work is done, in our own words · Common practice widely used ways of working.
Concept
When a supplier fails
- Act on two tracks: protect what you're owed under the contract (deposits, bonds, ownership of goods), and secure a replacement at once.
Where you will meet this: Supplier insolvency · performance bonds
Concept
Issues and the issue log
- An issue is happening now; a risk might happen. Issues go in an issue log with impact, priority, owner, actions and status.
- Leaders review open issues regularly.
Where you will meet this: Issue log · issue register
Common practice
Options under pressure
- When plans break, compare options against requirements, time, cost and risk, and choose openly with the people who decide.
Explained in our own words. This helps you understand the concepts behind the certifications; it does not reproduce or replace any official guide. Sources
Day 29 complete
3 situations today.
Your responsibility todayHandling supplier failure
Technique you usedContract protections, replacement options, the issue log
Key points to remember
- When a supplier fails, act on two tracks: protect what you're owed under the contract, and secure a replacement at once.
- When plans break, lay out the options against the requirements, time, cost and risk, and choose openly.
- Issues (happening now) go in an issue log with owners and actions; risks (might happen) stay in the risk register.
Documents today Risk register Issue log