Contract types

The main ways to pay a supplier, which decide who carries the cost risk: fixed price, time and materials, or cost plus a fee.

Common practice
5 steps
Used by Project Manager

What it is

The main ways to pay a supplier, each putting cost risk in a different place: fixed price (supplier carries it), time and materials (buyer carries it), cost-reimbursable plus fee (shared, often with incentives).

When to use it

When planning what to buy, before the tender.

Variations

  • Fixed price with economic price adjustment for long contracts where material prices may change.
  • Target cost with shared savings buyer and supplier share any savings or overruns.

Why it works

Choosing the wrong type causes padded prices, endless claims or runaway costs. The right type fits how well the scope is known.

Do

  • Fixed price on vague scope isn't safe; it's expensive.

Don't

  • Fixed price on unclear scope: big buffers and endless claims.
  • Open time and materials with no cap.

Step by step

  1. Ask how clear the scope is Clear → fixed price; unclear → time and materials or cost-reimbursable.
  2. Ask who can best manage the risk Put the risk where it can be controlled.
  3. Add protections Caps on time and materials, milestones and acceptance on fixed price, incentives where useful.
  4. Define changes How changes are priced and approved.
  5. Write acceptance and payment terms Pay against accepted deliverables.
Also called: Fixed price, time and materials, cost-reimbursablePrint the blank template ↗

Worked example

The situation. A building conversion with one uncertain part.

  1. Main works: fixed price after a full survey.
  2. Investigations of an old basement: time and materials, capped at €30,000.

The result. The main price held; the basement work cost €18,000 within the cap.

Contract type decision Print blank
WorkScope clarityWho controls the riskContract typeProtec­tions

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

The building works are fixed price now that the survey defines them; the remaining investigation work is time and materials with a cap.

Questions people ask

Which is cheapest?

None by default; the cheapest is the one that fits the scope and risk.