Scope and scheduling · cheat sheetSchedule compression
Ways to shorten a schedule without cutting scope: add resources to critical work (crashing) or overlap activities (fast-tracking).
Common practice
6 steps
Used by Project Manager
What it is
Ways to shorten a schedule without cutting scope: crashing (adding resources to critical work) and fast-tracking (overlapping activities).
When to use it
When the end date must move earlier, or to recover a delay.
Why it works
When a date must move earlier or a delay must be recovered, these are the main options, each with a cost or a risk.
Do
- Shortening non-critical activities doesn't help the end date.
Don't
- Compressing activities that aren't critical.
- Fast-tracking so much that rework wipes out the gain.
Step by step
Find the critical path Only critical activities affect the end date.
Crashing Which critical activities can go faster with more people or equipment, and at what cost?
Fast-tracking Which can overlap, and what rework risk does that add?
Compare options Time saved, cost, risk.
Let the sponsor decide With the trade-offs clear.
Re-check the critical path A new one may appear.
Worked example
The situation. An opening must move two weeks earlier.
- Crash: a second crew on fit-out, €60,000, saves 2 weeks.
- Fast-track: start furniture install during painting, free, saves 1 week, risk of damage.
The result. The sponsor chose fast-tracking plus one week's later opening event.
| Activity (critical) | Option | Crash or fast-track | Time saved | Cost | Risk |
|---|
| | | | | |
| | | | | |
| | | | | |
| | | | | |
Copy this structure, or print the blank version and fill it in by hand.
Before you use it: check these
| Check | If it fails |
|---|
| The activity is on the critical path | Compressing work with float gains no time |
| The extra cost or rework risk is accepted by the sponsor | Show the cost per week gained and let the sponsor choose |
How to do it with real data
The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataWhat would an earlier opening cost?
From Day 20: Signing off the plan of the Project Manager story
Options to gain weeks on the critical path for an opening in month 6.
Step by step
- Crashing€120,000 ÷ 4 weeks= €30,000 a week
- Fast-trackingno direct cost; expected rework 0.25 × €60,000= €15,000 expected
- Only critical activitiescompressing anything with float gains nothing
| Option | Weeks gained | Extra cost (€) | Cost per week (€) | Risk |
|---|
| Second building crew (crashing) | 4 | 120000 | 30000 | Low |
| Overlap fit-out with building works (fast-tracking) | 3 | 0 | 0 | Rework: 25% chance of €60,000 |
| Both | 5 | 120000 | 24000 | Rework risk remains |
How to read the result
Weeks can be bought, at a price or with risk. Only work on the critical path is worth compressing.
What it led to
Atticus (Sponsor) keeps month 7 and holds a public “first look” event in month 6 instead.
Do it in a spreadsheet
Try it yourself: Why not compress hiring to open earlier?
Hiring has 5 weeks of float; it isn't on the critical path, so shortening it gains no time.
In the roles
How a Project Manager uses it
For a month 6 opening: a second building crew (≈ €120,000) or overlapping fit-out with works (more rework risk). Atticus (Sponsor) keeps month 7.
Questions people ask
Can I just ask people to work harder?
Not as a plan; it burns people out and rarely holds.