Scope and scheduling · cheat sheet

Schedule compression

Ways to shorten a schedule without cutting scope: add resources to critical work (crashing) or overlap activities (fast-tracking).

Common practice
6 steps
Used by Project Manager

What it is

Ways to shorten a schedule without cutting scope: crashing (adding resources to critical work) and fast-tracking (overlapping activities).

When to use it

When the end date must move earlier, or to recover a delay.

Why it works

When a date must move earlier or a delay must be recovered, these are the main options, each with a cost or a risk.

Do

  • Shortening non-critical activities doesn't help the end date.

Don't

  • Compressing activities that aren't critical.
  • Fast-tracking so much that rework wipes out the gain.

Step by step

  1. Find the critical path Only critical activities affect the end date.
  2. Crashing Which critical activities can go faster with more people or equipment, and at what cost?
  3. Fast-tracking Which can overlap, and what rework risk does that add?
  4. Compare options Time saved, cost, risk.
  5. Let the sponsor decide With the trade-offs clear.
  6. Re-check the critical path A new one may appear.
Also called: Crashing, fast-trackingPrint the blank template ↗

Worked example

The situation. An opening must move two weeks earlier.

  1. Crash: a second crew on fit-out, €60,000, saves 2 weeks.
  2. Fast-track: start furniture install during painting, free, saves 1 week, risk of damage.

The result. The sponsor chose fast-tracking plus one week's later opening event.

Compression options Print blank
Activity (critical)OptionCrash or fast-trackTime savedCostRisk

Copy this structure, or print the blank version and fill it in by hand.

Before you use it: check these

CheckIf it fails
The activity is on the critical pathCompressing work with float gains no time
The extra cost or rework risk is accepted by the sponsorShow the cost per week gained and let the sponsor choose

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

What would an earlier opening cost?

From Day 20: Signing off the plan of the Project Manager story

Options to gain weeks on the critical path for an opening in month 6.

Step by step

  1. Crashing€120,000 ÷ 4 weeks= €30,000 a week
  2. Fast-trackingno direct cost; expected rework 0.25 × €60,000= €15,000 expected
  3. Only critical activitiescompressing anything with float gains nothing
OptionWeeks gainedExtra cost (€)Cost per week (€)Risk
Second building crew (crashing)412000030000Low
Overlap fit-out with building works (fast-tracking)300Rework: 25% chance of €60,000
Both512000024000Rework risk remains

How to read the result

Weeks can be bought, at a price or with risk. Only work on the critical path is worth compressing.

What it led to

Atticus (Sponsor) keeps month 7 and holds a public “first look” event in month 6 instead.

Do it in a spreadsheet

Cost per week=C2/B2
Try it yourself: Why not compress hiring to open earlier?

Hiring has 5 weeks of float; it isn't on the critical path, so shortening it gains no time.

In the roles

How a Project Manager uses it

For a month 6 opening: a second building crew (≈ €120,000) or overlapping fit-out with works (more rework risk). Atticus (Sponsor) keeps month 7.

Questions people ask

Can I just ask people to work harder?

Not as a plan; it burns people out and rarely holds.