Problem-solving · cheat sheet Pareto chart A bar chart of problems grouped by cause, sorted from most to least frequent, showing the few causes behind most problems.
Common practice 5 steps Used by Project Manager, Process Improvement Specialist
What it is A bar chart of problems grouped by cause, sorted from most to least frequent, often with a line showing the cumulative percentage.
When to use it When there are many defects or complaints and you need to decide where to start.
Why it works It shows the few causes behind most problems, so you fix what matters most first.
Do Don't ignore a rare but severe problem just because its bar is short. Don't Grouping by symptom instead of cause. Ignoring a rare but severe problem because it's small on the chart. Step by step Collect problems Over a defined period.
Group by cause Not by symptom.
Count and sort Largest first.
Draw bars and the cumulative line Often 2 or 3 causes cover most problems.
Fix the top causes Then measure again.
Worked example The situation. An online shop's 200 complaints in a month.
Late delivery 90, wrong size 50, damaged 30, other 30. Late delivery and wrong size = 70%. The result. A new courier and a size guide cut complaints by more than half.
Cause Count Cumulative % Late delivery 90 45% Wrong size 50 70% Damaged 30 85% Other 30 100%
Filled in for: An online shop's 200 complaints in a month.
Cause Count % of total Cumulative %
Copy this structure, or print the blank version and fill it in by hand.
How to do it with real data The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataWhich waste costs the most time?
From Day 3: Eight kinds of waste of the Process Improvement Specialist story
Astrid (Data Analyst) counts the 40 observations by kind of waste and draws a Pareto chart.
Observations by kind of waste, largest first, with the cumulative share 0 5 10 15 20 0% 25% 50% 75% 100% Waiting: 14.0 14 Waiting Rework: 7.0 7 Rework Movement: 6.0 6 Movement Extra / processing: 5.0 5 Extra processing Excess / stock: 3.0 3 Excess stock Transport: 2.0 2 Transport Over- / production: 2.0 2 Over- production Unused / talent: 1.0 1 Unused talent 80%
Step by step Count each kind Tally the 40 observations by kind of waste Sort Largest count first Share of each count ÷ total, e.g. Waiting: 14 ÷ 40 = 35% Cumulative share add the shares as you go: 35% + 17.5% + 15% + 12.5% = 80% after four kinds Read the chart Where does the line cross 80%? = 4 of 8 kinds
Kind of waste Observations Share Cumulative share Waiting 14 35% 35% Rework and errors 7 17.5% 52.5% Movement 6 15% 67.5% Extra processing 5 12.5% 80% Excess stock 3 7.5% 87.5% Transport 2 5% 92.5% Overproduction 2 5% 97.5% Unused talent 1 2.5% 100%
How to read the result Half the kinds of waste (waiting, rework, movement and extra processing) account for 80% of what was seen. Waiting alone is more than a third.
What it led to Focus the first improvements on waiting and rework. Keep the small groups on the opportunity log rather than ignoring them.
Do it in a spreadsheet Sort largest first =SORT(A2:B9, 2, FALSE)Share =B2/SUM($B$2:$B$9)Cumulative share =SUM($B$2:B2)/SUM($B$2:$B$9)Chart Excel: Insert, Statistic chart, Pareto. Google Sheets: a combo chart (bars plus a line)
Try it yourself: If all waiting and rework were removed, what share of the observed waste would be left? 100% − 52.5% = 47.5%.
In the roles How a Project Manager uses itOf 47 small defects, door hardware and paint finish cause 70%. The door supplier sends a fitter and the painter changes products; most of the list disappears.
How a Process Improvement Specialist uses it40 gemba observations by kind of waste: waiting, rework, movement and extra processing make up 80%.
Questions people ask Is it always 80/20? No. It's a tendency, not a law.