Organisation and impediments · cheat sheet

Escalating impediments

Move a blocker to the people who can decide, with the impact made clear, quickly and openly.

Common practice
5 steps
Used by Scrum Master, Project Manager

What it is

An agreed route for problems a person or team can't solve themselves: who to go to, how quickly, and with what information.

When to use it

When the team can't remove an impediment on its own.

Why it works

Without a clear path, problems either sit unsolved or jump straight to the top. A good path gets decisions at the right level, fast.

Do

  • Escalating isn't failing; waiting too long is.

Don't

  • Escalating everything, so nobody listens.
  • Workarounds that hide the problem.

Step by step

  1. Define levels Team → project manager → sponsor or board.
  2. Set triggers Time (stuck for two days), size (beyond tolerance), type (safety, legal).
  3. Agree response times For example same day, two days.
  4. Escalate with options Problem, impact, options, recommendation.
  5. Record outcomes In the issue or decision log.
Also called: Escalation pathPrint the blank template ↗

Worked example

The situation. A delayed approval threatens a milestone.

  1. Team raises it to the project manager the same day.
  2. PM tries to resolve; after two days, escalates to the sponsor with options.

The result. The sponsor called the approver; approval came the next morning.

Escalation route Print blank
LevelWhoTriggerResponse timeWhat to bring

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Scrum Master uses it

IT and finance pass the map licence back and forth. Aaron (Scrum Master) gets both in one meeting with Anna (Product Owner), with the impact clear: tracking stops. Approved the same day.

How a Project Manager uses it

With the project board set up, an issue outside tolerances goes from the team to Annelise (Project Manager) the same day and from Annelise to Atticus (Sponsor) within two days, always with options.

Questions people ask

How do I escalate without blaming?

Focus on the impact and the decision needed, not on who caused it.