Cloud migration51 questions5 phases

Cloudshift: a Project Manager case study

An online retailer runs 120 applications in its own data centre. The building's lease and the hardware support both end in 14 months. The board wants everything moved to the cloud without disrupting the busiest shopping season. You run the project.

What this case study tests
Blackout windowsSecurity as a stakeholderCapped contractsRunning-cost benefits

You're the Project Manager. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Stakeholders
Alicia (Project Manager)You
Ambrose (Chief Technology Officer)Sponsor
Aditi (Head of E-commerce)Senior user: the online shop
Arthur (Cloud Architect)Designs the target setup
Ayaan (Security Officer)Data protection and security
Amelie (Cloud Partner Delivery Manager)External migration partner
Axl (Operations Lead)Runs the systems day to day
Arwen (Finance Business Partner)Cloud costs
Cloudshift

Starting up

A data centre with a closing date

Question 1 of 51

Choose 1
Ambrose (Chief Technology Officer)
Move everything to the cloud. Lift and shift. Simple.

What do you do first?

Learn it on Day 1: A request lands on your desk

Question 2 of 51

Choose 2
Arwen (Finance Business Partner)
Options: move as is, redesign for the cloud, replace with SaaS products, or renew the lease.

Which two statements are true?

Learn it on Day 3: Is it worth it?

Question 3 of 51

True or false
Ambrose (Chief Technology Officer)
Approved: €3M, plus €300,000 I hold for surprises.

True or false: the project plans to use the €300,000.

Learn it on Day 4: The decision

Question 4 of 51

Choose 1
Ambrose (Chief Technology Officer)
Write me a charter. Short.

Which item must it include?

Learn it on Day 5: Who's in charge here?

Question 5 of 51

Choose 1
Ayaan (Security Officer)
Nobody involved security. We have customer card data.

How do you treat security?

Learn it on Day 6: Everyone who matters

Technique: Stakeholder map (power and interest)

Question 6 of 51

Choose 1
Axl (Operations Lead)
The operations team fears they'll lose their jobs.

What do you do?

Learn it on Day 6: Everyone who matters

Technique: Active listening

Question 7 of 51

Choose 1
Amelie (Cloud Partner Delivery Manager)
Who decides which applications move first: us or your architect?

What settles it?

Learn it on Day 7: Who does what

Technique: RACI

Question 8 of 51

Choose 1
Arthur (Cloud Architect)
At the kick-off we learned 15 applications have no documentation at all.

What happens to the assumption that systems are documented?

Learn it on Day 9: The kick-off

Technique: Risk identification

Question 9 of 51

Choose 1
Ambrose (Chief Technology Officer)
Do we have the skills and budget to move 120 applications in 14 months?

What do you check?

Learn it on Day 2: Not the only proposal

Technique: PESTLE analysis

Question 10 of 51

Choose 1
Arwen (Finance Business Partner)
Cloud costs are monthly and grow with use. The data centre was one big upfront cost. How do we compare them?

What do you use?

Learn it on Day 3: Is it worth it?
Cloudshift

Planning

120 applications in 14 months

Question 11 of 51

Choose 1
Ambrose (Chief Technology Officer)
The group's project office says the migration is part of the digital programme. And another project's new sign-in platform must be ready before wave 3.

How do you handle this?

Learn it on Day 20: Signing off the plan

Question 12 of 51

Choose 1
Aditi (Head of E-commerce)
While we're moving, can we also redesign the shop's checkout?

How do you handle it?

Learn it on Day 10: What exactly are we building?

Technique: MoSCoW

Question 13 of 51

Choose 1
Arthur (Cloud Architect)
How do we organise 120 applications into plannable work?

What helps most?

Learn it on Day 10: What exactly are we building?

Technique: Work breakdown (decomposition)

Question 14 of 51

Choose 1
Aditi (Head of E-commerce)
No changes to the shop in November and December.

What is this for the schedule?

Learn it on Day 12: How long will it really take?

Technique: Critical path

Question 15 of 51

Choose 1
Arwen (Finance Business Partner)
Estimates per wave add up to €2.75M.

What kind of estimate is this?

Learn it on Day 14: What will it cost?

Technique: Bottom-up estimating

Question 16 of 51

Choose 1
Ayaan (Security Officer)
Risk: customer data exposed during transfer.

Which response fits?

Learn it on Day 16: What could go wrong?

Technique: Risk responses

Question 17 of 51

Choose 1
Arwen (Finance Business Partner)
If we commit to three years, the cloud provider offers 30% off.

What is this?

Learn it on Day 16: What could go wrong?

Question 18 of 51

Choose 1
Amelie (Cloud Partner Delivery Manager)
Should our contract be fixed price?

What's a good structure?

Learn it on Day 18: Buying what we need

Technique: Contract types

Question 19 of 51

Choose 1
Aditi (Head of E-commerce)
How do we know a migrated application is good enough?

What does quality mean here?

Learn it on Day 19: Good enough, and who hears what

Technique: Acceptance criteria and Given/When/Then

Question 20 of 51

Choose 1
Ambrose (Chief Technology Officer)
Can we finish two months earlier?

How do you respond?

Learn it on Day 20: Signing off the plan

Technique: Schedule compression

Question 21 of 51

Choose 1
Ayaan (Security Officer)
Customer data must stay in our region by law.

Where does this go?

Learn it on Day 13: Rules we must follow

Question 22 of 51

Choose 1
Arwen (Finance Business Partner)
If we skip the load test (€30,000), there's a 20% chance of a €400,000 outage at peak.

Is the test worth it?

Learn it on Day 17: Putting numbers on risk

Technique: Expected value and decision trees

Question 23 of 51

Choose 1
Aditi (Head of E-commerce)
The online shop must stay fast during the move. That's my only requirement.

How do you capture it?

Learn it on Day 11: From needs to tests

Question 24 of 51

Choose 1
Ambrose (Chief Technology Officer)
Some applications are simple to move as they are; others need redesigning for the cloud.

What approach do you use?

Learn it on Day 8: How should we run it?
Cloudshift

Delivering

Wave after wave

Question 25 of 51

Choose 1
Amelie (Cloud Partner Delivery Manager)
Can we skip the backup test for this wave? We're behind.

What do you decide?

Learn it on Day 21: Breaking ground

Question 26 of 51

Choose 1
Axl (Operations Lead)
My team doesn't know which nights they'll be needed for cutovers.

How do you fix it?

Learn it on Day 21: Breaking ground

Technique: Dependency board

Question 27 of 51

Choose 1
Axl (Operations Lead)
My team is exhausted from night cutovers.

What do you do?

Learn it on Day 23: Building the team

Technique: One-on-ones

Question 28 of 51

Choose 1
Amelie (Cloud Partner Delivery Manager)
The undocumented systems took twice as long. We need €90,000 more.

What do you do?

Learn it on Day 25: When a supplier slips

Technique: Negotiation

Question 29 of 51

Choose 1
Aditi (Head of E-commerce)
After wave 3, the product search is 40% slower.

What happens?

Learn it on Day 26: Quality on site

Technique: Inspection and testing

Question 30 of 51

Choose 1
Arthur (Cloud Architect)
We keep getting the same kind of failure in each wave.

What do you do?

Learn it on Day 26: Quality on site

Technique: Fishbone diagram

Question 31 of 51

Choose 1
Aditi (Head of E-commerce)
Customers posted that the shop was down for an hour.

What do you do?

Learn it on Day 28: The neighbours are angry

Technique: Stakeholder communication plan

Question 32 of 51

Choose 1
Arthur (Cloud Architect)
I'm moving to another company in a month.

What do you do?

Learn it on Day 30: A key person leaves

Technique: Knowledge transfer

Question 33 of 51

True or false
Aditi (Head of E-commerce)
Can't the partner just add a feature for us while they're in there?

True or false: it's fine if the partner agrees.

Learn it on Day 30: A key person leaves

Question 34 of 51

Choose 1
Amelie (Cloud Partner Delivery Manager)
Our migration team works from two countries. Handovers between them keep failing.

What helps?

Learn it on Day 22: Working with an agile supplier

Technique: Working agreements

Question 35 of 51

Choose 1
Axl (Operations Lead)
My operations team has run hardware for 15 years. The cloud feels foreign, and some worry about their jobs.

How do you help?

Learn it on Day 31: Getting people ready
Cloudshift

Keeping control

Before the shopping season

Question 36 of 51

Choose 2
Arwen (Finance Business Partner)
Planned value €1.5M, earned value €1.2M, actual cost €1.4M.

Which two statements are true?

Learn it on Day 32: Are we on track?

Technique: Earned value

Question 37 of 51

Choose 1
Amelie (Cloud Partner Delivery Manager)
Let's show wave 5 as green; the issues are minor.

What do you report?

Learn it on Day 32: Are we on track?

Technique: RAG status

Question 38 of 51

Choose 1
Ayaan (Security Officer)
New regulation: logs must be kept for 2 years, not 1.

What happens?

Learn it on Day 33: The change request

Technique: Impact analysis

Question 39 of 51

Choose 1
Arthur (Cloud Architect)
The payment system can't move before the blackout. It slips to January.

That's beyond your tolerance. What do you do?

Learn it on Day 34: Out of tolerance

Technique: Management by exception

Question 40 of 51

Choose 1
Arwen (Finance Business Partner)
Cloud running costs are 25% above the business case.

What do you do?

Learn it on Day 34: Out of tolerance

Question 41 of 51

Choose 1
Aditi (Head of E-commerce)
Can I sign off the shop's migration?

How?

Learn it on Day 36: Is it done?

Technique: Acceptance criteria and Given/When/Then

Question 42 of 51

Choose 1
Arwen (Finance Business Partner)
How much contingency is left?

What is reserve analysis?

Learn it on Day 38: The risk review

Technique: Reserve analysis

Question 43 of 51

Choose 1
Arwen (Finance Business Partner)
The board cuts €250,000 from the budget.

How do you respond?

Learn it on Day 35: The budget is cut

Technique: MoSCoW

Question 44 of 51

Choose 1
Arthur (Cloud Architect)
Two different versions of the network design are in use.

What do you set up?

Learn it on Day 37: Is the process working?

Technique: Version control

Cloudshift

Closing

Switching off the data centre

Question 45 of 51

Choose 1
Axl (Operations Lead)
Should we rehearse switching off the data centre?

Why?

Learn it on Day 41: Are we ready to open?

Technique: Dress rehearsal

Question 46 of 51

Choose 1
Ambrose (Chief Technology Officer)
Do we switch off for good this weekend?

How do you decide?

Learn it on Day 41: Are we ready to open?

Technique: Go or no-go review

Question 47 of 51

Choose 1
Axl (Operations Lead)
When does operations fully own the cloud setup?

What does handover include?

Learn it on Day 42: Opening day

Technique: Hypercare

Question 48 of 51

Choose 1
Amelie (Cloud Partner Delivery Manager)
Can we close our contract?

What must happen?

Learn it on Day 43: Closing the contracts

Technique: Procurement review

Question 49 of 51

Choose 1
Ambrose (Chief Technology Officer)
What should the next migration learn from us?

What does the lessons report include?

Learn it on Day 44: Letting the team go

Question 50 of 51

Choose 1
Ambrose (Chief Technology Officer)
Can we just send an email that the project is done?

What does formal closure include?

Learn it on Day 44: Letting the team go

Question 51 of 51

Choose 1
Arwen (Finance Business Partner)
A year later, running costs are 5% below the old data centre, not 20%.

How do you report it?

Learn it on Day 46: Was it worth it?

Technique: Benefits tracking