Bottom-up estimating

Estimating each small piece of work separately and adding them up. Slower, but more accurate.

Common practice
6 steps
Used by Project Manager

What it is

Estimating each small piece of work separately and adding them up. It needs a work breakdown and is slower, but more accurate.

When to use it

Once the work is broken down (a WBS exists) and quotes or expert input are available.

Why it works

Small pieces are easier to estimate well, and the people doing the work can estimate their own parts.

Do

  • Don't let each estimator pad silently; padding hidden everywhere adds up to a lot.

Don't

  • Every estimator adding their own hidden buffer.
  • Forgetting management, testing or handover work.

Step by step

  1. Start from the work breakdown Each lowest-level work package is estimated.
  2. Estimate with the people doing the work Use quotes, rates and past data.
  3. Record assumptions What each estimate includes and assumes (the basis of estimate).
  4. Add up by branch Then the whole project.
  5. Add contingency visibly For identified risks, as a separate line, not hidden in each estimate.
  6. Compare with the top-down figure Explain any big difference before anyone decides.
Also called: Detailed estimatePrint the blank template ↗

Worked example

The situation. An office refurbishment.

  1. Flooring €42,000 (quote), lighting €18,000, furniture €65,000, IT €30,000, moving €8,000, project management €12,000.
  2. Total €175,000; contingency €15,000 for asbestos risk.

The result. The sponsor saw exactly where the money goes, and what the contingency is for.

Bottom-up estimate sheet Print blank
Work packageEstimateBasis
Flooring42,000Quote
Lighting18,000Quote
Furniture65,000Catalogue prices
IT30,000Past project
Moving8,000Quote
Project management12,000Days × rate

Filled in for: An office refurbishment.

CodeWork packageEstimateBasis (quote, rate, history)Assum­ptions

Copy this structure, or print the blank version and fill it in by hand.

How to do it with real data

The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.

Worked example with real data

From bottom-up estimate to total funding

From Day 14: What will it cost? of the Project Manager story

Each part of the work breakdown is estimated from quotes and the survey (€ thousands).

Bottom-up estimate by WBS item, € thousands01,0002,0003,0004,000Building: 3,0003,000BuildingEquipment: 650650EquipmentBooking: 200200BookingPeople: 120120PeopleLicence: 3030LicencePM: 5050PM

Step by step

  1. Add the estimates3,000 + 650 + 200 + 120 + 30 + 50= €4,050k
  2. Contingency for known risksheld by the project= + €150k
  3. Cost baseline4,050 + 150= €4,200k
  4. Management reserve for unknown risksheld by the sponsor= + €300k
  5. Total funding4,200 + 300= €4,500k
WBSItemEstimate (€k)
1Building3000
2Equipment650
3Booking system200
4People120
5Licence and opening30
6Project management50

How to read the result

The work fits the €4.2M approved in the business case, with €150k set aside for the risks on the register and €300k with the sponsor for the unexpected.

What it led to

The €4.2M becomes the cost baseline; contingency use is reported monthly.

Do it in a spreadsheet

Total=SUM(C2:C7)
Baseline=C8+150
Funding=C9+300
Try it yourself: If equipment quotes rose 15%, how much contingency would be left?

650 × 0.15 = €97.5k used; €150k − €97.5k = €52.5k left.

In the roles

How a Project Manager uses it

Bottom-up, the clinic comes to €4.05M. The €0.15M difference from €4.2M becomes visible contingency for the identified risks.

Questions people ask

Is it always better than top-down?

More accurate, but only once the work is known well enough to break down.