Estimation · cheat sheet Bottom-up estimating Estimating each small piece of work separately and adding them up. Slower, but more accurate.
Common practice 6 steps Used by Project Manager
What it is Estimating each small piece of work separately and adding them up. It needs a work breakdown and is slower, but more accurate.
When to use it Once the work is broken down (a WBS exists) and quotes or expert input are available.
Why it works Small pieces are easier to estimate well, and the people doing the work can estimate their own parts.
Do Don't let each estimator pad silently; padding hidden everywhere adds up to a lot. Don't Every estimator adding their own hidden buffer. Forgetting management, testing or handover work. Step by step Start from the work breakdown Each lowest-level work package is estimated.
Estimate with the people doing the work Use quotes, rates and past data.
Record assumptions What each estimate includes and assumes (the basis of estimate).
Add up by branch Then the whole project.
Add contingency visibly For identified risks, as a separate line, not hidden in each estimate.
Compare with the top-down figure Explain any big difference before anyone decides.
What the letters mean
IT Information technology
WBS Work breakdown structure
÷ × Divided by, multiplied by
€M Millions of euros (€4.2M = €4,200,000) Worked example The situation. An office refurbishment.
Flooring €42,000 (quote), lighting €18,000, furniture €65,000, IT €30,000, moving €8,000, project management €12,000. Total €175,000; contingency €15,000 for asbestos risk. The result. The sponsor saw exactly where the money goes, and what the contingency is for.
Work package Estimate Basis Flooring 42,000 Quote Lighting 18,000 Quote Furniture 65,000 Catalogue prices IT 30,000 Past project Moving 8,000 Quote Project management 12,000 Days × rate
Filled in for: An office refurbishment.
Code Work package Estimate Basis (quote, rate, history) Assumptions
Copy this structure, or print the blank version and fill it in by hand.
How to do it with real data The full calculation, as it happens in the story: the data, every step, how to read the result, and the spreadsheet functions to do it yourself.
Worked example with real dataFrom bottom-up estimate to total funding
From Day 14: What will it cost? of the Project Manager story
Each part of the work breakdown is estimated from quotes and the survey (€ thousands).
Bottom-up estimate by WBS item, € thousands 0 1,000 2,000 3,000 4,000 Building: 3,000 3,000 Building Equipment: 650 650 Equipment Booking: 200 200 Booking People: 120 120 People Licence: 30 30 Licence PM: 50 50 PM
Step by step Add the estimates 3,000 + 650 + 200 + 120 + 30 + 50 = €4,050k Contingency for known risks held by the project = + €150k Cost baseline 4,050 + 150 = €4,200k Management reserve for unknown risks held by the sponsor = + €300k Total funding 4,200 + 300 = €4,500k
WBS Item Estimate (€k) 1 Building 3000 2 Equipment 650 3 Booking system 200 4 People 120 5 Licence and opening 30 6 Project management 50
How to read the result The work fits the €4.2M approved in the business case, with €150k set aside for the risks on the register and €300k with the sponsor for the unexpected.
What it led to The €4.2M becomes the cost baseline; contingency use is reported monthly.
Do it in a spreadsheet Total =SUM(C2:C7)Baseline =C8+150Funding =C9+300
Try it yourself: If equipment quotes rose 15%, how much contingency would be left? 650 × 0.15 = €97.5k used; €150k − €97.5k = €52.5k left.
In the roles How a Project Manager uses itBottom-up, the clinic comes to €4.05M. The €0.15M difference from €4.2M becomes visible contingency for the identified risks.
Questions people ask Is it always better than top-down? More accurate, but only once the work is known well enough to break down.